1、 WORLDWIDE ENGINEERING STANDARDS Test Procedure GMW17007 Ethernet AVB Device Test Specification Copyright 2013 General Motors Company All Rights Reserved August 2013 Page 1 of 3 1 Scope Note: Nothing in this standard supercedes applicable laws and regulations. Note: In the event of conflict between
2、the English and domestic language, the English language shall take precedence. 1.1 Purpose. The purpose of this procedure is to verify the interface requirements of the physical and data link layers of an Ethernet Audio/Video Bridging (AVB) Communications System as specified in the Global Infotainme
3、nt System documentation. 1.2 Foreword. This procedure describes component/single Electronic Control Unit (ECU) level tests. This procedure shall be executed by the ECU supplier at each sample delivery phase and at every software change thereafter. Test results shall be submitted to the GM Serial Dat
4、a Team () for review by GM as per the Global Component Serial Communication Process described in the Appendix of the Statement of Requirements (SOR). 1.3 Applicability. This procedure applies to all ECUs communicating in an Ethernet AVB Infotainment System. 2 References Note: Only the latest approve
5、d standards are applicable unless otherwise specified. 2.1 External Standards/Specifications. None 2.2 GM Standards/Specifications. None 2.3 Additional References. CG3689, Ethernet AVB Device Test Result Template Electrical and Software Issues Management System (ESIMS) ECU Functional Requirements Sp
6、ecification Global Infotainment Standard (GIS)-610, Ethernet AVB Network Management for Infotainment 3.0 GIS-611, Message Schema and Serialization Specification GIS-612, Network Interface Configuration for Infotainment 3.0 GIS-618, I3B System State Management Specification Problem Resolution Trackin
7、g System (PRTS) Statement of Requirements (Appendix describing the Global Component Serial Communication Process) 3 Resources 3.1 Facilities. Testing shall be performed at the supplier facility using a bench that allows communication between the test tools and the ECU being tested. 3.1.1 Calibration
8、. The test facilities and equipment shall be in good working order and shall have a valid calibration label. 3.1.2 Alternatives. Alternative test facilities and equipment may also be used. However, all measuring variables as specified in this standard shall be determined correctly with respect to th
9、eir physical definition. Copyright General Motors Company Provided by IHS under license with General Motors CompanyNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-GM WORLDWIDE ENGINEERING STANDARDS GMW17007 Copyright 2013 General Motors Company All Rights Reserved
10、August 2013 Page 2 of 3 3.2 Equipment. The minimum required set of equipment to perform this test procedure includes: 3.2.1 Unless otherwise specified, the ECU being tested shall be powered by a direct current (DC) power supply at 12.5 V. This need not be an independent supply (i.e., it could be use
11、d to supply power to other devices in the test setup) unless specifically noted in the test procedure. 3.2.2 GM recommended hardware and software as needed for automated testing. 3.2.3 A high end oscilloscope with differential probes and the supporting software; measurement equipment for voltage and
12、 current. 3.2.4 A computer capable of running the GM recommended automated verification software. 3.2.5 A table listing the required hardware and software for automation, including versions and part numbers, is listed in CG3689. 3.3 Test Vehicle/Test Piece. A representative ECU flashed with the appl
13、icable software version for testing. 3.4 Test Time. Calendar time: 2 days to 5 days Test hours: 16 hours to 40 hours Coordination hours: 3 hours 3.5 Test Required Information. Not applicable. 3.6 Personnel/Skills. 3.6.1. Familiarity with Ethernet AVB serial data communications protocol, physical lay
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- GMWGMW170072013ETHERNETAVBDEVICETESTSPECIFICATIONISSUE1ENGLISHPDF

链接地址:http://www.mydoc123.com/p-757964.html