1、PMP 资格认证考试-项目时间管理(二)及答案解析(总分:20.00,做题时间:90 分钟)一、单项选择题(总题数:20,分数:20.00)1.If task A has seven days of free float and 15 days of total float and the early start date is delayed 5 days, what does this do to the completion date of the project?A) Pushes the finish date out ten days.B) Delays the early sta
2、rt date of the next dependent task five days.C) Allows the project to finish five days earlier.D) The finish date doesnt change.(分数:1.00)A.B.C.D.2.If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected?A) The
3、 next dependent tasks start date will be delayed 15 days.B) The duration of the task will be shortened 15 days.C) The completion date of the project will be pushed out 5 days.D) Both A and C.(分数:1.00)A.B.C.D.3.If Task C has 0 days of free float and 0 days of total float, what does this mean to the p
4、roject?A) The project does not have adequate lead and lag times built in.B) The task is on the critical path.C) The duration of the task should be compressed.D) The dates for the task are not accurate.(分数:1.00)A.B.C.D.4.A master schedule is delayed or an executive presentation. What information must
5、 the PM gather to complete this schedule?A) Dates of major activities.B) Key milestones.C) Summary level task descriptions.D). All of above.(分数:1.00)A.B.C.D.5.What is one of the key problems with using crashing rather than fast tracking to compress project duration?A) Personnel overlap.B) Budget con
6、straints.C) Sub-dividing critical path tasks to work in parallel.D) Finish to start relationships are modified.(分数:1.00)A.B.C.D.6.Time planning _.A) involves determining how the various tasks required to completed the project, and the activities within the tasks, will be accomplished in terms of seq
7、uence and dependencyB) refers to setting up the vacation schedule for each member of the project teamC) is the sole responsibility of the project scheduling departmentD) is having a well staked scheduling department(分数:1.00)A.B.C.D.7.A prerequisite of effective time management is _.A) knowing the di
8、ctated project completion dateB) having the most advanced software package for project planning, scheduling, and controlC) having a good project WBS which identifies the major project deliverables and tasks, and the person responsible for each of themD) having a well staffed scheduling department(分数
9、:1.00)A.B.C.D.8.Slack time is _.A) a way of decreasing the time required for decision makingB) not used to level resourcesC) the same as float timeD) used to assist in developing a timetable of the major components of a schedule(分数:1.00)A.B.C.D.9.Network planning (PERT/ CPM/PDM) methods _.A) are usu
10、ally too complicated for practical use on most projectsB) require highly trained specialists for effective useC) always require computer support to be practicalD) are based on flow charts and they allow observation of what happens to the project schedule when changes occur to a tasks start and stop
11、dates(分数:1.00)A.B.C.D.10.The critical path _.A) is the earliest series of events and activities which have the highest technical risk in the projectB) is the series of events and activities which have the highest cost in the projectC) is the longest chain of events and activities from todays date to
12、 the end of the project, if the plan represented by the current network plan is executedD) is an interesting concept, but is has little significance to the project functional managers assigned to the project(分数:1.00)A.B.C.D.11.Trending is _.A) the practice of keeping up with the latest fashions in p
13、roject management (newest software packages, terms, concepts, etc)B) recording and evaluating the trends regarding schedule accomplishment, resource expenditures, and forecasting the impacts of the trends on the future work and ultimate completion of the projectC) generally impractical and not very
14、useful on larger projectsD) when the project manager determines the degree to which the schedule is meeting expectations(分数:1.00)A.B.C.D.12.The work breakdown structure(WBS) used in the classical sense is a practical methodology used for _.A) adding activities to the projectB) expanding the scope of
15、 the projectC) developing a responsibility matrix for work assignmentsD) delineating project work effort into discrete and logical sub-elements(分数:1.00)A.B.C.D.13.The expected time TE used in the PERT algorithm is calculated using the following equation _.A) (a+3m+b)/6B) (a+4m+b)/6C) (a+5m+b)/6D) (a
16、+m+b)/3Note: A major assumption for all network methods is that activity durations are statistically dependent and where a=most optimistic time, b=most pessimistic time, m=most likely time.(分数:1.00)A.B.C.D.14.In order to compute the probability of completing a project on time, the standard deviation
17、s (SD) of each activity must be known. These can be calculated using the following expression _.A) SD=(b-a)/6B) SD=b-a/6C) SD=(a-b)/6D) SD=(b-a)/12Note: The definitions of a=most optimistic time and b=most pessimistic time. Use the following information for questions 10 and 11 for the following is d
18、uration data related to an activity in a time scale network.Optimistic time=a=10 daysPessimistic time=b=20 daysMost likely time=m=12 days(分数:1.00)A.B.C.D.15.Using this data, what is the expected time for this activity?A) 12 days.B) 13 days.C) 17 days.D) 16 days.(分数:1.00)A.B.C.D.16.The standard devia
19、tion for the activity is _.A) 1.66 daysB) 5.00 daysC) 3.88 daysD) 6.05 days(分数:1.00)A.B.C.D.17.The difference between a project and a program is that the _.A) program has many projectsB) Project is typically longer than a programC) program is another name for processD) both B and C(分数:1.00)A.B.C.D.1
20、8.If you were crashing a project, you would focus attention on _.A) all non-critical tasksB) only those on the critical path without concern for costC) accelerating performance by minimizing costD) the critical task with the least cost first(分数:1.00)A.B.C.D.19.What is the key purpose of using projec
21、t control?A) Ensuing the project stays on track.B) To have a good WBS.C) To satisfy the customer.D) To assist in developing the upper management reports.(分数:1.00)A.B.C.D.20.Gantt charts are great for _.A) showing task relationshipsB) tracking actual versus plannedC) good communications with the cust
22、omers, management, and project teamD) B and C(分数:1.00)A.B.C.D.PMP 资格认证考试-项目时间管理(二)答案解析(总分:20.00,做题时间:90 分钟)一、单项选择题(总题数:20,分数:20.00)1.If task A has seven days of free float and 15 days of total float and the early start date is delayed 5 days, what does this do to the completion date of the project?A
23、) Pushes the finish date out ten days.B) Delays the early start date of the next dependent task five days.C) Allows the project to finish five days earlier.D) The finish date doesnt change.(分数:1.00)A.B.C.D. 解析:由于自由时差和总时差都大于 5,所以最早开始时间延迟 5 天将不影响项目完成。如果任务 A 有 7 天的自由时差和 15 天的总时差,最早开始时间延迟了 5 天,这对项目的完成有什
24、么样的影响?A) 将完工期限推迟 10 天。B) 推迟下一个相关任务最早开始日期 5 天的时间。C) 使项目提前 5 天完成。D) 完工时间不变。2.If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected?A) The next dependent tasks start date will be delayed 15 days.B) The duration
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 时间 管理 答案 解析 DOC