《ASD-STAN PREN 9200-2001 Aerospace Series Programme Management Guidelines for Project Management Specification (Edition P 1)《航空航天系列 项目管理 项目管理规范指引 第P1版》.pdf》由会员分享,可在线阅读,更多相关《ASD-STAN PREN 9200-2001 Aerospace Series Programme Management Guidelines for Project Management Specification (Edition P 1)《航空航天系列 项目管理 项目管理规范指引 第P1版》.pdf(44页珍藏版)》请在麦多课文档分享上搜索。
1、AECMA STANDARD NORME AECMA AECMA NORM Edition approved for publication prEN 9200 Edition P 1 December 2001 Comments should be sent within six months after the date of publication to Procedure and Process Domain PUBLISHED BY THE EUROPEAN ASSOCIATION OF AEROSPACE INDUSTRIES - STANDARDIZATION (AECMA-ST
2、AN) Gulledelle 94 - 8-1200 BRUXELLES - Tel. (+32) 2 775 81 10 - Fax. (+32) 2 775 81 11 ICs: Descriptors: ENGLISH VERSION Aerospace series Programme management Guidelines for project management specification Srie arospatiale Luft- und Raumfahrt Recommandation Richtlinie Management de programme Progra
3、mm-Management pour une spcification de management de projet fr eine Projektmanagement-Spezifikation This “Aerospace Series“ Prestandard has been drawn up under the responsibility of AECMA-STAN (The European Association of Aerospace Industries - Standardization). It is published on green paper for th
4、e needs of the European Aerospace Industry. It has been technically approved by the experts of the concerned Domain following member comments. Subsequent to the publication of this Prestandard, the technical content shall not be changed to an extent that interchangeability is affected, physically or
5、 functionally, without re-identification of the standard. Afer examination and review by users and formal agreement of AECMA-STAN it will be submitted as a draft European Standard to CEN (European Committee for Standardization) for formal vote. 2001-12-28 AECM A-STAN Gulledelle 94 8-1200 BRUXELLES M
6、r Zagonel 1 I aecma 200 Page 2 prEN 9200: 2001 Contents Page O 1 2 3 4 5 6 6.1 6.2 6.3 6.4 6.5 6.6 7 7.1 7.1 . 1 7.1.2 7.1.3 7.2 7.2.1 7.2.2 7.2.3 7.2.4 7.3 7.3.1 7.3.2 7.4 7.4.1 7.4.2 7.4.3 7.4.4 7.4.5 8 8.1 8.2 8.3 8.3.1 8.3.2 8.4 8.5 8.6 8.7 9 9.1 9.2 9.3 9.4 9.5 9.6 Normative references . Terms
7、and Definitions . Project objectives . . Resource assessment Project business case Project planning Purpose Application to all the Management plan . Purpose . Requirements relating to the project progress evaluation Setting-up of the wor . . Purpose Risk management Purpose . . Organisation of the ri
8、sk management . Risk identification . Lessons learnt . Systematic analysis . Risk evaluation and characterisation Risks management process Human factor Configuration management Purpose . Configuration Management processes Configuration Identification Establishment of Configuration Baselines Configur
9、ation Contro Configuration Status 4 4 6 6 6 15 15 15 16 16 16 16 16 17 17 17 17 17 18 18 18 19 19 20 20 20 21 21 21 22 23 24 24 24 24 25 25 25 25 25 26 26 26 26 27 27 27 28 28 Page 3 prEN 9200: 2001 9.7 9.8 io 10.1 10.2 10.3 10.4 10.4.1 10.4.2 10.4.3 10.4.4 Il 11.1 11.2 11.2.1 11.2.2 11.2.3 11.3 11.
10、3.1 1 1.3.2 11.4 11.4.1 1 1.4.2 12 12.1 12.1.1 12.1.2 12.2 12.2.1 12.2.2 12.2.3 12.2.4 12.3 13 13.1 13.2 13.3 13.4 13.5 13.6 14 14.1 14.2 14.3 14.4 14.5 15 15.1 15.2 15.3 Annex A Annex B Configuration Review/Audit Configuration Management Plan . Documentation management . List of documents to be app
11、lied and reference documents . Documentation management plan Documentation management requirements . Documentation management Documentation identification Document validation . Management requirements due to the systems engineering activities RAMS (Reliability - Availability . Maintainability . Safe
12、ty) . . . . . Technical performance control . Performance optimisation . Verification and validation, justification and qualification . Schedule control . Resource Management . General . Resource Assessment Resource Acquisition / Staffmg of the Project Resource Allocation . Training/Development o Fa
13、cilities and Infrastructure Quality assurance Purpose Requirements of quality assurance in a project . Quality assurance plan . . Project organisation . Project quality assurance au . Project Closure . Scheduled Project Closure . Unscheduled closure of the project (informative) Bibliography . Genera
14、l . (informative) Documents of accompaniment . 28 28 29 29 29 29 29 29 29 30 30 31 31 31 31 31 32 33 33 33 34 34 34 35 35 35 35 36 36 36 37 37 38 38 38 38 38 39 39 39 39 39 40 40 40 40 40 40 41 41 42 43 Page 4 prEN 9200: 2001 O Foreword Project management aims at planning, monitoring and control of
15、all aspects of a project, and the motivation of all those involved in it, to achieve the project objectives, on time and to the specified cost, quality and performance. It requires: - the definition of the activities, - the roles and the responsibilities for the various actors, - consistency between
16、 their activities, - capacity for communication between them, - a stable and rigorous project organisation. To achieve these objectives, the present document describes the key best practices for the management of an aerospace project, to be adapted specifically for each particular project to be mana
17、ged. In this standard, the customer is either an external identified customer, or an internal entity within the organisation, in charge of receiving or accepting the product. Additionally, this standard may also be used as a basis for the relationship between customers and suppliers at any level of
18、the supply chain. Prior to contract negotiations, the customer will issue a management specification, against which a supplier will submit a management plan. This document will assist in that process by indicating the major issues presented in both documents. The customers in charge of the establish
19、ment of the project management specification should be aware that any management requirement has an impact on the costs and that, as in the case of the requirements for a product, the minimum acceptable requirements should be an objective. The project management specification is to be established wi
20、th the objective of achieving the highest effectiveness in this discipline. In particular, attention is drawn to the possibility for suppliers to use, to the maximum extent, their own internal methods and procedures, in order to obtain quality, reliability and limitation of costs, provided internal
21、procedures meet this recommendation. I Scope For a given aerospace project, the present document is intended to be used as a reference to current best practices. These can be used as a guideline for the creation and negotiation of the project management specification between a customer and a supplie
22、r, and hence lead to the creation of the project management plan. It may be used for any project utilising several actors at different levels. In particular in the case of large projects it presents provisions recommended for the management of a project according to (see figure 1): - project organis
23、ation, - work breakdown structure, - phasing and scheduling, - risk management, - configuration management, - documentation management, - interfaces with other disciplines, - project monitoring and control, - technical performance control, - cost control, - schedule control, - resource management, -
24、 quality assurance, - project closure. Page 5 prEN 9200: 2001 PROJECT MANAGEMENT ., - Risk management (clause 8) 4 Configuration management (clause 9) Documentation management (clause IO) Interfaces with other disciplines (clause 11) +- I / 8 u Quality assurance (clause 14) I I Technical performance
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASDSTANPREN92002001AEROSPACESERIESPROGRAMMEMANAGEMENTGUIDELINESFORPROJECTMANAGEMENTSPECIFICATIONEDITIONP1

链接地址:http://www.mydoc123.com/p-453773.html