ASTM C1618-2005 Standard Test Method for Concrete Sanitary Sewer Pipe by Negative (Vacuum) or Positive Air Pressure《使用负气压(真空)或正气压的混凝土排污管的标准试验方法》.pdf
《ASTM C1618-2005 Standard Test Method for Concrete Sanitary Sewer Pipe by Negative (Vacuum) or Positive Air Pressure《使用负气压(真空)或正气压的混凝土排污管的标准试验方法》.pdf》由会员分享,可在线阅读,更多相关《ASTM C1618-2005 Standard Test Method for Concrete Sanitary Sewer Pipe by Negative (Vacuum) or Positive Air Pressure《使用负气压(真空)或正气压的混凝土排污管的标准试验方法》.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: C 1618 05Standard Test Method forConcrete Sanitary Sewer Pipe by Negative (Vacuum) orPositive Air Pressure1This standard is issued under the fixed designation C 1618; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the
2、 year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.1. Scope1.1 This test method covers procedures for testing of precastconcrete pipe sections, prior to delivery, where ma
3、ximum fieldleakage rates are specified.1.2 Tests described in this standard are intended to be usedat the point of manufacture of the concrete pipe and are notintended for testing installed pipe (for field tests see PracticesC 924, C 969, and C 1214). The user of this specification isadvised that in
4、dividual or multiple pipe sections may be testedfor the purpose of testing the pipe barrel and additionally thejoints in straight alignment when multiple pipe sections aretested.1.3 The two leakage rates shown, which were used incalculating the test times, were chosen based on two generallyaccepted
5、field air and vacuum test criteria. Test times are basedon leakage rates and therefore are proportional only to the pipediameter and are constant for any length of test pipe orpipeline.1.4 The values stated in inch-pound units are to be regardedas standard. No other units of measurement are included
6、 in thisstandard.NOTE 1The availability of this test procedure for concrete pipe variesfrom location to location. Check with local supplier(s) for availability andrecommendations.1.5 This standard does not purport to address all the safetyconcerns, if any, associated with its use. It is the responsi
7、bilityof the user of this standard to establish the appropriate safetyand health practices and to determine the applicability ofregulatory limitations prior to its use. See Section 6 for specificsafety precautions.2. Referenced Documents2.1 ASTM Standards:2C 822 Terminology Relating to Concrete Pipe
8、 and RelatedPracticeC 924 Practice for Testing Concrete Pipe Sewer Lines byLow-Pressure Air Test MethodC 969 Practice for Infiltration and Exfiltration AcceptanceTesting of Installed Precast Concrete Pipe Sewer LinesC 1214 Practice for Testing Concrete Pipe Sewer Lines byNegative Air Pressure (Vacuu
9、m) Test Method3. Terminology3.1 Definitions: For definitions of terms related to precastconcrete pipe, see Terminology C 822.4. Summary of Test Method4.1 The pipe to be tested shall be sealed at the outer endswith suitable airtight bulkheads. The manufacturer shall chooseto use either low-pressure a
10、ir or negative pressure air (vacuum)test methods to evaluate the condition of the pipe beforedelivery. The change in the internal pressure during a specifiedtime is used to determine the acceptability of the pipe.5. Significance and Use5.1 This is a quality control test performed at the manufac-turi
11、ng plant to establish that the finished, shippable pipe meetsthe leakage limits stated in the specifications.6. Safety Precautions6.1 The user of this specification is advised of the following:6.1.1 This test may be dangerous if a pipe is not preparedproperly and proper procedures are not followed.6
12、.1.2 No one should be allowed near the ends of the pipe ortest bulkheads during the test.7. Apparatus7.1 For positive air pressure test, one bulkhead shall includea remote controlled valve that will release the internal testpressure.7.2 For the low-pressure air test, tie rods or an external testfram
13、e that is designed to resist the force caused by internal airpressure shall be used to restrain the bulkheads. The low-pressure air test assembly shall be protected by a relief valve1This test method is under the jurisdiction of ASTM Committee C13 onConcrete Pipe and is the direct responsibility of
14、Subcommittee C13.09 on Methodsof Test.Current edition approved May 1, 2005. Published June 2005.2For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Docume
15、nt Summary page onthe ASTM website.1Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.set to release at a pressure no greater than 6 psi. The bulkheadsused for negative pressure air tests do not require externalrestraints.7.3 The pressu
16、re or vacuum pumps shall have adequatecapacity to obtain the required test pressure.7.4 The test pressure shall be measured with a gage ormanometer that is precise enough to measure the increments ofpressure change specified by this standard.7.5 The pressure measuring devices shall be located in asa
17、fe area where they can be observed without danger to testpersonnel.8. Preparation of the Pipe8.1 Allow the test pipe to cool to ambient air temperature.NOTE 2A wetted pipe is desirable and will produce more consistenttest results. Air may pass through the walls of dry pipe.8.2 The pipe joint shall b
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMC16182005STANDARDTESTMETHODFORCONCRETESANITARYSEWERPIPEBYNEGATIVEVACUUMORPOSITIVEAIRPRESSURE 使用 气压

链接地址:http://www.mydoc123.com/p-465314.html