ASHRAE OR-16-C011-2016 Design-Build Successes and Challenges for the Byron G Rogers Federal Office Building.pdf
《ASHRAE OR-16-C011-2016 Design-Build Successes and Challenges for the Byron G Rogers Federal Office Building.pdf》由会员分享,可在线阅读,更多相关《ASHRAE OR-16-C011-2016 Design-Build Successes and Challenges for the Byron G Rogers Federal Office Building.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、Michelle L Swanson is a Mechanical Engineer and Project Manager with The RMH Group in Lakewood, CO.Design-Build Successes and Challenges for the Byron G. Rogers Federal Office Building Michelle L. Swanson, PE ASHRAE Member ABSTRACT The design-build construction method presents opportunities and chal
2、lenges to all the groups involved in a construction project. This paper will explore how the mechanical and electrical designers and contractors addressed these opportunities and challenges for the recent Byron G. Rogers Federal Office Building modernization project in downtown Denver, Colorado. The
3、 project involved approximately 500,000 square feet of renovation and deep energy retrofit in an existing high-rise building which is anticipated to to be added to the National Register of Historic Places in the future. The project team was challenged to rebuild the entire mechanical/electrical infr
4、astructure while maintaining the historic exterior faade and keeping the adjoining courthouse operational which has mechanical/electrical systems fed from the office building. Because the building provides office space for multiple government agencies, the design-build team was tasked with coordinat
5、ing the differing agencies requirements and schedules to complete their spaces. The building owner, the General Services Administration, had very aggressive energy-saving goals; one of these goals was for the projects lighting to be 100% LEDs, which presented a challenge due to the lack of commercia
6、lly available LED fixtures in 2010. The project team consisted of a general contractor, who held the contracts for the architectural and structural designers and for the mechanical and electrical contractors. The mechanical and electrical contractors held the contracts with the respective mechanical
7、 and electrical designers. INTRODUCTION Located in downtown Denver, Colorado, the 18-story, 494,000-square-foot (45,894-square meters) office building is home to more than 20 federal agencies/sub-agencies and serves as an important example of 1960s-era federal architecture. Due to its age and condit
8、ion, the building was selected to receive funding for a complete remodel through the 2009 American Reinvestment and Recovery Act (ARRA). Because the General Service Administration (GSA) received additional ARRA funding strictly to incorporate emerging energy efficiency technologies such as LED light
9、ing into the design, the GSA established aggressive sustainability targets well beyond federal requirements for the project. The challenge of meeting these sustainability targets was complicated by having to preserve the architectural elements and characteristics of the era in which this historic bu
10、ilding was built. The GSA selected design-build as the project delivery method. Design-build is a project delivery method in which both design and construction services are simultaneously contracted to Figure 1 The 18-story office building is located in downtown, Denver, Colorado. a single entity. T
11、his is in contrast to the more traditional design-bid-build project delivery method in which the project owner contracts with separate entities for the design and construction portions of a project; the construction portion of a design-bid-build project is usually bid to a construction entity after
12、the design has been completed. Various metrics and studies have shown that design-build delivery can be completed with decreased costs and in a shorter time frame than with design-bid-build project delivery. Both delivery methods can result in quality projects; building owners needs to weigh differe
13、nt variables when determining which project delivery methods are most appropriate for their individual projects. THE PROCESS In 2009, the GSA released a Request for Qualifications (RFQ) document for design-build teams to renovate the office building. At the time, the team (which would ultimately be
14、selected for the project) was led by a general contractor with architectural, structural, historic preservation, mechanical, plumbing and electrical design partners. The team presented an innovative overall design solution to assist the GSA in meeting federal sustainability mandates and delivering a
15、n energy efficient and inviting place to work in the GSA property portfolio. After being selected for the renovation project, the team worked with the GSA to tailor its design-bid-build standards to accommodate design-build project delivery. Although some standards were easily modified, others were
16、required by the GSA to remain the same, which presented challenges to the project team. As the process progressed, the design-build team worked with the GSA and multiple tenant agencies to work through numerous issues including meeting ARRA funding regulations for the project. Complicating the matte
17、r was the fact that some federal agencies and sub-agencies were not planning to return to the building after the renovation. Understanding and documenting all parties needs and desires for the project presented an interesting and sometimes overwhelming task. The project team spent time educating the
18、 groups that the project would not be hard bid, which was different from what most of the participating groups had experienced before. Although the project primarily followed a design-build structure, some changes had to be made to allow for some products and subcontractors to be hard bid. PROJECT C
19、HALLENGES Like any construction project, this one was not free from challenges; however, the team worked through many project issues to deliver a successful project. The way the mechanical and electrical contractors were brought onto the project presented a major challenge for the design team. Durin
20、g the schematic design phase of the project, the general contractor selected the mechanical and electrical contractors from the trade partners that were assisting with the budgeting of the renovation during the proposal phase. The mechanical and electrical contractor pricing was based on the proposa
21、l-level narrative and the very few drawings developed during the proposal phase not on the current, continuously developing design drawings. The mechanical and electrical contractors submitted a hard-bid number to the general contractor for every deviation from the proposal-level narrative; however,
22、 the overall project budget could not change. Because of this scenario, the engineers were required to find other items to value engineer to pay for the changes. For example, as the design evolved, we discovered a need for larger domestic water heaters than were originally planned. The mechanical en
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAEOR16C0112016DESIGNBUILDSUCCESSESANDCHALLENGESFORTHEBYRONGROGERSFEDERALOFFICEBUILDINGPDF

链接地址:http://www.mydoc123.com/p-455736.html