GEIA HB-748-1-2004 Handbook The Program Managers Guide to the Integrated Baseline Review Process《手册 项目管理者 综合基线审查过程指南》.pdf
《GEIA HB-748-1-2004 Handbook The Program Managers Guide to the Integrated Baseline Review Process《手册 项目管理者 综合基线审查过程指南》.pdf》由会员分享,可在线阅读,更多相关《GEIA HB-748-1-2004 Handbook The Program Managers Guide to the Integrated Baseline Review Process《手册 项目管理者 综合基线审查过程指南》.pdf(26页珍藏版)》请在麦多课文档分享上搜索。
1、GEIA ENGINEERING BULLETIN Handbook: The Program Managers Guide to the Integrated Baseline Review Process GEIA HB-748-1 May 2004 GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION A Sector of the Electronic Industries Allianc Copyright Government Electronics Provides an invaluable opportun
2、ity to compare PMs expectations, and to address differences before problems arise; Provides project management teams with a thorough understanding of the project plan and its risks, allowing early intervention and the application of resources to address project challenges; and Increases confidence i
3、n the project PMB, which provides a powerful, proactive, program management capability to obtain timely and reliable cost and schedule projections . Additional, continuing benefits to the PMs, once a PMB has been established and the IBR Process has been implemented, include the following: Management
4、 insight. Enables the principles of management by exception and improves problem traceability rather than require continuous oversight of all tasks. 0 Early warning. Indicates potential problems early. Earned value management. Enables management to quantify the impact of known problems, to measure w
5、ork accomplished, and to obtain realistic estimates at completion. 1.2 Key Elements The key elements in the IBR Process are the following: The IBR Process establishes and maintains a mutual understanding of the PMB and mitigates program risk. (page 3) 0 0 Preparation for the IBR should begin as soon
6、 as practical. (page 7) Copyright Government Electronics action risks should be incorporated into the project risk management planning. (page 12) Management processes provide the PMs with a continuous source of project information that enables mutual understanding and the reduction or elimination of
7、 the need for future IBRs. (page 14) 2 Copyright Government Electronics and may include subcontractor, as well as prime contractor entities. 2.2 The IBR Guide This guide identifies the purpose of the IBR Process and conveys the need for a continuous IBR process environment. It integrates the IBR wit
8、h risk management. Identifying and mitigating risks, including those associated with the PMB and management processes, is essential to successful project completion. This guide is neither a how-to nor a step-by-step tool kit for executing an IBR. The IBR is only one element in a series of management
9、 activities that comprise the IBR Process. This guide discusses theframework within which the project or program managers employ the IBR. In so doing, this Guide will improve the overall understanding of the total IBR Process, and enhance its contribution to program success. 4 Copyright Government E
10、lectronics at other times, nominal management activities or events may drive a change. Examples of such program dynamics include contract award, 5 Copyright Government Electronics Provide an adequate number of qualified personnel to serve as IBR team members; Specify evaluation criteria for risk are
11、as; Document risk issues identified during an IBR; and Monitor progress on required actions until issues are resolved. 4.6 Training Training is essential to ensure that the IBR team can identify and adequately assess the project risk. The PMs should conduct joint training in which all members of the
12、 IBR team participate. The training should provide enough information so that the team can mutually understand the cost, schedule, technical, and management processes used on the project. The essential elements of training include the following: 1. PMsS Expeetations IBR objectives 0 IBR approach and
13、 expectations 0 Risk identification and documentation 9 Copyright Government Electronics Key schedule milestones are identified; Supporting schedules reflect a logical flow to accomplish the technical work scope; 11 Copyright Government Electronics Tasks are planned and can be measured objectively,
14、relative to technical progress; Underlying PMB rationales are reasonable; and Managers have appropriately implemented required management processes. Additionally, the IBR team should assess the management reserve with respect to project risk not accounted for in the PMB. To evaluate project PMB risk
15、s, the IBR team should assess the degree to which the project attains the above objectives. 5.3 IBR Closeout 5.3.1 PM Responsibilities After completing the IBR, the PMs should assess whether they have achieved the purpose of the IBR: 0 Have they gained a mutual understanding of the project PMB? Have
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- GEIAHB74812004HANDBOOKTHEPROGRAMMANAGERSGUIDETOTHEINTEGRATEDBASELINEREVIEWPROCESS 手册 项目 管理者 综合 基线 审查

链接地址:http://www.mydoc123.com/p-754561.html