VA 26 24 11-2009 DISTRIBUTION SWITCHBOARDS.pdf
《VA 26 24 11-2009 DISTRIBUTION SWITCHBOARDS.pdf》由会员分享,可在线阅读,更多相关《VA 26 24 11-2009 DISTRIBUTION SWITCHBOARDS.pdf(12页珍藏版)》请在麦多课文档分享上搜索。
1、4-09 26 24 11 - 1 SECTION 26 24 11 DISTRIBUTION SWITCHBOARDS SPEC WRITER NOTE: Delete between / - / if not applicable to project. Also delete any other item or paragraph not applicable to the section and renumber the paragraphs. Use this section for individual switchboards or in conjunction with Sec
2、tion 26 11 16, SECONDARY UNIT SUBSTATIONS. PART 1 - GENERAL 1.1 DESCRIPTION This section specifies the furnishing, installation, and connection of the distribution switchboards. 1.2 RELATED WORK /A. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS: Requirements for Seis
3、mic Restraint for Nonstructural Components./ B. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: General electrical requirements and items that are common to more than one section of Division 26. C. Section 26 05 21, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 VOLTS AND BELOW
4、): Cables and wiring. D. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS: Requirements for Personnel Safety and to provide a low impedance path for possible fault currents. E. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduit and outlet boxes. F. Section 26 05 71, EL
5、ECTRICAL SYSTEM PROTECTIVE DEVICE STUDY: Coordination study of overcurrent protection devices. G. Section 26 09 13, ELECTRICAL POWER MONITORING AND CONTROL: For metering devices integral to the distribution switchboards. H. Section 26 11 16, SECONDARY UNIT SUBSTATIONS: Switchboards as part of second
6、ary unit substation. I. Section 26 25 11, BUSWAYS: Feeder busway and fittings. /J. Section 26 27 13, ELECTRIC METERING: For revenue metering devices integral to the distribution switchboards./ K. Section 26 43 13, TRANSIENT-VOLTAGE SURGE SUPPRESSION: TVSS equipment for distribution switchboards. 1.3
7、 QUALITY ASSURANCE Refer to Paragraph, QUALIFICATIONS, in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-4-09 26 24 11 - 2 1.4 FACTORY TESTS A. Distribution switchboards shall be thoroughl
8、y tested at the factory to assure that there are no electrical or mechanical defects. Tests shall be conducted as per NEMA PB 2 and UL 891. Factory tests shall be certified. B. The following additional tests shall be performed: 1. Verify that circuit breaker sizes and types correspond to drawings an
9、d coordination study. 2. Verify tightness of bolted electrical connections by calibrated torque-wrench method in accordance with manufacturers published data. /3. Confirm correct operation and sequencing of electrical and mechanical interlock systems by attempting closure on locked-open devices, and
10、 attempting to open locked-closed devices, and making key exchange with devices operated in off-normal positions./ 4. Exercise all active components. 5. Perform a dielectric withstand voltage test on each bus section, each phase-to-ground with phases not under test grounded, in accordance with manuf
11、acturers published data. 6. Perform insulation-resistance tests on control wiring with respect to ground. Applied potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated cable, or as required if solid-state components or control devices cannot tolerate the appli
12、ed voltage. 7. If applicable, verify correct function of control transfer relays located in the switchboard with multiple control power sources. 8. Perform phasing checks on double-ended or dual-source switchboards to insure correct bus phasing from each source. C. Furnish four (4) copies of certifi
13、ed manufacturers factory test reports to the Resident Engineer prior to shipment of the switchboards to ensure that the switchboards have been successfully tested as specified. /D. The Government shall have an option to witness the factory tests. All expenses of the Government Representatives trips
14、to witness the testing will be paid by the Government. Notify the Resident Engineer not less than 30 days prior to making tests at the factory./ 1.5 SUBMITTALS Submit in accordance with Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: A. Shop Drawings: 1. Sufficient information, clearly
15、presented, shall be included to determine compliance with drawings and specifications. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-4-09 26 24 11 - 3 2. Include electrical ratings, dimensions, mounting details, materials, required clearances, term
16、inations, weight, temperature rise, wiring and connection diagrams, plan, front, side, and rear elevations, sectional views, bus work, circuit breaker frame sizes, trip and short-circuit rating, long-time, short-time, instantaneous and ground fault settings, coordinated breaker and fuse curves, acce
17、ssories, and device nameplate data. 3. Show the size, ampere-rating, number of bars per phase and neutral in each bus run (horizontal and vertical), bus spacing, equipment ground bus, and bus material. B. Manuals: 1. Submit, simultaneously with the shop drawings, companion copies of complete mainten
18、ance and operating manuals including technical data sheets, wiring diagrams, and information for ordering replacement parts. a. Wiring diagrams shall have their terminals identified to facilitate installation, maintenance, and operation. b. Wiring diagrams shall indicate internal wiring for each ite
19、m of equipment and the interconnection between the items of equipment. c. Provide a clear and concise description of operation, which gives, in detail, the information required to properly operate the equipment. d. Approvals will be based on complete submissions of manuals together with shop drawing
20、s. 2. Two weeks prior to final inspection, deliver four copies of the final updated maintenance and operating manuals to the Resident Engineer. a. The manuals shall be updated to include any information necessitated by shop drawing approval. b. Complete “As Installed“ wiring and schematic diagrams s
21、hall be included which show all items of equipment and their interconnecting wiring. c. Show all terminal identification. d. Include information for testing, repair, trouble shooting, assembly, disassembly, and recommended maintenance intervals. e. Provide a replacement parts list with current price
22、s. Include a list of recommended spare parts, tools, and instruments for testing and maintenance purposes. f. Furnish manuals in loose-leaf binder or manufacturers standard binder. C. Certifications: Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-4-
23、09 26 24 11 - 4 1. Two weeks prior to final inspection, submit four copies of the following to the Resident Engineer: a. Certification by the Contractor that the assemblies have been properly installed, adjusted and tested, including circuit breakers settings. b. Certified copies of all of the facto
24、ry design and production tests, field test data sheets and reports for the assemblies. 1.6 APPLICABLE PUBLICATIONS Publications listed below (including amendments, addenda, revisions, supplements and errata) form a part of this specification to the extent referenced. Publications are referenced in t
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- VA2624112009DISTRIBUTIONSWITCHBOARDSPDF