REG NASA-LLIS-1200-1990 Lessons Learned Improper Raising of Orbiter 103 Payload Bay Door Mishap.pdf
《REG NASA-LLIS-1200-1990 Lessons Learned Improper Raising of Orbiter 103 Payload Bay Door Mishap.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1200-1990 Lessons Learned Improper Raising of Orbiter 103 Payload Bay Door Mishap.pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1200Lesson Info:a71 Lesson Number: 1200a71 Lesson Date: 1990-06-04a71 Submitting Organization: KSCa71 Submitted by: Paul D. Myers Jr./ Eric RaynorSubject: Improper Raising of Orbiter 103 Payload Bay Door Mishap Description of Driving Event: On June 4, 1990, in High Bay 1 of th
2、e Orbiter Processing Facility (OPF) at the Kennedy Space Center (KSC), the aft bridge of the Payload Bay Bridge and Hoist System was moved approximately 78 inches aft of its set position for Payload Bay Door (PLBD) operations. The right-hand PLBD Zero-G System was configured to support a scheduled P
3、LBD closing operation on first shift, June 4, 1990, except the Zero-G weight baskets were left pinned to their weight cages. The right Payload Bay Door (PLBD) was supported by the Zero-G cabling (not pinned to the platform). Movement of the bridge put the Zero-G cabling into tension and at an angle
4、sufficient to shear a portion of the weight basket pulley “V,“ fray the Zero-G cabling, move the weight basket off its track, and deflect the C-hook approximately 2 to 3 inches. Since the weight basket was pinned, the aft movement of the bridge also caused the right PLBD aft portion to rise approxim
5、ately 31 to 33 inches (calculated).Lesson(s) Learned: Failure of the bridge operator to follow the approved procedure, which requires verification that the Zero-G System is not hooked up prior to bridge movement and assignment of an observer, was the major contributing cause of this mishap. The seco
6、nd contributing cause involved multiple deficient control systems to preclude bridge operation while connected to the Zero-G Simulator. Supervisory control of the bridge power key was nonexistent, allowing technicians free access to bridge keys. Procedural steps included in Operations and Maintenanc
7、e Instruction (OMI) V3575 to tag the bridge/bucket system out of service and secure the key during Zero-G operations were not referenced in the OMI V9023 that configured the PLBD and Zero-G System for PLBD operations. Shift tie-in from the third shift Mechanical/Electrical/TCS Supervisor to the firs
8、t shift Electrical/TCS Supervisor did not occur. In addition, the first shift Electrical/TCS Supervisor was not aware of the scheduled PLBD operations status nor did he perform a complete walkdown. Therefore, the supervisor assigning work requiring bridge operations Provided by IHSNot for ResaleNo r
9、eproduction or networking permitted without license from IHS-,-,-was not aware the Zero-G System was connected. The work assigned to the bridge operator involved in this mishap did not appear either on the Orbiter Processing Facility (OPF) shop schedule or the KSC Integrated Contractor Schedule (KIC
10、S). Had this work been properly integrated into the KICS schedule, work involving bridge movement would have been scheduled to occur after use of the Zero-G Simulator was complete. The third contributing cause is attributed to this lack of integrated scheduling. Improper raising of the right PLBD pr
11、ompted a detailed inspection of the door structure but no damage was found that could be directly attributed to this mishap. Recommendation(s): Primary Cause Finding: Aft movement of Bridge 9A of the Payload Bay Area Bridge and Bucket Hoist System with the Payload Bay Door Zero-G Simulator connected
12、 (right side only) caused the improper raising of Orbiter 103s (OV-103) right payload bay door (PLBD). Contributing Causes: 1. The operator of bridge 9A, in support of TPS No. VTCS-3-11-138, TCS Blanket Rework - Aft Bulkhead, failed to follow the approved procedure covering bridge/bucket operations
13、(OMI V3575, OPF PLB Access Bridge/Bucket System) as follows: A) A thorough walkdown/inspection of bridge 9A was not performed per sequences 03 and 04 of OMI V3575 to verify Zero-G Simulator was not connected. Appendix A checklist only was used to checkout the bridge/bucket system. B) A bridge/bucket
14、 observer was not assigned.Recommendation: Delete Appendix A checklist and require use of OMI V3575 applicable sequences for bridge/bucket checkout and operation. 2. Control systems utilized by Shuttle Processing Contract (SPC) to preclude bridge operation while connected to the Zero-G Simulator wer
15、e deficient as follows: A) Control of the bridge/bucket keys was nonexistent. The technician had virtually free access to the keys. B) No provision is set forth in OMI V9023 (Orbiter Payload Bay Door Operations - Horizontal/Vertical) to tag bridge/bucket system out of service and secure the key duri
16、ng Zero-G operations per OMI V3575 requirements. C) Shift tie-in from third shift Mechanical/Electrical/TCS Supervisor to first shift Electrical/TCS Supervisor did not occur. Supervisor was not aware of scheduled PLBD operations status nor did he perform a complete walkdown. Therefore, the superviso
17、r assigning TPS No. VTCS-3-11-138 was not aware the Zero-G System was connected.Recommendation: SP-?018(2)K IOPF Payload Bay Access Equipment (Buckets) Operation and Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Control and OPF Fixed Platform Movem
18、ent Control, paragraph 6.1.1.b, which provides for specific key control, should be enforced. Recommendation: OMI V3575 steps to tag bridge/bucket system out of service and secure keys during Zero-G operations should be incorporated into OMI V9023. Recommendation: SPC OPF management needs to formaliz
19、e and enforce third to first shift tie-in. A formal end of shift tie-in needs to be established. Recommendation: The sustaining engineering design organization should incorporate a positive, actively controlled lockout device to prevent improper operation of the bridge system while the Zero-G Simula
20、tor is connected. 3. TPS VTCS-3-11-138 did not appear on the OPF shop schedule or the KSC Integrated Control Schedule (KICS) for June 4, 1990. This TPS was in response to MCR No. 14725 and should have been scheduled through the KICS system. Had TPS VTCS-3-11-138 been properly integrated into the KIC
21、S schedule, work involving bridge movement would have been scheduled to occur after use of the Zero-G Simulator was complete.Recommendation: All OPF shop work (non-hazardous) should be fully integrated with the KICS. OBSERVATIONS 1. Keys for both forward and aft bridge/buckets are fully interchangea
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS12001990LESSONSLEARNEDIMPROPERRAISINGOFORBITER103PAYLOADBAYDOORMISHAPPDF

链接地址:http://www.mydoc123.com/p-1018839.html