ASTM C1479M-2007a Standard Practice for Installation of Precast Concrete Sewer Storm Drain and Culvert Pipe Using Standard Installations (Metric)《使用标准设备(米制的)安装预制混凝土污水管、雨水管和排水管的标准实施.pdf
《ASTM C1479M-2007a Standard Practice for Installation of Precast Concrete Sewer Storm Drain and Culvert Pipe Using Standard Installations (Metric)《使用标准设备(米制的)安装预制混凝土污水管、雨水管和排水管的标准实施.pdf》由会员分享,可在线阅读,更多相关《ASTM C1479M-2007a Standard Practice for Installation of Precast Concrete Sewer Storm Drain and Culvert Pipe Using Standard Installations (Metric)《使用标准设备(米制的)安装预制混凝土污水管、雨水管和排水管的标准实施.pdf(9页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: C 1479M 07aStandard Practice forInstallation of Precast Concrete Sewer, Storm Drain, andCulvert Pipe Using Standard Installations (Metric)1This standard is issued under the fixed designation C 1479M; the number immediately following the designation indicates the year oforiginal adoption
2、 or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers the installation of precast concretepipe intended to b
3、e used for the conveyance of sewage,industrial wastes, and storm water, and for the construction ofculverts.1.2 This specification is the metric counterpart of Specifi-cation C 1479.1.3 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theres
4、ponsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2C 822 Terminology Relating to Concrete Pipe and RelatedProductsC 1417 Specification for Ma
5、nufacture of Reinforced Con-crete Sewer, Storm Drain, and Culvert Pipe for DirectDesignD 698 Test Methods for Laboratory Compaction Character-istics of Soil Using Standard Effort (12 400 ft-lbf/ft3(600kN-m/m3)D 1557 Test Methods for Laboratory Compaction Charac-teristics of Soil Using Modified Effor
6、t (56,000 ft-lbf/ft3(2,700 kN-m/m3)D 2487 Practice for Classification of Soils for EngineeringPurposes (Unified Soil Classification System)D 2488 Practice for Description and Identification of Soils(Visual-Manual Procedure)IEEE/ASTM SI 10 Standard for Use of the InternationalSystem of Units (SI): Th
7、e Modern Metric System2.2 AASHTO Standards:3Standard Specifications for Highway BridgesM 145 Classification of Soils and SoilAggregate Mix-tures for Highway Construction PurposesT99 The Moisture-Density Relations of Soils Using a5.5-lb (2.5-kg) Rammer and a 12-in. (305-mm) DropT 180 The Moisture-Den
8、sity Relations of Soils Using a10-lb (4.54-kg) Rammer and an 18-in. (457-mm) DropT 310 In-Place Density and Moisture Content of Soil andSoil-Aggregate by Nuclear Methods (Shallow Depth)2.3 ASCE Standard:4ASCE 15 Standard Practice for the Direct Design of BuriedPrecast Reinforced Concrete Pipe Using
9、Standard Instal-lations (SIDD)3. Terminology3.1 For definitions of terms relating to concrete pipe, seeTerminology C 822.3.2 For terminology related to soil classifications, see Prac-tices D 2487 and D 2488.3.3 For terminology and definitions of terms relating tostructural design, see ASCE 15.3.4 Fi
10、g. 1 illustrates the definitions and limits of the terms:foundation, subgrade, bedding, outer bedding, middle bedding,haunch, lower side, backfill or overfill, invert, crown, spring-line, top of pipe, and bottom of pipe as used in this practice.4. Significance and Use4.1 This practice is useful as a
11、 reference by an owner andthe owners engineer in preparing project specifications.5. NotationsDi= inside diameter of pipe, mmDo= outside diameter of pipe, mmH = design height of earth above top of pipe, mw = unit weight of soil, N/m31This practice is under the jurisdiction of ASTM Committee C13 on C
12、oncretePipe and is the direct responsibility of Subcommittee C13.05 on Special Projects.Current edition approved Dec. 15, 2007. Published January 2008. Originallyapproved in 2007. Last previous edition approved in 2007 as C 1479M 07.2For referenced ASTM standards, visit the ASTM website, www.astm.or
13、g, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.3Available from American Association of State Highway and TransportationOfficials (AASHTO), 444 N. Capitol St., NW, Suite 249, W
14、ashington, DC 20001,http:/www.transportation.org.4Available from American Society of Civil Engineers (ASCE), 1801 AlexanderBell Dr., Reston, VA 20191, http:/www.asce.org.1Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.6. Standard Ins
15、tallations6.1 The precast concrete pipe/soil system shall be con-structed to conform to the requirements of Figs. 2 and 3 andTables 1 and 2 as designated on the plans.7. Excavation7.1 When rock or other unyielding foundation material isencountered, it shall be removed at least to the requirementssho
16、wn in Figs. 2 and 3 and Tables 1 and 2. Overexcavatedareas shall be backfilled with approved materials and com-pacted to at least the standard proctor density specified for thebedding.7.2 Where surface water or groundwater conditions exist,the site and trench shall be dewatered.8. Foundation8.1 The
17、foundation shall be moderately firm to hard in situsoil, stabilized soil, or compacted fill material.8.2 When unsuitable or unstable material is encountered,the foundation shall be stabilized.8.3 Methods to prevent migration of soil fines shall beprovided when groundwater or existing soil conditions
18、 areconducive to particle migration. Gravelly soils, with little or nofines, could migrate under certain conditions, causing lack ofsupport.8.4 Pipe installed over an unyielding foundation shall becushioned so as to prevent blasting shock when future blastingis anticipated in the area.9. Bedding9.1
19、The bedding shall be constructed uniformly over the fulllength of the pipe barrel, as required for the designatedstandard installation, to distribute the load-bearing reactionuniformly on the pipe barrel over its full length, and tomaintain the required pipe grade. See Fig. 4. If placed in layers,th
20、e thickness of the layers shall be as required to achieve thespecified compaction and as required by the project specifica-tions.9.2 The bedding layers for standard installation Types 1, 2,and 3 shall be placed to be as uniform as possible, but shall beFIG. 1 Pipe/Installation TerminologyC 1479M 07a
21、2loosely placed uncompacted material under the middle third ofthe pipe prior to placement of the pipe.9.3 The maximum aggregate size shall be 25 mm when thebedding thickness is less than 150 mm and 38 mm when thebedding thickness is 150 mm or greater, except as noted in 9.4.9.4 When in situ soils co
22、nforming to project specificationsare used in constructing the bedding for Type 3 and 4installations, the maximum aggregate size shall not be greaterthan 75 mm, or half the bedding thickness, whichever is less.9.5 The use of aggregate sizes larger than 25 mm shall belimited to 20 % of the bedding ma
23、terial by weight.9.6 Bell holes shall be excavated in the bedding or founda-tion, or both, when installing pipe with expanded bells so thatthe pipe is supported by the barrel and not by the bells. See Fig.4.9.7 Any outer bedding under the lower side areas shall becompacted to at least the same requi
24、rements as for the lowerside areas.10. Pipe Placement and Joining10.1 Pipe shall be installed to the line and grade shown onthe project plans and specifications. The joint shall be asspecified in the project specifications and shall be installed inaccordance with the pipe manufacturers recommendatio
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMC1479M2007ASTANDARDPRACTICEFORINSTALLATIONOFPRECASTCONCRETESEWERSTORMDRAINANDCULVERTPIPEUSINGSTANDARDINSTALLATIONSMETRIC

链接地址:http://www.mydoc123.com/p-464802.html