《ASTM D7982-2015 8212 Standard Practice for Testing of Factory Thermo-Fusion Seams for Fabricated Geomembrane Panels《预制土工膜板工厂热熔接缝试验的标准实践规程》.pdf》由会员分享,可在线阅读,更多相关《ASTM D7982-2015 8212 Standard Practice for Testing of Factory Thermo-Fusion Seams for Fabricated Geomembrane Panels《预制土工膜板工厂热熔接缝试验的标准实践规程》.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: D7982 15Standard Practice forTesting of Factory Thermo-Fusion Seams for FabricatedGeomembrane Panels1This standard is issued under the fixed designation D7982; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the year o
2、f last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice provides manufacturing quality controlguidance for the factory seaming of fabricated geomembranepanels
3、. This practice is not to be considered as all-encompassing since there are a large number of geomembranetypes, weld types and fabrication processes that cannot beanticipated and covered in this document.1.2 This practice is written for factory fabricated geomem-brane panels only and does not apply
4、to field fabricationon-site.1.3 This practice does not cover joining of materials duringthe primary geomembrane manufacturing process such as thevulcanized overlaps found in EPDM sheet.1.4 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is the
5、responsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2D4439 Terminology for GeosyntheticsD6392 Test Method for Determining the Integrity of N
6、onre-inforced Geomembrane Seams Produced Using Thermo-Fusion MethodsD7408 Specification for Non Reinforced PVC (PolyvinylChloride) Geomembrane SeamsD7700 Guide for Selecting Test Methods for GeomembraneSeamsD7747 Test Method for Determining Integrity of SeamsProduced Using Thermo-Fusion Methods for
7、ReinforcedGeomembranes by the Strip Tensile MethodD7749 Test Method for Determining Integrity of SeamsProduced Using Thermo-Fusion Methods for ReinforcedGeomembranes by the Grab MethodD7865 Guide for Identification, Packaging, Handling, Stor-age and Deployment of Fabricated Geomembrane Panels3. Term
8、inology3.1 For definition of terms related to geomembranes, refer toTerminology D4439.3.2 Definitions:3.2.1 destructive test samplea seam sample taken before,during or after production welding that is used to determinecompliance of production seams with a specification.3.2.2 post-production testa de
9、structive test sample testedat the conclusion of the manufacturing process (productionseam or trial seam) to qualify the previously produced produc-tion seams.3.2.3 pre-production testa destructive test sample tested atthe beginning of the manufacturing process to qualify subse-quent production seam
10、s.3.2.4 production seama factory seam that is made as partof a finished fabricated panel.3.2.5 trial seama seam made prior to or after productionwelding, made by the same personnel, using the samegeomembrane material, the same welding unit and the sameseaming conditions used in the actual production
11、 seamingprocess. Trial seams are used to provide destructive testsamples without damaging production seams.3.2.6 welding uniteach individual welding station or pieceof welding equipment used to make a single seam.4. Significance and Use4.1 This practice is intended to aid fabricators, suppliers,purc
12、hasers, and users of fabricated panels in the testingrequirements for factory created seams during fabrication ofgeomembrane panels.4.2 Factory seaming of geomembranes has advantages overfield seaming including less temperature variation, no wind,less contamination (soil and water) concerns, a consi
13、stent worksurface for welding and options for factory equipment that maynot be robust enough for the field environment. This results in1This practice is under the jurisdiction of ASTM Committee D35 on Geosyn-thetics and is the direct responsibility of Subcommittee D35.10 on Geomembranes.Current edit
14、ion approved Jan. 1, 2015. Published January 2015. DOI: 10.1520/D7982152For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe AST
15、M website.Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States1factory welds more consistent than field seams and allows fora lesser frequency of testing than for field seams.4.3 This guide is not intended to replace project-specificseamin
16、g and testing requirements or quality assurance pro-grams.5. Procedure5.1 Factory Seam Testing Frequency:5.1.1 The quality of production seams must be verified bydestructively testing portions of production seams or test seamsfrom each welding unit used at a frequency that is sufficient toprovide co
17、nfidence in the seam quality contained in the factoryfabricated panels. To that end, all production seaming must bebounded by passing destructive test samples consisting of, at aminimum, a pre-production test and a post-production test. Adestructive test sample tested during production process quali
18、-fies as a post-production test for the seams already made aswell as a pre-production test for the seams to be made goingforward.5.1.2 Destructive test samples can be taken from productionseams as part of in-process inspections. Destructive testsamples can be removed from extra material added to the
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMD798220158212STANDARDPRACTICEFORTESTINGOFFACTORYTHERMOFUSIONSEAMSFORFABRICATEDGEOMEMBRANEPANELS 预制

链接地址:http://www.mydoc123.com/p-526600.html