ARMY UFGS-31 63 26-2008 DRILLED CAISSONS [Superseded ARMY UFGS-31 63 26 00 10 NAVY UFGS-31 63 26 16 20]《钻孔沉井(代替 ARMY UFGS-31 63 26 00 10 NAVY UFGS-31 63 26 16 20)》.pdf
《ARMY UFGS-31 63 26-2008 DRILLED CAISSONS [Superseded ARMY UFGS-31 63 26 00 10 NAVY UFGS-31 63 26 16 20]《钻孔沉井(代替 ARMY UFGS-31 63 26 00 10 NAVY UFGS-31 63 26 16 20)》.pdf》由会员分享,可在线阅读,更多相关《ARMY UFGS-31 63 26-2008 DRILLED CAISSONS [Superseded ARMY UFGS-31 63 26 00 10 NAVY UFGS-31 63 26 16 20]《钻孔沉井(代替 ARMY UFGS-31 63 26 00 10 NAVY UFGS-31 63 26 16 20)》.pdf(18页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-31 63 26 (August 2008)-Preparing Activity: USACE SupersedingUFGS-31 63 26.00 10 (April 2006)UFGS-31 63 26.16 20 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2008*SECTION TABLE OF CONTENTSDIVISION 31 - EARTHWO
2、RKSECTION 31 63 26DRILLED CAISSONS08/08PART 1 GENERAL1.1 UNIT PRICES1.1.1 Basis of Bids1.1.2 Tests1.1.2.1 Load Test1.1.2.2 Penetration Test1.1.2.3 Proof Test Hole1.1.3 Separate Unit Prices1.1.3.1 Additional Caisson Lengths1.1.3.2 Omitted Caisson Lengths1.1.3.3 Casings Permanently Left in Place1.1.3.
3、4 Reinforcing Steel for Additional Caisson1.1.3.5 Reinforcing Steel for Caissons Omitted1.1.3.6 Removal of Rock1.1.3.7 Removal of Obstructions Other Than Rock1.1.4 Basis Of Payment1.1.4.1 Unit Price1.1.4.2 Full Compensation1.1.4.3 Load Tests1.1.4.4 Penetration Tests1.1.4.5 Proof Test Holes1.2 REFERE
4、NCES1.3 SUBMITTALS1.4 QUALITY ASSURANCE1.4.1 Survey of Caisson Locations1.4.2 Specialty Subcontractor Qualifications1.4.3 Welding1.4.4 Pre-installation Conference1.4.5 Contractor Supervision1.4.6 Government Inspection1.4.7 Safety Precautions for Workmen and Inspectors1.4.7.1 Life Line1.4.7.2 Ventila
5、tion1.5 DELIVERY, STORAGE, and HANDLINGSECTION 31 63 26 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.6 PROJECT/SITE CONDITIONS1.6.1 Subsurface Data1.6.2 Caisson Drilling Equipment1.7 SEQUENCING1.7.1 Caisson Excavation1.7.2 AcceptancePART 2
6、 PRODUCTS2.1 MATERIALS2.1.1 Concrete Work2.1.1.1 Strength2.1.1.2 Coarse Aggregate2.1.1.3 Reinforcing Steel2.1.2 Welding2.1.3 Casing Steel2.2 CAISSON DRILLING EQUIPMENTPART 3 EXECUTION3.1 PREPARATION3.2 INSTALLATION3.3 TOLERANCES3.4 PENETRATION TESTS3.5 PROOF TEST HOLE REQUIREMENTS3.6 LOAD TESTS3.6.1
7、 General Requirements3.6.2 Replacements3.7 PROTECTION3.8 SPECIAL INSPECTION AND TESTING FOR SEISMIC-RESISTING SYSTEMS3.9 RECORDS- End of Section Table of Contents -SECTION 31 63 26 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC
8、 / AFCESA / NASA UFGS-31 63 26 (August 2008)-Preparing Activity: USACE SupersedingUFGS-31 63 26.00 10 (April 2006)UFGS-31 63 26.16 20 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2008*SECTION 31 63 26DRILLED CAISSONS08/08*NOTE: This guide specif
9、ication covers the requirements for the procurement, installation, and testing of drilled foundation caissons including reinforcing and cast-in-place concrete.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable
10、 items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing o
11、f technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).This guide specification includes tailoring options for NAVFAC, NASA and USACE. Selection or deselection of a
12、 tailoring option will include or exclude that option in the section, but editing the resulting section to fit the project is still required.*PART 1 GENERAL*NOTE: Use the following specifications in conjunction with this section:SECTION 00 22 13 SUPPLEMENTARY INSTRUCTIONS TO BIDDERSSECTION 31 63 26
13、Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-SECTION 01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTSOn the drawings, show:1. Subsurface-soil-data logs.2. Top and bottom elevation of each caisson.3. Size (diameter in mm (inches), bearing
14、 capacity, and total number of each size of caissons.4. Dimensions of the bell, if required.5. Dimensions of the casing.6. Reinforcing steel details, if required.7. Location of caissons to be penetration tested, if required.8. Location of caisson to be proof tested, if required.9. Locations, size, b
15、ell dimensions, and installation sequence of load testing caisson, if required.*1.1 UNIT PRICES*NOTE: Delete this subpart for NASA projects.*a. Requirements for price breakdown of Drilled Caisson work are specified in Section 01 20 00.00 20 PRICE AND PAYMENT PROCEDURES. Requirements for construction
16、 scheduling related to Drilled Caisson work are specified in Section 01 32 17.00 20 NETWORK ANALYSIS SCHEDULES.*NOTE: If requirements for price breakdown of drilled caissons work are specified in Section 01 22 00.00 10 MEASUREMENT AND PAYMENT, use the following paragraph and delete subparts 1.2.1 th
17、rough 1.2.4.*b. Requirements for price breakdown of Drilled Caisson work are specified in Section 01 22 00.00 10 MEASUREMENT AND PAYMENT.*NOTE: This paragraph anticipates bids on a lump sum price for an entire project including caisson work with directed changes being in accordance with the CONTRACT
18、 CLAUSES or in accordance with unit prices SECTION 31 63 26 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-as defined in paragraph “Separate Unit Prices.“Delete “in accordance with the CONTRACT CLAUSES“ or paragraphs “Tests“ and “Separate Unit
19、 Prices“ for lump sum projects.*1.1.1 Basis of BidsBase the bid on the number and total length of caissons, established by top and bottom elevations and diameters, as indicated and specified. Adjustment of the contract will be made in accordance with the CONTRACT CLAUSES, should the total length of
20、caissons installed and approved be greater or less than the total length shown. The Contractor will not receive payment for rejected caissons or for those not conforming to specifications.1.1.2 Tests1.1.2.1 Load TestThe Contract includes _ load tests rated at _ metric ton ton per caisson. The Contra
21、cting Officer reserves the right to increase or decrease the number of load tests. Adjustments in the contract price will be made for each such increase or decrease by the amount bid for “Additional Caisson Load Test“ or “Omitted Caisson Load Test“.1.1.2.2 Penetration TestThe Contract includes _ pen
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS3163262008DRILLEDCAISSONSSUPERSEDEDARMYUFGS3163260010NAVYUFGS3163261620 钻孔 沉井 代替 ARMYUFGS3163260010NAVYUFGS3163261620PDF

链接地址:http://www.mydoc123.com/p-449699.html