1、PMP 资格认证考试-项目范围管理(四)及答案解析(总分:20.00,做题时间:90 分钟)一、B单项选择题/B(总题数:20,分数:20.00)1.During the execution phase of the project, you realized the subcontractors are working with incomplete and different scope statements. As the project manager, what should you do FIRST? A. Check the work completed against the
2、correct scope statements. B. Review the scope of work with the stakeholders. C. Document the inconsistencies to management, calculating the cost of nonconformance. D. Stop all activities until the scope of the work complete.(分数:1.00)A.B.C.D.2.Over the last few weeks, the team has made three scope ch
3、anges to the activities and tasks on the projects. The project manager must be MOST careful to _. A. record all the changes B. provide documentation on all the changes to the sponsor C. make sure the changes are reflected in the project scope D. prevent more changes from occurring(分数:1.00)A.B.C.D.3.
4、The customer wants to expand the scope of the project after performance measurement baseline has been established. Which document will the customer need to submit? A. Change request. B. Statement of work. C. Revised project schedule. D. Invoice.(分数:1.00)A.B.C.D.4.During a walk through of a task, you
5、 discover that a team member is completing the work differently than stated in the WBS directory. How should you deal with this? A. Tell the team member to take a corrective action. B. Determine if the alternative way is acceptable to the functional manager. C. Ask the team member if the changes are
6、 necessary. D. Determine if the changes also change the scope of the work package.(分数:1.00)A.B.C.D.5.Two months into a design project, the customer requested a modification to the project. The change was made a without notify the project manager. During the final testing phase, result were different
7、 from what was planned for, This scenario is an example of which of following? A. Poor definition of the test plan. B. Poor development of quality management plan. C. Poor use of scope change control. D. Poor adherence to the communication plan.(分数:1.00)A.B.C.D.6.If a project manager is told that mo
8、difying the scope of the project may provide added value for the customer, the project manager should _. A. change the WBS B. change the scope baseline C. fix a variance report D. postpone the modification till a separate enhancement project in(分数:1.00)A.B.C.D.7.Management-by-objectives refers to _.
9、 A. confirming practical objectives B. making objectives clearly C. increasing the project managers power D. A and B(分数:1.00)A.B.C.D.8.Configuration management describes procedures for applying technical and administrative direction and surveillance. Which one of the following tasks is not performed
10、 in configuration management? A. Identifying functional and physical characteristics of an item or system. B. Controlling changes to characteristics. C. Performing an audit to verify conformance to requirements. D. Allowing automatic approval of changes.(分数:1.00)A.B.C.D.9.You have been appointed pro
11、ject manager for a new project in your organization and must prepare a project plan. To help you provide the framework for this project, you decide to prepare a WBS to show the magnitude and complexity of the work involved. No WBS templates are available to help you. To prepare the WBS, you first st
12、ep should be to _. A. determine the cost and duration estimates for each project deliverable B. identify the major project deliverable C. identify the components of each project deliverable D. determine the key tasks to be performed(分数:1.00)A.B.C.D.10.You are working on a telecommunication project.
13、The product and system requirements have been determined and agreed to by the customer, your management, and other key stakeholders. Work is proceeding on the project according to schedule. Everyone seems pleased with the progress to date. You have just learned that a new regulatory requirement will
14、 cause a change in one of the projects performance specification. To ensure that this change is incorporated onto the project plan, you should _. A. call a meeting of the change control board B. change the WBS, project schedule, and project plan to reflect the new requirement C. prepare a change req
15、uest D. immediately inform all affected stakeholders of the new approach to take on tee project(分数:1.00)A.B.C.D.11.The PM distributed a document to the stakeholders which described the software to be developed, the functionality, the users it would serve and the installation timeline. The document w
16、as an example of _. A. product scope B. project scope C. a combination of project and product scope D. it was not complete enough to be either a product or a project scope document(分数:1.00)A.B.C.D.12.The PM and project team have completed decomposition and have verified scope, when the marketing dep
17、artment makes a minor change to the product functionality to improve its appeal to the end customer. The PM and the project team _. A. refuses to accept the change since the scope has been veriied B. modifies the WBS and the decomposition C. accepts the change and incorporates it into the WBS, modif
18、ying the budget and the schedule and assigning accountability to the marketing team D. proceeds per the change process(分数:1.00)A.B.C.D.13.The scope management plan is developed as _. A. part of the scope verification phase B. part of scope planning C. the initial steps of scope control D. part of th
19、e Scope Statement(分数:1.00)A.B.C.D.14.The purpose of the scope statement includes all but which of the following? A. Provides a basis for future project decision. B. Establishes a contract between the project team and the customer. C. Sets criteria to use to determine if a project or phase have been
20、completed successfully. D. Establishes project constrains and assumptions.(分数:1.00)A.B.C.D.15.On a critical project, with a short timeframe, a contractor found an omission in a proposal which had been submitted and approved. The contractor indicated this omission may change both scope and thus cost
21、to the project. Upon receiving notification, the PM should _. A. submit, or ask the vender to submit, a change request to include the omission in the scope of the project B. check the type of the contract used and approve the increase to the budget C. since the project is falling behind, approve bot
22、h the change in scope and the additional cost to the project to make sure the project is not delayed D. gather more information(分数:1.00)A.B.C.D.16.To integrate approved scope changes, the PM should begin with _. A. approved budget B. project schedule C. product description D. WBS(分数:1.00)A.B.C.D.17.
23、A precise description of a deliverable is called a _. A. specification B. baseline C. work package D. work breakdown structure element(分数:1.00)A.B.C.D.18.Because of a new government regulation, you had to change the scope of your telecommunications project. Several changes were made to the projects
24、objectives. You have updated the projects technical and planning document as needed. Your next step should be to _. A. notify the stakeholders as appropriate B. revise the company the knowledge management system C. obtain formal acceptance from your sponsor and customer D. prepare a performance repo
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 范围 管理 答案 解析 DOC