ASTM E1946-2018 Standard Practice for Measuring Cost Risk of Buildings and Building Systems and Other Constructed Projects.pdf
《ASTM E1946-2018 Standard Practice for Measuring Cost Risk of Buildings and Building Systems and Other Constructed Projects.pdf》由会员分享,可在线阅读,更多相关《ASTM E1946-2018 Standard Practice for Measuring Cost Risk of Buildings and Building Systems and Other Constructed Projects.pdf(9页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: E1946 18Standard Practice forMeasuring Cost Risk of Buildings and Building Systemsand Other Constructed Projects1This standard is issued under the fixed designation E1946; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision
2、, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers a procedure for measuring cost riskfor buildings and building systems and other con
3、structedprojects, using the Monte Carlo simulation technique asdescribed in Guide E1369.1.2 A computer program is required for the Monte Carlosimulation. This can be one of the commercially availablesoftware programs for cost risk analysis, or one constructed bythe user.1.3 This standard does not pu
4、rport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety, health, and environmental practices and deter-mine the applicability of regulatory limitations prior to use.1.4 This international stand
5、ard was developed in accor-dance with internationally recognized principles on standard-ization established in the Decision on Principles for theDevelopment of International Standards, Guides and Recom-mendations issued by the World Trade Organization TechnicalBarriers to Trade (TBT) Committee.2. Re
6、ferenced Documents2.1 ASTM Standards:2E631 Terminology of Building ConstructionsE833 Terminology of Building EconomicsE1369 Guide for Selecting Techniques for Treating Uncer-tainty and Risk in the Economic Evaluation of Buildingsand Building SystemsE1557 Classification for Building Elements and Rela
7、tedSiteworkUNIFORMAT IIE2083 Classification for Building Construction FieldRequirements, and Office Overhead and for general terms related to building economics,refer to Terminology E833.4. Summary of Practice4.1 The procedure for calculating building cost risk consistsof the following steps:4.1.1 I
8、dentify critical cost elements.4.1.2 Eliminate interdependencies between critical ele-ments.4.1.3 Select Probability Density Function.4.1.4 Quantify risk in critical elements.4.1.5 Create a cost model.4.1.6 Conduct a Monte Carlo simulation.4.1.7 Interpret the results.4.1.8 Conduct a sensitivity anal
9、ysis.5. Significance and Use5.1 Measuring cost risk enables owners of buildings andother constructed projects, architects, engineers, and contrac-tors to measure and evaluate the cost risk exposures of theirconstruction projects.3Specifically, cost risk analysis (CRA)helps answer the following quest
10、ions:5.1.1 What are the probabilities for the construction contractto be bid above or below the estimated value?5.1.2 How low or high can the total project cost be?5.1.3 What is the appropriate amount of contingency to use?5.1.4 What cost elements have the greatest impact on theprojects cost risk ex
11、posure?1This practice is under the jurisdiction of ASTM Committee E06 on Perfor-mance of Buildings and is the direct responsibility of Subcommittee E06.81 onBuilding Economics.Current edition approved Sept. 1, 2018. Published September 2018. Originallyapproved in 1998. Last previous edition approved
12、 in 2012 as E194612. DOI:10.1520/E194618.2For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.3This practice is ba
13、sed, in part, on the article, “Measuring Cost Risk of BuildingProjects,” by D. N. Mitten and B. Kwong, Project Management Services, Inc.,Rockville, MD, 1996.Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United StatesThis international standard wa
14、s developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for theDevelopment of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.15.2 CRA can
15、be applied to a projects contract cost, con-struction cost (contract cost plus construction change orders),and project cost (construction cost plus owners cost), depend-ing on the users perspectives and needs. This practice shallrefer to these different terms generally as “project cost.”6. Procedure
16、6.1 Identify Critical Cost Elements:6.1.1 A project cost estimate consists of many variables.Even though each variable contributes to the total project costrisk, not every variable makes a significant enough contribu-tion to warrant inclusion in the cost model. Identify the criticalelements in order
17、 to simplify the cost risk model.6.1.2 A critical element is one which varies up or downenough to cause the total project cost to vary by an amountgreater than the total project costs critical variation, and onewhich is not composed of any other element which qualifies asa critical element. This cri
18、terion is expressed as:IF VY.VCRIT(1)AND Y contains no other element X where VX.VCRITTHEN Y is a critical elementwhere:VY5 (2)Max. percentage variation of the element Y!*Ys anticipated cost!Total Project CostVCRIT= Critical Variation of the Project Cost.6.1.3 A typical value for the total project co
19、sts criticalvariation is 0.5 %.4By experience this limits the number ofcritical elements to about 20. A larger VCRITwill lead to fewercritical elements and a smaller VCRITwill yield more. A riskanalysis with too few elements is over-simplistic. Too manyelements makes the analysis more detailed and d
20、ifficult tointerpret. A CRA with about 20 critical elements provides anappropriate level of detail. Review the critical variation usedand the number of critical elements for a CRA against theunique requirements for each project and the design stage. Ahigher critical variance resulting in fewer criti
21、cal elements, ismore appropriate at the earlier stages of design.6.1.4 Arrange the cost estimate in a hierarchical structuresuch as UNIFORMATII (Classification E1557 for Buildings orClassification E2103/E2103M for Bridges; Practice E2514provides a presentation format for elemental costs). Table 1sho
22、ws a sample project cost model based on a UNIFORMATII Levels 2 and 3 cost breakdown for a building. TheUNIFORMAT II structure of the cost estimate facilitates thesearch of critical elements for the risk analysis. One does notneed to examine every element in the cost estimate in order toidentify thos
23、e which are critical.6.1.5 Starting at the top of the cost estimate hierarchy (thatis, the Group Element level), identify critical elements in adownward search through the branches of the hierarchy.Conduct this search by repeatedly asking the question: Is itpossible that this element could vary enou
24、gh to cause the totalbuilding cost to vary, up or down, by more than its criticalvariation? Terminate the search at the branch when a negativeanswer is encountered. Examine the next branch until allbranches are exhausted and the list of critical elements estab-lished (denoted by asterisks in the las
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTME19462018STANDARDPRACTICEFORMEASURINGCOSTRISKOFBUILDINGSANDBUILDINGSYSTEMSANDOTHERCONSTRUCTEDPROJECTSPDF

链接地址:http://www.mydoc123.com/p-529886.html