REG MSFC-HDBK-3684-2013 PROJECT PLANNING AND CONTROL HANDBOOK.pdf
《REG MSFC-HDBK-3684-2013 PROJECT PLANNING AND CONTROL HANDBOOK.pdf》由会员分享,可在线阅读,更多相关《REG MSFC-HDBK-3684-2013 PROJECT PLANNING AND CONTROL HANDBOOK.pdf(233页珍藏版)》请在麦多课文档分享上搜索。
1、National Aeronautics and MSFC-HDBK-3684Space Administration BASELINE EFFECTIVE DATE: February 26, 2013George C. Marshall Space Flight CenterMarshall Space Flight Center, Alabama 35812CS40PROJECT PLANNING AND CONTROLHANDBOOKApproved for Public Release; Distribution UnlimitedCHECK THE MASTER LIST VERI
2、FY THAT THIS IS THE CORRECT VERSION BEFORE USE at https:/repository.msfc.nasa.gov/docs/multiprogram/MSFC-SPEC-3684Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-MSFC Technical StandardCS40Title: Project Planning and Control HandbookDocument No.: MSF
3、C-HDBK-3684 Revision: BaselineEffective Date: February 26, 2013 Page 2 of 233DOCUMENT HISTORY LOGStatus (Baseline/Revision/Cancelled)Document RevisionEffective DateDescriptionBaseline 2/26/2013 Baseline Release. Document is authorized through MPDMS.CHECK THE MASTER LIST VERIFY THAT THIS IS THE CORRE
4、CT VERSION BEFORE USE at https:/repository.msfc.nasa.gov/docs/multiprogram/MSFC-SPEC-3684 Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-MSFC Technical StandardCS40Title: Project Planning and Control HandbookDocument No.: MSFC-HDBK-3684 Revision: Ba
5、selineEffective Date: February 26, 2013 Page 3 of 233TABLE OF CONTENTS1. INTRODUCTION 101.1 BACKGROUND AND PURPOSE 101.2 SCOPE. 111.3 REFERENCE DOCUMENTS . 132. RELATIONSHIP OF PP and in the case of projected over-runs, determine the amount of technical content that should be removed from the projec
6、t, or the amount of reserves that should be utilized, to meet budget, schedule, and minimum success criteria. Mission support analysis and strategic planning is critical to ensure that MSFC is providing the optimum workforce, facilities, and infrastructure required for current and future Center proj
7、ects, and to identify and mitigate cross-cutting risks to mission success.Managing the development and operations of the Centers missions with limited resources is one of the most significant challenges facing MSFC today. The result of effective project management and mission support execution is th
8、e delivery and successful completion of the program / project /activity within the specified limits of cost, schedule, technical, and risk management. The manager for the given area is responsible for the outcome, and is closely supported by a deputy manager, and possibly a technical manager (or chi
9、ef engineer, lead systems engineer, etc.), a Chief Safety Officer, and a project business manager (or Project Control manager, PP proposed and agreed to project scope changes; proposed or agreed to risks and associated actions; etc. MSFC-HDBK 3173, Project Management and Systems Engineering Handbook
10、, was developed to provide guidance and best practices for the project management and systems engineering disciplines. This companion handbook provides PP however, the emphasis of this handbook is to describe the processes necessary for project and mission support business management. The MSFC Assoc
11、iate Director for Management is the executive sponsor for the PP financial accountability; Earned Value Management (EVM); workforce assessment; programmatic analysis and reporting; and the technical, quality, risk, and configuration change aspects affecting PP however, all have a life-cycle that beg
12、ins by maturing a concept into a specific scope and set of requirements that define a project deliverable. These requirements drive a design phase that leads to product fabrication, integration, and testing. Many project products culminate into space flight and operation. NASA Headquarters is organi
13、zed into major mission and support directorates that manage portfolios of programs and supporting projects. MSFC work ranges from very large projects to much smaller activities, which are referred to and managed as projects by Center personnel and follow the same project life-cycle.The project life-
14、cycle management process receives oversight from a Governing Project Management Council (GPMC). Depending on the project size and complexity, the GPMC may be the MSFC Center Management Council (CMC), a MSFC project directorate, an Agency Mission Directorate, or the Agency Program Management Council.
15、 After initial project authorization approval is granted, projects formalize their life-cycle phases, life-cycle gates, and major events such as key project reviews. Single-project programs and MSFC projects follow the project life-cycle and its associated decision gates and major events as shown in
16、 Figure 2. Each type will follow the associated requirements as specified in Marshall Procedural Requirements (MPR) 7120.1, MSFC Engineering and Program/Project Management Requirements.A Key Decision Point (KDP) is the event where the Decision Authority (DA) determines the readiness of a project to
17、progress to the next phase of the life-cycle. KDPs for projects are labeled with capital letters (e.g., KDP A). Transition to a following phase occurs immediately following KDP approval except for transition from Phase D to E where transition occurs following on orbit checkout and initial operations
18、.2.1.1 Project FormulationDuring project formulation (Pre-Phase A, Phase A, and Phase B), PP approved risk list with an evaluation of cost and schedule impacts associated with approved risk mitigation; and cost, schedule, and risk assessment of any approved project design changes as a result of the
19、PDR that is conducted during this phase) for the KDP C review that are required to demonstrate that the technical challenges, major risks, and the cost and schedule are sufficiently understood, and stakeholder expectations and formulation requirements have been met. By approving the project, the DA
20、commits the budget resources necessary to continue into implementation. 2.1.6 Project ImplementationThe role of PP CHECK THE MASTER LIST VERIFY THAT THIS IS THE CORRECT VERSION BEFORE USE at https:/repository.msfc.nasa.gov/docs/multiprogram/MSFC-SPEC-3684 Provided by IHSNot for ResaleNo reproduction
21、 or networking permitted without license from IHS-,-,-MSFC Technical StandardCS40Title: Project Planning and Control HandbookDocument No.: MSFC-HDBK-3684 Revision: BaselineEffective Date: February 26, 2013 Page 18 of 233assessment and decisions associated with identified risks; and reporting of resu
22、lts to project stakeholders.2.1.7 Phase C: Final Design and FabricationDuring Phase C, the project completes the design that meets the detailed requirements and begins fabrication of test and flight architecture (e.g., flight article components, assemblies, and subsystems). These activities focus on
23、 implementing the project in accordance with the Project Plan, completing the final design, and assuring that the systems engineering activities are performed to determine if the design is mature enough to proceed with full-scale implementation. Phase C is focused toward the Critical Design Review (
24、CDR) and the System Integration Review (SIR). Completion of Phase C culminates in KDP D. Project costs (labor, equipment, test facilities, etc.) peak at the end of Phase C and early into Phase D; therefore, unexpected problems and delays are most costly (and critical to be resolved as quickly as pos
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGMSFCHDBK36842013PROJECTPLANNINGANDCONTROLHANDBOOKPDF

链接地址:http://www.mydoc123.com/p-1017440.html