COE EP 1110-1-8 VOL 12-2009 Construction Equipment Ownership and Operating Expense Schedule Region XII《施工设备的所有权和运行费用表XII》.pdf
《COE EP 1110-1-8 VOL 12-2009 Construction Equipment Ownership and Operating Expense Schedule Region XII《施工设备的所有权和运行费用表XII》.pdf》由会员分享,可在线阅读,更多相关《COE EP 1110-1-8 VOL 12-2009 Construction Equipment Ownership and Operating Expense Schedule Region XII《施工设备的所有权和运行费用表XII》.pdf(570页珍藏版)》请在麦多课文档分享上搜索。
1、 EP 1110-1-8 Volume 12 November 2009 Construction Equipment Ownership and Operating Expense Schedule Region XII Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Provided by IHSNot for ResaleNo reproduction or networking permitted without license from
2、IHS-,-,-DEPARTMENT OF ARMY U.S. Army Corps of Engineers Washington, DC 20314-1000 This pamphlet supersedes EP 1110-1-8, dated 31 July 2007. REPLY TO ATTENTION OF: CECW-EC Pamphlet 30 November 2009 No. 1110-1-8, Vol. 12 CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE 1. Purpose. This
3、pamphlet is authorized by and established in accordance with Federal Acquisition Regulation (FAR) 31.105 and Engineer Federal Acquisition Regulation (EFAR) SUBPART 31.105. This pamphlet establishes predetermined equipment ownership and operating expense rates for construction equipment. This pamphle
4、t also establishes a method to calculate equipment ownership and operating expense rates for construction equipment when the predetermined rates are not considered appropriate. The overall intent of this pamphlet is to determine equipment costs that are fair and reasonable. Expense factors for calcu
5、lating dredge plant and marine equipment costs are provided in chapter 4. 2. Applicability. This pamphlet applies to all USACE commands. It is applicable to all solicitations and contracts for construction expected to exceed the Simplified Acquisition Threshold of $100,000 when actual cost data for
6、both ownership and operating costs cannot be determined. This volume is for use in Region XII, which includes the following states: Kwajalein Island 3. References. See APPENDIX A. 4. Distribution Statement. Approved for public release, distribution is unlimited. FOR THE COMMANDER: 12 Appendixes STEP
7、HEN L. HILL (See Table of Contents) Colonel, Corps of Engineers Chief of Staff EP 1110-1-8, Vol. 1230 Nov 09Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-This page intentionally left blankEP 1110-1-8, Vol. 1230 Nov 09Provided by IHSNot for ResaleNo
8、 reproduction or networking permitted without license from IHS-,-,-iCONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE Table of Contents CHAPTER 1.0 - INTRODUCTION 1.1 Use 1-1 1.2 Decision Flow Process 1-1 1.3 How to Obtain Assistance 1-1 1.4 How to Obtain CHECKRATE Spreadsheet 1-2 1.5
9、How to Obtain this Publication. 1-2 CHAPTER 2.0 - METHODOLOGY FOR CONSTRUCTION EQUIPMENT SECTION I. GENERAL.2-1 2.1 Contents 2-1 2.2 Basis for Equipment Rates 2-1 2.3 Total Hourly Rate. 2-1 SECTION II. OPERATING CONDITIONS.2-2 2.4 Average, Difficult, or Severe Conditions 2-2 2.5 Determination of Con
10、dition 2-3 SECTION III. EQUIPMENT SELECTION2-3 2.6 General 2-3 2.7 Truck Selection 2-3 2.8 Crawler Tractor Selection 2-3 2.9 Equipment Accessories. 2-4 SECTION IV. EQUIPMENT VALUE .2-4 2.10 List Price and Accessories. 2-4 2.11 Discount Code (DC) 2-4 2.12 Sales or Import Tax . 2-4 2.13 Freight . 2-4
11、2.14 Total Equipment Value (TEV) 2-4 SECTION V. LIFE .2-5 2.15 Economic Life (LIFE). 2-5 2.16 Working Hours Per Year (WHPY) 2-5 SECTION VI. SALVAGE VALUE .2-5 2.17 Salvage Value (SLV) . 2-5 2.18 Salvage Value Percentage 2-5 EP 1110-1-8, Vol. 1230 Nov 09Provided by IHSNot for ResaleNo reproduction or
12、 networking permitted without license from IHS-,-,-iiCONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE Table of Contents (Continued) SECTION VII. OWNERSHIP COST2-6 2.19 Ownership Elements . 2-6 2.20 Depreciation 2-6 2.21 Facilities Capital Cost of Money (FCCM). 2-7 SECTION VIII. OPERAT
13、ING COST2-7 2.22 Operating Cost Elements 2-7 2.23 Fuel Cost . 2-8 2.24 Filters, Oil, and Grease (FOG) Cost 2-9 2.25 Repair Cost 2-10 2.26 Tire Wear Cost 2-12 2.27 Tire Repair Cost 2-13 SECTION IX. STANDBY HOURLY RATE2-14 2.28 Standby Hourly Rate . 2-14 SECTION X. RATE CALCULATION EXAMPLE2-14 2.29 Co
14、mputation Example . 2-14 CHAPTER 3.0 - ADJUSTMENTS TO HOURLY RATES SECTION I. GENERAL.3-1 3.1 Contents 3-1 3.2 Basis for Equipment Rates 3-1 3.3 Equipment Rate Adjustment Tables 3-1 3.4 Determination for Use of Equipment Rates in Tables 2-1 and 2-2.3-1 SECTION II. RATE ADJUSTMENTS3-2 3.5 Rate Adjust
15、ments 3-2 3.6 Changes in Operating Conditions 3-2 3.7 Change in Cost of Money Rate (CMR) 3-2 3.8 Actual Work Hours Greater than 40 Hours per Week 3-3 3.9 Changes in Fuel Cost 3-4 3.10 Adjustments to Fuel, Oil, and Grease (FOG) Cost 3-5 3.11 Equipment of Different Age than Table 2-1 . 3-5 3.12 Rate A
16、djustment for Overage Equipment 3-6 3.13 Standby Rate Adjustment for Equipment of a Different Age than Table 2-13-7 3.14 Equipment Purchased Used 3-8 3.15 Rate Calculation Examples 3-8 EP 1110-1-8, Vol. 1230 Nov 09Provided by IHSNot for ResaleNo reproduction or networking permitted without license f
17、rom IHS-,-,-iiiCONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE Table of Contents (Continued) CHAPTER 4.0 - METHODOLOGY FOR DREDGING PLANT AND MARINE EQUIPMENT SECTION I. GENERAL.4-1 4.1 Contents 4-1 4.2 General 4-1 SECTION II. ANNUAL USE4-1 4.3 Time Available to Dredge 4-2 SECTION II
18、I. LIFE 4-2 4.4 Life. 4-2 4.5 Annual Hours Available . 4-3 SECTION IV. SALVAGE VALUE .4-3 4.6 Salvage Value (SLV) . 4-3 SECTION V. OWNERSHIP COST4-3 4.7 Ownership Cost. 4-3 4.8 Depreciation Factor . 4-4 4.9 The Cost of Money Rate (CMR) Factor . 4-4 4.10 Other Ownership Elements 4-5 SECTION VI. OPERA
19、TING FACTORS 4-5 4.11 Hourly Operating Cost. 4-5 4.12 Prime and Secondary Power. 4-5 4.13 Water, Lube, and Supplies (WLS) . 4-6 4.14 Repairs (RPR) . 4-6 SECTION VII. STANDBY4-7 4.15 Standby Rate. 4-7 SECTION VIII. NEGOTIATED PROCUREMENT .4-7 4.16 Rates. 4-7 4.17 Allowance for Additional Capital Impr
20、ovements. 4-8 4.18 Overage Plant 4-8 4.19 Dredging Plant Purchased Used . 4-8 SECTION IX. RATE CALCULATION EXAMPLE .4-8 4.20 Rate Calculation Example . 4-8 EP 1110-1-8, Vol. 1230 Nov 09Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-ivCONSTRUCTION EQ
21、UIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE Table of Contents (Continued) List of Tables Table 2-1. Hourly Equipment Ownership and Operating Expense 2-21 Table 2-2. Hourly Rate Elements.2-253 Table 3-1. Equipment Age Adjustment Factors .3-9 Table 3-2. Equipment Age Adjustment Factors .3-33 Tabl
22、e 4-1. Dredging Plant Cost Factors 4-9 List of Figures Figure 1-1. Methodology for Developing an Hourly Ownership and Operating Rate for Construction Equipment1-3 Figure 2-1. Equipment Rate Computation Worksheet .2-15 Figure 3-1. Total Hourly Rate Calculation for Overage Equipment3-25 Figure 3-2. St
23、andby Hourly Rate Calculation for Overage Equipment.3-49 Figure 4-1. Months Available by Region4-2 Figure 4-2. Dredging Plant Ownership and Operating Rate Worksheet 4-13 List of Appendixes Appendix A References .A-1 Appendix B Area Factors .B-1 Appendix C Guide for Selecting Operating Conditions C-1
24、 Appendix D Equipment Hourly Calculation Factors. D-1 Appendix E Economic Indexes for Construction Equipment E-1 Appendix F Tire Description and Tire Cost F-1 Appendix G Tire Life and Tire Wear Factors . G-1 Appendix H Manufacturer List . H-1 Appendix I Federal Cost-of-Money Rate I-1 Appendix J Equi
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- COEEP111018VOL122009CONSTRUCTIONEQUIPMENTOWNERSHIPANDOPERATINGEXPENSESCHEDULEREGIONXII 施工 设备 所有权 运行 费用

链接地址:http://www.mydoc123.com/p-620661.html