1、Lessons Learned Entry: 0978Lesson Info:a71 Lesson Number: 0978a71 Lesson Date: 2000-03-25a71 Submitting Organization: GSFCa71 Submitted by: Kevin GradySubject: End-to-End Testing Description of Driving Event: The successful early mission on-orbit space-to-ground communications between the Terra spac
2、ecraft and the EOS Control Center is a reaffirmation of the value of rigorous pre-launch end-to-end testing. The Terra mission has experienced virtually trouble-free space-to-ground communications from launch and ascent, through the present completion of instrument activation. This success is a dire
3、ct product of the mandate to perform rigorous end-to-end testing prior to launch.Lesson(s) Learned: The Terra development schedule had always planned to perform end-to-end testing between the spacecraft and the EOS control center as soon as the ground system was capable of such testing. The initial
4、test between the satellite and the ground system was in fact conducted while the spacecraft was in spacecraft-level thermal/vacuum test. The Terra housekeeping command and control links were exercised, just prior to completion of the Terra thermal/vacuum test. Due to unforeseen problems in the launc
5、h vehicle and the ground system, this initial test would prove to be almost two years before the launch of Terra.When the decision was made to change the implementation of the Terra ground system, due to the fact that a number of technical problems were not reaching resolution, the resolve to execut
6、e rigorous end-to-end testing became even more critical. A decision was made in the fall of 1998 to incorporate a new control center software package. The software was planned for completion in the spring, with the launch of Terra scheduled for the summer.Schedule pressures could have forced a lesse
7、r amount of allocated time for end-to-end testing, however the Project adopted the philosophy that no rigor be compromised, and a comprehensive test flow was adopted. Where early testing was possible with preliminary deliveries of the ground Provided by IHSNot for ResaleNo reproduction or networking
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS09782000LESSONSLEARNEDENDTOENDTESTINGPDF

链接地址:http://www.mydoc123.com/p-1018623.html