《ASTM C1645 C1645M-2009 Standard Test Method for Freeze-thaw and De-icing Salt Durability of Solid Concrete Interlocking Paving Units《固体混凝土联锁铺砌石块的解冻和除冰盐耐用性标准试验方法》.pdf》由会员分享,可在线阅读,更多相关《ASTM C1645 C1645M-2009 Standard Test Method for Freeze-thaw and De-icing Salt Durability of Solid Concrete Interlocking Paving Units《固体混凝土联锁铺砌石块的解冻和除冰盐耐用性标准试验方法》.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: C 1645/C 1645M 09Standard Test Method forFreeze-thaw and De-icing Salt Durability of Solid ConcreteInterlocking Paving Units1This standard is issued under the fixed designation C 1645/C 1645M; the number immediately following the designation indicates theyear of original adoption or, in
2、 the case of revision, the year of last revision. A number in parentheses indicates the year of lastreapproval. A superscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope*1.1 This test method evaluates the resistance to freezing andthawing of solid interloc
3、king concrete paving units conformingto the dimensional requirements of Specification C 936/C 936M. Units are tested in a test solution that is either tapwater or 3 % saline solution, depending on the intended use ofthe units in actual service.1.2 The values stated in either SI units or inch-pound u
4、nitsare to be regarded separately as standard. The values stated ineach system may not be exact equivalents; therefore, eachsystem shall be used independently of the other. Combiningvalues from the two systems may result in non-conformancewith the standard.1.3 This standard does not purport to addre
5、ss all of thesafety concerns, in any, associated with its use. It is theresponsibility of the use of this standard to establish appropri-ate safety and health practices and determine the applicabilityof regulatory limitation prior to use.2. Referenced Documents2.1 ASTM Standards:2C 936/C 936M Specif
6、ication for Solid Concrete Interlock-ing Paving Units3. Significance and Use3.1 This test method is intended to determine the effects offreezing and thawing on units conforming to the dimensionalrequirements of Specification C 936/C 936M while immersedin a test solution. Other types of segmental con
7、crete pavingunits that do not conform to the dimensional requirements ofSpecification C 936/C 936M may be tested using this testmethod.3.2 The results from this test method are not intended toprovide a quantitative measure of the length of service fromconcrete paving units conforming to the dimensio
8、nal require-ments of Specification C 936/C 936M.4. Apparatus4.1 Freezing-and-Thawing ApparatusThe freezing appa-ratus shall consist of suitable cabinet or cold room withcontrols to reach and maintain within1hofintroduction ofspecimens an air temperature of 5 6 3C 23 6 5F at alllocations within the c
9、hamber regardless of the number ofspecimens in the chamber. The thawing chamber shall maintaina controlled air temperature. This temperature shall never begreater than + 30C 86F.4.2 BalanceA balance capable of weighing 500 g with anaccuracy of 6 0.1 g shall be used for measuring the mass of thefine
10、spalled material.4.3 Drying OvenThe drying oven shall be vented andcapable of being maintained at 100 to 115C 212 to 239F.4.4 Specimen ContainerThe specimen container shall bemade of non-corroding flexible material and have dimensionsthat allow complete submersion of the specimen in the testsolution
11、. The size of the container shall be less than or equal tothree times the volume of the unit that is being tested. Thecontainer shall prevent evaporation of the test solution.5. Sampling5.1 Selection of Test SpecimensSelect whole units repre-sentative of the lot from which they are selected. The uni
12、tsshall be free from visible cracks, chipped edges, and structuraldefects.5.2 Number of Test SpecimensSample according to therequirements of Specification C 936/C 936M.5.3 IdentificationMark each test specimen so that it isidentifiable at any time.6. Preparation of Test Specimens6.1 Curing and Condi
13、tioningWhen possible, specimensshall be full-sized units. When the units cannot be testedfull-size due to specimen configuration or lack of suitablespecimen containers, obtain a specimen by saw-cutting afull-height coupon with a surface area of at least 1901This test method is under the jurisdiction
14、 of ASTM Committee C27 on PrecastConcrete Products and is the direct responsibility of Subcommittee C27.20 onArchitectural and Structural Products.Current edition approved on July 15, 2009. Published July 2009. Originallyapproved in 2006. Last previous edition approved in 2006 as C 1645 06.2For refe
15、renced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.1*A Summary of Changes section appears at the end of this standard.Cop
16、yright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.cm229.5 in.2. Test specimens shall be a minimum of 28 daysold before freeze-thaw cycling begins. After sampling, all testspecimens shall be cured for 14 days in a moist chamber(cabinet or r
17、oom) at an air temperature of 23 6 2C 73 6 4Fand a relative humidity of at least 90 % or submerged in asaturated lime solution maintained at 23 6 2C 73 6 4F.Moist curing shall be followed by air curing for a minimum of14 days at 24 6 8C 75 6 15F at a maximum 80 % relativehumidity. The curing and con
18、ditioning of the test specimensshall be waived at the option of the manufacturer of the pavers.When curing is waived, allow the specimens to air cure for aminimum of 48 h at 24 6 8C 75 6 15F at a maximum80 % relative humidity.6.1.1 Before testing begins, the specimens shall be brushedclean with a st
19、iff bristled brush and all loose burrs and edgeshards shall be removed with a carborundum stone.7. Procedure7.1 Freezing and Thawing CyclesOne freeze-thaw cycleshall be completed every 24 h. The cycle shall consist of 16 61 h of freezing followed by 8 6 1 h of thawing. The specimensshall be subjecte
20、d to continuous cycles. If for reasons beyondthe operators control, a freezing period cannot commence atthe specified time, the specimens shall remain in a thawedcondition until conditions are suitable for resumption of the testbut not longer than 96 h. The specimen temperature shallconform to 5 6 3
21、C 23 6 5F for the last 7 to 12 h of thefreezing cycle and a minimum of +5 C 40F for the last 1 hof the thawing cycle. The temperature shall be recorded at leastevery 15 min in the smallest and largest specimen (by weight)within the apparatus with a temperature probe that is insulatedfrom cabinet air
22、 and rests against, below, or inside a specimen.7.2 Specimen ContainmentImmediately followingcompletion of the conditioning, each specimen shall be cen-tered with the wearing surface facing upwards in individualcontainers. The supported bottom surface of the specimensshall rest on solid, noncorrosiv
23、e, nonabsorptive (for example,glass, stainless steel, ceramic, plastic, etc.) spacers approxi-mately 5 mm 0.2 in. high to ensure exposure of at least 95 %of the bottom surface to the test solution. A minimum of 5 mm0.2 in. clearance shall be provided between the specimen andthe container in all dire
24、ctions.7.3 Test SolutionThe test solution shall be tap water orsaline as requested by the client. If the test solution is saline,containers shall be filled with 3 6 0.1 % (by weight) NaClsolution. The test solution (tap water or saline) shall have atemperature of 24 6 8C 75 6 15F. The level of the t
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMC1645C1645M2009STANDARDTESTMETHODFORFREEZETHAWANDDEICINGSALTDURABILITYOFSOLIDCONCRETEINTERLOCKINGPAVINGUNITS

链接地址:http://www.mydoc123.com/p-465393.html