NAVY UFGS-01 45 00 00 20-2011 QUALITY CONTROL《质量控制》.pdf
《NAVY UFGS-01 45 00 00 20-2011 QUALITY CONTROL《质量控制》.pdf》由会员分享,可在线阅读,更多相关《NAVY UFGS-01 45 00 00 20-2011 QUALITY CONTROL《质量控制》.pdf(29页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-01 45 00.00 20 (November 2011)-Preparing Activity: NAVFAC SupersedingUFGS-01 45 02 (February 2010)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated October 2011*SECTION TABLE OF CONTENTSDIVISION 01 - GENERAL REQUIREMENTSSECTION 01
2、 45 00.00 20QUALITY CONTROL11/11PART 1 GENERAL1.1 REFERENCES1.2 SUBMITTALS1.3 INFORMATION FOR THE CONTRACTING OFFICER1.4 QC PROGRAM REQUIREMENTS1.4.1 Commissioning1.4.2 Acceptance of the Construction Quality Control (QC) Plan1.4.3 Preliminary Construction Work Authorized Prior to Acceptance1.4.4 Not
3、ification of Changes1.5 QC ORGANIZATION1.5.1 QC Manager1.5.1.1 Duties1.5.1.2 Qualifications1.5.2 LEED Commissioning Authority1.5.2.1 Duties1.5.2.2 Qualifications1.5.3 Construction Quality Management Training1.5.4 Alternate QC Manager Duties and Qualifications1.5.5 Assistant QC Manager Duties and Qua
4、lifications1.5.6 QC Specialists Duties and Qualifications1.5.7 Registered Fire Protection Engineer1.5.8 Submittal Reviewers Duties and Qualifications1.5.9 QC Administrative Assistant1.5.10 Underwater QC Team1.6 QUALITY CONTROL (QC) PLAN1.6.1 Construction Quality Control (QC) Plan1.6.1.1 Requirements
5、1.7 QC PLAN MEETINGS1.8 COORDINATION AND MUTUAL UNDERSTANDING MEETING1.8.1 Purpose1.8.2 Coordination of Activities1.8.3 Attendees1.9 QC MEETINGS1.10 DESIGN REVIEW AND DOCUMENTATION1.10.1 Basis of Design and Design IntentSECTION 01 45 00.00 20 Page 1Provided by IHSNot for ResaleNo reproduction or net
6、working permitted without license from IHS-,-,-1.10.2 Design Review1.10.3 Contract Document Review1.11 THREE PHASES OF CONTROL1.11.1 Preparatory Phase1.11.2 Initial Phase1.11.3 Follow-Up Phase1.11.4 Additional Preparatory and Initial Phases1.11.5 Notification of Three Phases of Control for Off-Site
7、Work1.12 SUBMITTAL REVIEW AND APPROVAL1.13 TESTING1.13.1 Accreditation Requirements1.13.2 Laboratory Accreditation Authorities1.13.3 Capability Check1.13.4 Test Results1.13.5 Test Reports and Monthly Summary Report of Tests1.14 QC CERTIFICATIONS1.14.1 CQC Report Certification1.14.2 Invoice Certifica
8、tion1.14.3 Completion Certification1.15 COMPLETION INSPECTIONS1.15.1 Punch-Out Inspection1.15.2 Pre-Final Inspection1.15.3 Final Acceptance Inspection1.16 DOCUMENTATION1.16.1 Construction Documentation1.16.2 Quality Control Validation1.16.3 Reports from the QC Specialist(s)1.16.4 Testing Plan and Lo
9、g1.16.5 Rework Items List1.16.6 As-Built Drawings1.17 NOTIFICATION ON NON-COMPLIANCE1.18 CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT PLAN1.18.1 Requirements During Construction1.18.1.1 Control Measures1.18.1.2 Moisture Contamination1.18.2 Requirements after ConstructionPART 2 PRODUCTSPART 3 EXE
10、CUTION3.1 PREPARATION- End of Section Table of Contents -SECTION 01 45 00.00 20 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-01 45 00.00 20 (November 2011)-Preparing Activity: NAVFAC SupersedingUFGS-01 45
11、 02 (February 2010)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated October 2011*SECTION 01 45 00.00 20QUALITY CONTROL11/11*NOTE: This guide specification covers the preparation and use of Design-Bid-Build (DBB) Quality Control. This guide specification will normall
12、y be used for Category One and Category Two projects. It may be also used for smaller, complex projects at the discretion of the Government. This section requires specific editing of the QC requirements. This section, as edited, must be reviewed and approved by the Administering ROICC Office prior t
13、o the 100 percent design submission.Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or rev
14、ising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments, suggestions and recommended changes for this guide specification are welcome and should
15、be submitted as a Criteria Change Request (CCR).*NOTE: When this specification is used, it will be in conjunction with Section 01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS).Additional QC requirements may be included in additional sections of the project. Some of the sections that include QC requir
16、ements are: Section 09 97 13.15 EPOXY/FLUOROPOLYURETHANE INTERIOR COATING OF WELDED STEEL PETROLEUM FUEL TANKS, Section 09 97 13.17 THREE COAT EPOXY INTERIOR COATING OF WELDED STEEL PETROLEUM FUEL TANKS, SECTION 01 45 00.00 20 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitte
17、d without license from IHS-,-,-Section 09 97 13.16 INTERIOR COATING OF WELDED STEEL WATER TANKS, and Section 09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES.*NOTE: Two options for the QC Manager duties havebeen incorporated into this guide specification.The first option allows the QC Manager to per
18、formproduction related duties and the second option doesnot. Both options can include the use of QCSpecialists responsible for performing QC forspecific areas of work and for a specifiedfrequency. Specify QC Specialists for those areasof work that are of sufficient complexity or size tojustify the e
19、xpense.Determine whether a full time QC Manager isjustified or designate the QC Manager as the Project Superintendent, i.e. to act in a dual role. If the QC Manager and Project Superintendent positions are being filled as a dual role, that person shall not be utilized as or the Commissioning Authori
20、ty. Consider:a. Design and complexity of project.b. Location of project.c. Cost and type of Contract.d. Characteristics of area construction labormarket.e. Amount and type of off-site fabrication.f. Duration of project.When requiring the use of a Registered ProfessionalEngineer/Architect or a gradua
21、te Engineer/Architectfor the QC Manager or QC Specialist(s), keep in mindthe additional cost. The over-specifying ofexpertise for QC personnel should be avoided.*NOTE: This section has a corresponding graphic called “quality_control_reports.pdf.“*NOTE: TO DOWNLOAD UFGS GRAPHICSGo to http:/www.wbdg.o
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- NAVYUFGS01450000202011QUALITYCONTROL 质量 控制 PDF

链接地址:http://www.mydoc123.com/p-984692.html