ITU-T L 48-2003 Mini-trench installation technique《微型沟槽安装技术系列L 建造 安装和电缆保护以及外部设备其它元素》.pdf
《ITU-T L 48-2003 Mini-trench installation technique《微型沟槽安装技术系列L 建造 安装和电缆保护以及外部设备其它元素》.pdf》由会员分享,可在线阅读,更多相关《ITU-T L 48-2003 Mini-trench installation technique《微型沟槽安装技术系列L 建造 安装和电缆保护以及外部设备其它元素》.pdf(16页珍藏版)》请在麦多课文档分享上搜索。
1、 INTERNATIONAL TELECOMMUNICATION UNION ITU-T L.48TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (03/2003) SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF UTSIDE PLANT Mini-trench installation technique ITU-T Recommendation L.48 ITU-T Rec. L.48 (03/2003) i ITU-T R
2、ecommendation L.48 Mini-trench installation technique Summary This Recommendation describes the so-called mini-trenching technique, that allows the installation in small trenches of underground optical cables in ducts or directly buried copper cables. The advantages of this technique over convention
3、al cable laying technologies lie essentially in its speed of execution, lower cost, significantly lower environmental impact and limited disruption to road traffic and, as a consequence of the previous items, easiness in obtaining permits for the taking over of public area. Source ITU-T Recommendati
4、on L.48 was prepared by ITU-T Study Group 6 (2001-2004) and approved under the WTSA Resolution 1 procedure on 29 March 2003. ii ITU-T Rec. L.48 (03/2003) FOREWORD The International Telecommunication Union (ITU) is the United Nations specialized agency in the field of telecommunications. The ITU Tele
5、communication Standardization Sector (ITU-T) is a permanent organ of ITU. ITU-T is responsible for studying technical, operating and tariff questions and issuing Recommendations on them with a view to standardizing telecommunications on a worldwide basis. The World Telecommunication Standardization
6、Assembly (WTSA), which meets every four years, establishes the topics for study by the ITU-T study groups which, in turn, produce Recommendations on these topics. The approval of ITU-T Recommendations is covered by the procedure laid down in WTSA Resolution 1. In some areas of information technology
7、 which fall within ITU-Ts purview, the necessary standards are prepared on a collaborative basis with ISO and IEC. NOTE In this Recommendation, the expression “Administration“ is used for conciseness to indicate both a telecommunication administration and a recognized operating agency. INTELLECTUAL
8、PROPERTY RIGHTS ITU draws attention to the possibility that the practice or implementation of this Recommendation may involve the use of a claimed Intellectual Property Right. ITU takes no position concerning the evidence, validity or applicability of claimed Intellectual Property Rights, whether as
9、serted by ITU members or others outside of the Recommendation development process. As of the date of approval of this Recommendation, ITU had received notice of intellectual property, protected by patents, which may be required to implement this Recommendation. However, implementors are cautioned th
10、at this may not represent the latest information and are therefore strongly urged to consult the TSB patent database. ITU 2003 All rights reserved. No part of this publication may be reproduced, by any means whatsoever, without the prior written permission of ITU. ITU-T Rec. L.48 (03/2003) iii CONTE
11、NTS Page 1 Scope 1 2 The mini-trenching cable-laying technique 1 2.1 Preparatory steps 2 2.2 Excavation requirements 3 2.3 Mini-trench cleaning 3 2.4 Laying of the infrastructure or cables. 3 2.5 Pull cord and plugs . 4 2.6 Backfilling 4 2.7 Mechanical protection 5 2.8 Identification. 5 2.9 Resurfac
12、ing. 5 2.10 Maintenance of cable or duct after laying 6 3 Mini-trenching methods and procedures 6 3.1 Manual procedure. 6 3.2 Partially automated procedures 6 3.3 Fully automated procedures . 7 4 Mini-trenching application criteria. 7 4.1 Entry to existing manholes or chambers 7 4.2 Road crossings 7
13、 ITU-T Rec. L.48 (03/2003) 1 ITU-T Recommendation L.48 Mini-trench installation technique 1 Scope This Recommendation: gives advice on general requirements of the main phases in which the work can be divided; gives advice on the methods and procedures for performing the works; gives some application
14、 criteria. 2 The mini-trenching cable-laying technique The mini-trenching technique can be applied on routes that generally involve asphalted surfaces such as roads and sidewalks with a subgrade of compact material. It is not recommended that the technique be used on routes where the soil subgrade i
15、s sandy, gravelly or contains medium-sized cobbles (i.e., measuring 10 to 20 cm in diameter). If other underground utilities crossing a planned route already exists at a depth interfering with the depth of the mini-trench, this technology is not appropriate. The advantages of this technique over con
16、ventional cable laying technologies lie essentially in its speed of execution, lower cost, significantly lower environmental impact and limited disruption to road traffic and, as a consequence of the previous items, the easiness in obtaining permits for the occupation of public area. Mini-trenching
17、is normally carried out by simultaneously cutting through the paving and digging a trench whose depth and cross-section vary in accordance with the number of ducts to be laid: depth is normally between 30 and 40 cm, while cross-section can vary between 7 and 15 cm. In order to guarantee a protection
18、 against impact resulting from road-repairing, the depth of the laid infrastructure shall be maintained constant at a known level that must be 5 cm deeper than the foreseen asphalt cutting depth normally specified for road surface repair works. Figure 1 shows one of the possible installation configu
19、rations that can be used. Which configuration is selected will depend on the type of machinery employed and the number of ducts or cables envisaged in the project. L.48_ f0110 cm30 cmducts/cablescompact soil subgradehot mix asphaltwearing courseFigure 1/L.48 Example of mini-trenching installation co
20、nfiguration 2 ITU-T Rec. L.48 (03/2003) In cases where the mini-trench is dug along a road with no curb or sidewalk, the excavation shall normally be located at distance of around one metre from the edge of the road (or if possible just on the external side of the lateral line). In special circumsta
21、nces where this is not possible, the mini-trench may be dug in the shoulder at the edge of the asphalt. Any crossings through unpaved sections (which must in any case have a compact subgrade) should be carried out using the same technique. 2.1 Preparatory steps The mini-trench is excavated using app
22、ropriate disc-type cutting machines as shown in Figures 2 and 3. Figure 2/L.48 Example of standard cutting machine Figure 3/L.48 Example of fully automated trenching machine The designed route shall be free from sharp changes in direction. Where such changes are unavoidable, they shall be made by me
23、ans of cuts angled so as to comply with the minimum bend radii specified for the ducts and cables. ITU-T Rec. L.48 (03/2003) 3 The location of all underground utilities must be determined in order to establish the correct route for the trench. This is normally accomplished by means of cartographic d
24、ocumentation provided by the administrations that own the road or by the utility company, and/or through instrumented field surveys. Where other means of determining the location of underground utilities are not available, ground penetrating radar shall be used at detection depths between 0 and 100
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制: