1、PMP 资格认证考试-项目整合管理(二)及答案解析(总分:20.00,做题时间:90 分钟)一、单项选择题(总题数:20,分数:20.00)1.Your preferred resource is not available at the time needed. What is the BEST thing to do?A) Negotiate with management to get the resource. The management is responsible for provision of resources for the project.B) Assess your
2、alternatives.C) Begin the task early.D) Use reserves to increase resources assigned to those tasks.(分数:1.00)A.B.C.D.2.You are assigned to be the project manager in the middle of the project. The project is within tolerances for the baseline, but the customer is not happy with the performance of the
3、project. What is the FIRST thing you should do?A) Discuss it with the project team.B) Recalculate baselines.C) Renegotiate the contract.D) Meet with the customer.(分数:1.00)A.B.C.D.3.When is integration performed?A) Project planning.B) Project execution.C) At key interface points.D) At the end of each
4、 project management phase.(分数:1.00)A.B.C.D.4.When should the project baseline be changed?A) It should not he changed.B) Only for changes that have been approved by the change control board.C) At each project team meeting.D) For all implemented changes.(分数:1.00)A.B.C.D.5.A project manager has made a
5、change to the project. What should he do next?A) Assign resource.B) Revise the project plan.C) Evaluate impact.D) Request change control board involvement.(分数:1.00)A.B.C.D.6.Your project team identified six related projects with major dependencies on your deliverables. Some of these projects have a
6、very similar scope and may overlap with your deliverables. In Light of this, which of the following should you be MOST concerned about?A) Scope change control.B) Scope verification.C) Risk response planning.D) Communications planning.(分数:1.00)A.B.C.D.7.You are assigned as a project manager to lead a
7、 new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST?A) A process assurance plan.B) A quality management plan.C) A project management plan.D) A project scope statement.(分数:1.00)A.B.C.D.8.All of following should be done b
8、y the project manager during project control EXCEPT _.A) determine that a change has occurredB) ensure that a change is agreedC) make sure all changes are approved by managementD) manage changes as they occur(分数:1.00)A.B.C.D.9.The project charter is created by _.A) the project managerB) upper manage
9、mentC) the vice president over a functional management groupD) the customer(分数:1.00)A.B.C.D.10.Clearly defined project objectives will _.A) provide a participate work environmentB) not cause lengthy delays over trivial issuesC) result in poor project decision makingD) reduce risk by providing an abs
10、olute value which firmly defines project success or failure(分数:1.00)A.B.C.D.11.Having the client assist in the project planning _.A) is not always recommended since the client does not have adequate knowledge of project managementB) enables better planning since they are familiar with project insigh
11、tsC) provides only some understanding, but usually the client dealing with the project has only limited authorityD) usually confuses the situation(分数:1.00)A.B.C.D.12.What must be in place prior to establishing change control on a project?A) Project charter.B) Work Breakdown Structure.C) Baseline.D)
12、Statement of Work.(分数:1.00)A.B.C.D.13.The causes of variances and the reasoning behind the corrective action chosen are summarized in the _.A) work Breakdown StructureB) accounting codes for the activitiesC) lessons learnedD) performance reports(分数:1.00)A.B.C.D.14.In a project environment, functiona
13、l managers are responsible for _.A) acting as a sounding board for clarification of critical issuesB) establishing administrative policiesC) outlining time, cost and performance constrainsD) identifying and developing mitigation strategies for areas of risk(分数:1.00)A.B.C.D.15.The owner (buyer) of a
14、project usually has the right to direct changes to the scope of work while the project work is being accomplished. Often, the owner will orally request a change and insist that the change be initiated immediately without the normal documentation (e.g.a change order). When the change be initiated wit
15、hout documentation _.A) the owner assumes all responsibility for paying for the change although the owner may at a later not want the changeB) the owner assumes responsibility for one-half the cost of the change until the documentation is completed and all at the same timeC) the project manager assu
16、mes all risk for the change, if initiated, until the documentation is receivedD) the project manager assumes only the risk of misinterpreting the owners oral change directive, while the owner assumes responsibility for paying for the request change(分数:1.00)A.B.C.D.16.Which one of the following is NO
17、T a trade-off decision that must be made in the development of the project plan?A) Whether to use skilled or unskilled laborers.B) The amount of profit vendors should make versus the profit other vendors have received in the past.C) Manufacturing in-house or sub-contracting out the work.D) The impor
18、tant of cost versus quality.(分数:1.00)A.B.C.D.17.The internal communication linkages are the most important to the health of the project. Which of the following is one of the major diving forces for effective communication in a project?A) OptimizationB) DifferentiationC) SelectionD) Integration(分数:1.
19、00)A.B.C.D.18.A project plan is _.A) a formal, approved document used to guide both project execution and project controlB) a document issued by senior management that provides the product manager with the authority to apply organization resources of the companyC) a document description the organiza
20、tional breakdown structure of the companyD) a narrative description of products or services to be supplied(分数:1.00)A.B.C.D.19.Controlling occurs _.A) on a continual basis throughout the projectB) at the end of each phase of the project life cycle to assess its success in meeting project objectivesC)
21、 at the end of each planning processD) on a continual basis throughout the executing process and as needed in the other process(分数:1.00)A.B.C.D.20.The project plan is used to do all of the following EXCEPT _.A) document project planning assumptionB) define the content of management reviewsC) identif
22、y risks that arise during project executionD) provide a baseline for progress measurement and project control(分数:1.00)A.B.C.D.PMP 资格认证考试-项目整合管理(二)答案解析(总分:20.00,做题时间:90 分钟)一、单项选择题(总题数:20,分数:20.00)1.Your preferred resource is not available at the time needed. What is the BEST thing to do?A) Negotiate
23、with management to get the resource. The management is responsible for provision of resources for the project.B) Assess your alternatives.C) Begin the task early.D) Use reserves to increase resources assigned to those tasks.(分数:1.00)A.B. C.D.解析:(评估后再做决策)。尽管管理层负责项目的资源供给,这种职责指的是资源的量或可用性,但是资源冲突是项目管理中一种
24、严重的冲突。选项 C、D 是一种备选方案,不具有代表性。你首选资源在需要时不能使用。最好应该怎么做?A) 为得到该资源,与管理层谈判。B) 评估你的可选方案。C) 早点进行该项任务。D) 动用储备,增加分配给那些任务的资源。2.You are assigned to be the project manager in the middle of the project. The project is within tolerances for the baseline, but the customer is not happy with the performance of the proj
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 整合 管理 答案 解析 DOC