ASHRAE LV-11-C078-2011 Assessing the Impact Fire Heat Release Rate has on Infrastructure Design and Constructability of Rail and Road Tunnels Ventilation Systems.pdf
《ASHRAE LV-11-C078-2011 Assessing the Impact Fire Heat Release Rate has on Infrastructure Design and Constructability of Rail and Road Tunnels Ventilation Systems.pdf》由会员分享,可在线阅读,更多相关《ASHRAE LV-11-C078-2011 Assessing the Impact Fire Heat Release Rate has on Infrastructure Design and Constructability of Rail and Road Tunnels Ventilation Systems.pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Assessing the Impact Fire Heat Release Rate has on Infrastructure Design and Constructability of Rail and Road Tunnels Ventilation Systems J. Greg Sanchez, P.E. ASHRAE Member ABSTRACT Tunnel ventilation facilities, for road or rail tunnels, face the challenge of the design requirements imposed on th
2、em. Among them is the Fire Heat Release Rate (FHRR). Many think that the larger the FHRR, the safer the system, but the fact is that if FHRR is too large, the airflows required for a ventilation system to control the smoke become too large, the facility requires a lot of space, and the cost may esca
3、late to the point that the constructability of the ventilation plant may be too costly to build. The airflow rate through the tunnel ventilation facility and fan duty points are key parameters. The airflow through the tunnel ventilation facility is a function of the tunnel configuration constraints;
4、 while the duty point is a function of the number of fans, individual fan airflow, equipment room layout, and airflow path. The airflow rates are determined through computer modeling taking into account numerous branches and tunnel network losses. The duty point is usually determined by hand calcula
5、tions (for simple systems), but sometimes, it becomes very difficult that we need to carry out computer modeling. This paper will illustrate that there is a non-linear correlation between the magnitude of change in the FHRR, and the sizing of the tunnel ventilation facility. Ultimately, there is a c
6、hange, but through computer simulations, these changes will need to be assessed. INTRODUCTION Even though many tunnel designs have been completed over the years, there is still one question no one has answered: how does the fire heat release rate really impact the design and constructability of a tu
7、nnel ventilation system? Harvey (2009) tries to address the issue, but in the end, he does not answer the question. He just basically joins the thought of NFPA 502 (2008). We seem to believe that bigger is better. But is it really? The first thing we need to understand is the cost of safety. After a
8、ll, tunnel ventilation systems are capital projects very closely associated with taxpayers money one way or another, and cost is a very important component of the project. Figure 1 depicts in simple terms that if we build a project without safety being taken into consideration, the increase in risk
9、causes the cost accidents to rise to a high enough level where the project could be stopped in order to limit the liability. By the same token, if we go to the extreme and dream of very unlikely events, the project could become unbuildable. As engineers and designers, we must consider events that ar
10、e probable, but LV-11-C078 2011 ASHRAE 6492011. American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Transactions, Volume 117, Part 1. For personal use only. Additional reproduction, distribution, or transmission in either print or dig
11、ital form is not permitted without ASHRAES prior written permission.likely to happen. We cannot concentrate on the events and design scenarios with very small likelihood to occur. Otherwise, the project could not be built. For instance, we should determine the best credible design Fire Heat Release
12、Rate (FHRR), fan airflows, and fan pressures, and then add a safety factor. However, we should not estimate a large FHRR in order to determine a larger fan airflow and pressure. We must determine the level of risk and safety we can afford in a project. This will set the protocol and policies on how
13、to handle the hazards we could not consider for the project, and how to mitigate hazards of those we considered in order to avoid loss of life and transportation infrastructure. We should build something practical, functional, with reasonable degree risk and safety. Just remember: zero risk does not
14、 exist. Figure 1. The cost of safety FIRE HEAT RELEASE RATE To this extent, we come to the issue of fires. Many think that the larger the design FHRR, the safer the infrastructure. However, too large of a FHRR would require strenuous fire safety measures. If the very large fire scenarios are very li
15、kely to occur, by default that makes the project risk high enough to create an unacceptable high liability level and it should be stopped. We cannot talk about fire hazards without talking about how we intend to handle the hazards so that they do not become an incident where there is significant los
16、s of life and/or transportation infrastructure. For example, looking at the airline industry, an airplane is designed considering how much fuel it will carry, sufficient to allow a safe journey. The tanks are specified to safety standards that have been developed through lessons learned. In addition
17、s, if is it a cargo airplane, precautions are taken to ensure the materials do not create an accident (within the risk limits the air cargo has identified). If it is a passenger airplane, we have learned since 11 September 2001 events that passengers and luggage must be screened in order to control
18、the hazards that could create an accident, based on the new risk levels the industry has embraced. Tunnel ventilation facilities, for road or rail tunnels, should not be different from the airline industry. Both face the challenge of determining the appropriate design requirements that will manage t
19、he levels of risk and limit the magnitude of the loss consequences. 650 ASHRAE TransactionsNFPA 502 (2008) has some strong design fire scenarios, but there is no justification for their use. Past history of accidents alone is not enough. As stated above, we must specify the fire scenario by describi
20、ng how the hazards are to be handled. In this case, we must consider the requirements that the hazards must comply with in order to satisfy the design requirements. NFPA 130 (2010) does a better job in this regard. In the rolling stock section, the standard sets out fire hardening requirements for t
21、he materials that are to be used in the construction of the rolling stock. If these requirements are satisfied, there is a very likely possibility that the rolling stock will not blast in flames. Passengers may be protected by designing a ventilation system good enough to control the smoke in the tu
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAELV11C0782011ASSESSINGTHEIMPACTFIREHEATRELEASERATEHASONINFRASTRUCTUREDESIGNANDCONSTRUCTABILITYOFRAILANDROADTUNNELSVENTILATIONSYSTEMSPDF

链接地址:http://www.mydoc123.com/p-455481.html