REG NASA-LLIS-1282-2002 Lessons Learned Project Management Changing Workforce Requirements.pdf
《REG NASA-LLIS-1282-2002 Lessons Learned Project Management Changing Workforce Requirements.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1282-2002 Lessons Learned Project Management Changing Workforce Requirements.pdf(2页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1282Lesson Info:a71 Lesson Number: 1282a71 Lesson Date: 2002-01-01a71 Submitting Organization: ARCa71 Submitted by: DR Mendoza/ Mark LeonSubject: Project Management: Changing Workforce Requirements Description of Driving Event: The Project underwent several transitions requiri
2、ng a refocusing or resizing of project personnel resources. Thus, several employees were trimmed from the work force, causing a deflation in morale among the remaining Project personnel, in addition to the loss in capability. In response, the Project/Program management actively sought to place the t
3、rimmed workforce with other employment, either throughout the Programs other projects or with external sources. Knowing that their welfare was being protected and advocated for, the Project employees were able to sustain their productivity and morale.Lesson(s) Learned: During Project downsizing and/
4、or redirecting, care must be taken to allow people to adjust. This may mean finding employees alternate work so that they are not caught off guard, demoralized, or unsupported. This philosophy strengthens each remaining team members commitment to the team and to management, increases morale, reduces
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS12822002LESSONSLEARNEDPROJECTMANAGEMENTCHANGINGWORKFORCEREQUIREMENTSPDF

链接地址:http://www.mydoc123.com/p-1018921.html