ASTM C1131-2010(2015) Standard Practice for Least Cost (Life Cycle) Analysis of Concrete Culvert Storm Sewer and Sanitary Sewer Systems《混凝土涵洞 雨水沟以及排污沟系统的最低成本 (生命周期) 分析的标准实施规程》.pdf
《ASTM C1131-2010(2015) Standard Practice for Least Cost (Life Cycle) Analysis of Concrete Culvert Storm Sewer and Sanitary Sewer Systems《混凝土涵洞 雨水沟以及排污沟系统的最低成本 (生命周期) 分析的标准实施规程》.pdf》由会员分享,可在线阅读,更多相关《ASTM C1131-2010(2015) Standard Practice for Least Cost (Life Cycle) Analysis of Concrete Culvert Storm Sewer and Sanitary Sewer Systems《混凝土涵洞 雨水沟以及排污沟系统的最低成本 (生命周期) 分析的标准实施规程》.pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: C1131 10 (Reapproved 2015)Standard Practice forLeast Cost (Life Cycle) Analysis of Concrete Culvert, StormSewer, and Sanitary Sewer Systems1This standard is issued under the fixed designation C1131; the number immediately following the designation indicates the year oforiginal adoption
2、or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers procedures for least cost (life cycle)analysis (LCA) of
3、materials, systems, or structures proposedfor use in the construction of concrete culvert, storm sewer, andsanitary sewer systems.NOTE 1As intended in this practice, examples of analyses include, butare not limited to the following: (1) materials-pipe linings and coatings,concrete wall thicknesses,
4、cements, additives, etc.; (2) systems-circularpipe, box sections, multiple lines, force mains, etc.; and (3) structures-wetand dry wells, pump and lift stations, etc.1.2 The LCA method includes costs associated withplanning, engineering, construction (bid price), maintenance,rehabilitation, replacem
5、ent, and cost deductions for any re-sidual value at the end of the proposed project design life.1.3 For each material, system, or structure, the LCA methoddetermines in present value constant dollars, the total of allinitial and future costs over the project design life, and deductsany residual valu
6、e.1.4 Major factors in the LCA method include project designlife, service life, and relevant interest and inflation rates.2. Terminology2.1 Definitions:2.1.1 constant dollarsdollars of uniform purchasingpower exclusive of inflation or deflation.2.1.1.1 DiscussionConstant dollars are costs stated atp
7、rice levels for a specific reference year, usually the particulartime that the LCA is being conducted.2.1.2 current dollarsdollars of purchasing power in whichactual prices are stated, including inflation or deflation.2.1.2.1 DiscussionCurrent dollars are costs stated at pricelevels in effect whenev
8、er the costs are incurred. In the absenceof inflation or deflation, current dollars are equal to constantdollars.2.1.3 direct coststhe costs of excavation, removal, anddisposal of existing materials, systems, or structures; installa-tion and testing of replacements materials, systems, or struc-tures
9、; backfill; surface restoration, traffic rerouting, safety,utility relocations; and additional future costs required by newland uses, population growth.2.1.4 discount rateaccounts for the time value of moneyand reflects the impartiality of paying or receiving a dollar nowor at a future time.2.1.4.1
10、DiscussionThe discount rate is used to convertcosts occurring at different times to equivalent costs at acommon time. Discount rates may be expressed in nominal orreal terms.2.1.5 future costscosts incurred after a project has beenconstructed and operating, such as maintenance, rehabilitation,and re
11、placement costs.2.1.6 indirect coststhe costs to the owner that users pay interms of delayed time.2.1.7 inflation ratean increase in the volume of moneyand credit relative to available goods and services resulting ina continuing rise in the general price level.2.1.7.1 DiscussionIn this practice, inf
12、lation refers toyearly change in the Producer Price Index (1).22.1.8 interest ratethe cost of borrowed money.2.1.9 maintenance coststhe annual or periodic direct andindirect costs of keeping a material, system, or structurefunctioning for the project design life; such maintenance doesnot extend the
13、service life of the material, system, or structure.2.1.10 nominal discount ratea discount rate that takes intoaccount both the effects of inflation and the real earningpotential of money invested over time.2.1.10.1 DiscussionWhen future costs and values areexpressed in current dollars, after having
14、been adjusted forinflation, a nominal discount rate is used to convert the futurecosts and values to present value constant dollars. Users of thispractice should consult with their accountant or client todetermine the appropriate discount rate for a given project.2.1.11 original costscosts incurred
15、in planning, designing,and constructing a project.1This practice is under the jurisdiction of ASTM Committee C13 on ConcretePipe and is the direct responsibility of Subcommittee C13.05 on Special Projects.Current edition approved Oct. 15, 2015. Published October 2015. Originallyapproved in 1995. Las
16、t previous edition approved in 2010 as C1131 101. DOI:10.1520/C113110R15.2The boldface numbers refer to the list of references at the end of the standard.Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States12.1.12 project design lifethe nu
17、mber of years of useful lifethe material, system, or structure must provide.2.1.13 real discount ratea discount rate that takes intoaccount only the real earning potential of money over time andis the differential between the interest and inflation rates.2.1.13.1 DiscussionWhen future costs and valu
18、es areexpressed in future constant dollars, a real discount rate is usedto convert constant dollars to present value dollars. Life cycleeconomic analyses conducted in constant dollars and a realdiscount rate are often preferred to similar analyses conductedin current dollars using nominal discount r
19、ates because noforecast of the inflation rate is required.2.1.14 rehabilitation coststhe direct and indirect costs ofrehabilitating a material, system, or structure to extend theservice life of the material, system, or structure.2.1.15 replacement coststhe direct and indirect costs ofreplacing a mat
20、erial, system, or structure before the end of theproject design life, so it will again function as originallyintended.2.1.16 residual valuethe remaining value of the material,system, or structure at the end of the project design life.2.1.17 service lifethe number of years of service amaterial, syste
21、m, or structure will provide before rehabilitationor replacement is required.2.1.17.1 DiscussionProject design life and service life areusually established by the owner or controlling agency.3. Significance and Use3.1 The significance of the LCA method is that it is acomprehensive technique for taki
22、ng into account all relevantmonetary values over the project design life and provides ameasure of the total cost of the material, system, or structure.3.2 The LCA method can be effectively applied in both thepreconstruction and bid stages of projects.After bids are taken,real costs can be used inste
23、ad of estimates.4. Procedures4.1 The procedures for determining the LCA of a material,system, or structure can be summarized in five basic steps.4.1.1 Identify Objective, Alternatives, and Constraints.4.1.2 Establish Basic Criteria.4.1.3 Compile Data.4.1.4 Compute LCA for Each Material, System, or S
24、truc-ture.4.1.5 Evaluate Results.4.2 Objectives, Alternatives, and ConstraintsEstablish thespecific objectives of the project and identify alternative waysof accomplishing the objectives. For example, alternatives fora sanitary sewer system may include a gravity flow systemversus a gravity flow syst
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMC113120102015STANDARDPRACTICEFORLEASTCOSTLIFECYCLEANALYSISOFCONCRETECULVERTSTORMSEWERANDSANITARYSEWERSYSTEMS

链接地址:http://www.mydoc123.com/p-463483.html