1、Designation: C 172 07Standard Practice forSampling Freshly Mixed Concrete1This standard is issued under the fixed designation C 172; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the year of last revision. A number in parentheses
2、 indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.This standard has been approved for use by agencies of the Department of Defense.1. Scope*1.1 This practice covers procedures for obtaining represen-tative samples of
3、fresh concrete as delivered to the project siteon which tests are to be performed to determine compliancewith quality requirements of the specifications under which theconcrete is furnished (Note 1). The practice includes samplingfrom stationary, paving and truck mixers, and from agitatingand nonagi
4、tating equipment used to transport central-mixedconcrete.1.2 The values stated in SI units are to be regarded as thestandard. The values shown in parentheses are provided forinformation only.NOTE 1Composite samples are required by this practice, unlessspecifically excepted by procedures governing th
5、e tests to be performedsuch as tests to determine uniformity of consistency and mixer efficiency.Procedures used to select the specific test batches are not described in thispractice, but it is recommended that random sampling be used todetermine overall specification compliance.1.3 This practice al
6、so covers the procedures to be used forpreparing a sample of concrete for further testing where it isdesirable or necessary to remove the aggregate larger than adesignated size. This removal of larger aggregate particles ispreferably accomplished by wet-sieving.1.4 The text of this standard referenc
7、es notes and footnoteswhich provide explanatory material and shall not be consideredas requirements of the practice.1.5 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate
8、 safety and health practices and determine the applica-bility of regulatory limitations prior to use. (WarningFreshhydraulic cementitious mixtures are caustic and may causechemical burns to skin and tissue upon prolonged exposure.2)2. Referenced Documents2.1 ASTM Standards:3E11 Specification for Wir
9、e Cloth and Sieves for TestingPurposes3. Significance and Use3.1 This practice is intended to provide standard require-ments and procedures for sampling freshly mixed concretefrom different containers used in the production or transporta-tion of concrete. The detailed requirements as to materials,mi
10、xtures, air content, temperature, number of specimens,slump, interpretation of results, and precision and bias are inspecific test methods.4. Sampling4.1 The elapsed time shall not exceed 15 min. betweenobtaining the first and final portions of the composite sample.4.1.1 Transport the individual sam
11、ples to the place wherefresh concrete tests are to be performed or where test speci-mens are to be molded. They shall be combined and remixedwith a shovel the minimum amount necessary to ensureuniformity and compliance with the maximum time limitsspecified in 4.1.2.4.1.2 Start tests for slump, tempe
12、rature, and air contentwithin 5 min after obtaining the final portion of the compositesample. Complete these tests expeditiously. Start moldingspecimens for strength tests within 15 min after fabricating thecomposite sample. Expeditiously obtain and use the sampleand protect the sample from the sun,
13、 wind, and other sources ofrapid evaporation, and from contamination.1This practice is under the jurisdiction of ASTM Committee C09 on Concreteand ConcreteAggregates and is the direct responsibility of Subcommittee C09.60 onTesting Fresh Concrete.Current edition approved July 15, 2007. Published Aug
14、ust 2007. Originallyapproved in 1942. Last previous edition approved in 2004 as C 172 04.2Section on Safety Precautions, Manual of Aggregate and Concrete Testing,Annual Book of ASTM Standards, Vol 04.02.3For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Ser
15、vice at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.1*A Summary of Changes section appears at the end of this standard.Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 194
16、28-2959, United States.5. Procedure5.1 Size of SampleMake the samples to be used forstrength tests a minimum of 28 L (1 ft3). Smaller samples arenot prohibited for routine air content, temperature, and slumptests. The size of the samples shall be dictated by the maximumaggregate size.5.2 The procedu
17、res used in sampling shall include the use ofevery precaution that will assist in obtaining samples that aretruly representative of the nature and condition of concretesampled as follows:NOTE 2Sampling should normally be performed as the concrete isdelivered from the mixer to the conveying vehicle u
18、sed to transport theconcrete to the forms; however, specifications may require other points ofsampling, such as the discharge of a concrete pump.5.2.1 Sampling from Stationary Mixers, Except PavingMixersSample the concrete by collecting two or moreportions taken at regularly spaced intervals during
19、discharge ofthe middle portion of the batch. Obtain these portions withinthe time limit specified in Section 4. Composite the portionsinto one sample for testing purposes. Do not obtain portions ofthe composite sample from the very first or last part of thebatch discharge (Note 3). Perform sampling
20、by passing areceptacle completely through the discharge stream, or bycompletely diverting the discharge into a sample container. Ifdischarge of the concrete is too rapid to divert the completedischarge stream, discharge the concrete into a container ortransportation unit sufficiently large to accomm
21、odate the entirebatch and then accomplish the sampling in the same manner asgiven above. Take care not to restrict the flow of concrete fromthe mixer, container, or transportation unit so as to causesegregation. These requirements apply to both tilting andnontilting mixers.NOTE 3No samples should be
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMC1722007STANDARDPRACTICEFORSAMPLINGFRESHLYMIXEDCONCRETE 混合 混凝土 取样 标准 实施 规程 PDF

链接地址:http://www.mydoc123.com/p-465646.html