SAE AIR 1939-1986 Aircraft Engine Life Cycle Cost Guide《飞机发动机的生命周期成本指南》.pdf
《SAE AIR 1939-1986 Aircraft Engine Life Cycle Cost Guide《飞机发动机的生命周期成本指南》.pdf》由会员分享,可在线阅读,更多相关《SAE AIR 1939-1986 Aircraft Engine Life Cycle Cost Guide《飞机发动机的生命周期成本指南》.pdf(42页珍藏版)》请在麦多课文档分享上搜索。
1、 . .II_ . SAE AIRx1937 8b R 8357340 0007128 1 M 6 . 6.1 6.2 6.3 6.4 6.5 6; 6 6.7 6.8 6.9 6.10 7 . 7.1 7.2 7.3 7.4 7.5 8 . 8.1 8.2 8.3 8.4 8.5 9 . 9.1 9.2 1 o . 1 o . 10.2 10.3 10.4 -2- TABLE OF CONTENTS Contd . Section IhPUT . General Description of the Project System Parameters . Engine Design and
2、Development Requirements Fleet Size and Structure Overall Timescales and Del i very Schedules . Fleet Utilization . Maintenance Organization Maintenance Demands . Spares Requirements . Cost Basis OUIPUT RDT acquisition (initial procurement and investment); and operating and support (O and consequent
3、ly, the engine manufacturer needs airframe data and vice versa. All the ingredients of Section 5.3.1 apply; but in addition, airframe costs are included. LCC analyses focused on Engine Studies are based on a Such studies may be conducted at any depth. System Studies: This type of LCC analysis applie
4、s to variable airframe and fixed engine situations Since the engine is fixed, there is no effect on engine cycle or engine size. Because airframe variations can impact engine usage, severity effects can be important considerations. The ingredients of paragraph 5.3.1 again apply; in addition, however
5、, the engine and airframe costs (often from probably different phases) are added together. Ground Rule Studies: In this situation, both the airfrariie and engine are fixed, but the scenario is variable. Typically, the impact of changes in the maintenance concept, mission details, delivery schedule,
6、economics, etc. are evaluated. variability impact should be consistent with the LCC phase. paragraph 5.3.3, engine and airframe costs are added as appropriate. Choice of such specific variables and their allowed As in 5.3.2 5.3.3 5.3.4 5.4 Projecting/Tracking: LCC tracking projections are used for c
7、ost control by design engineers, program managers, financial analysts and many others. Design engineers use LCC as a technical parameter for improving the engine system, That is, LCC is established as a technical parameter in the same sense and for the same purpose as performance parameters. Program
8、 managers use LCC tracking projections for program cost control. Similarly, financial analysts use LCC tracking projections for contract cost control Five elements of LCC tracking projections are (Figure 8): - initial base1 ine - previous projections - current status - future project ions - goal or
9、target The initial baseline LCC is the Initial Projection, sometimes called a calibration, of the total cost of an engine program from start to finish. The current status LCC is the Current Projection or most recent calibration of the total cost of an engine program from start to finish, The goal or
10、 target LCC is the projected cost of the engine program that has been establ.ished as an achievement objective for engine program participants. 5.4 (Continued): As the engine program proceeds, improvement changes usually are incorporated into he engine design and its program elements to reduce cost.
11、 The results are additional LCC projections generally (but not always) lower than the initial projection. LCC tracking projections that have been estimated for time periods prior to the current status LCC are Previous Projections. Similarly, LCC tracking. projections that are being estimated for tim
12、e periods beyond the current status LCC are Future Projections, as shown by Figure 8. LCC tracking projections are either or both of the following cost and cost re1 a ted da ta approat hes : - absolute - relative ADsolute data has not had a quantity multiplied, divided, subtracted, or added to it. A
13、bsolute data presents numerical values independent of a fiase1 i ne. Relative data has had a quantity multiplied, divided, subtracted, or added to it. or values (e.g., net change from an established baseline). Relative data presents numerical values dependent upon another value For clarity and impro
14、ved tracking projections, Life Cycle Costs can be separated as illustrated in Figure 9 (for a scenario different from that. depicted in Figure 8). Using this approach to LCC tracking projections, both cost and cost-related actual and updated projections can be better presented and controlled. Some v
15、ariants to the above recommended guidelines for LCC tracking projections are practiced by industry and government. . Specifically, the claimed baseline LCC might not be the Initial Projection. For example, sometimes the claimed baseline is the Current Status Projection. times the claimed baseline is
16、 the Goal or Target LCC. For this and other areas of LCC data presentation, both users and suppliers of LCC data should coordinate and mutually agree upon consistent LCC data presentation gui del ines. Breakouts of Life Cycle Cost tracking projections to several higher and lower indenture levels can
17、 be helpful to both LCC data presentation users and suppliers. When tracking projections of engine LCC, the engines ongoing credit and debit impacts on total system LCC (e.g., aircraft/fleet) should be reported. This should be coordinated and mutually agreed upon in advance by LCC data presentation
18、users and suppl iers. At other _- - . SAE AIR*L937 6 357340 0007338 4 - 12 - 5.4 (Continued): Improvement experience curves, al so cal led 1 earning curves, are frequently applied for tracking projections of cost and cost related LCC parameters. Many different learning curves of the fom y=AX-B are i
19、n use by industry and government. Plotted data can be a straight line on log-log. paper depending on whether the data are cumulative average or per unit data (Figure 10). Users and suppliers of LCC data should clearly indicate which data tracking projections arebeing presented, e.g., cumulative aver
20、age or per unit. Historical data actuals should be used as a basis to substantiate and/or verify LCC tracking projections. 5.5 Caution; Program managers, financial analysts, design engineers and other technical specialists should be aware of erroneous conclusions resulting from inappropriate input a
21、nd/or inappropriate comparisons with historical results, in spite of adequate LCC effort and valid LCC output. For example, a new engine program managed “business not as usual“ with novel engine design features might not follow historical trends. LCC analyses intended for engineering design activity
22、 might be inappropriate (without additional coordination and costing) for financial budget activity (see Figures 11 and 12). 5.5.1 Engine Fleet Size LCC Impact: dominant is the engine development cost. engine fleet size the more dominant is the engine acquisition, maintenance and fuel cost. With onl
23、y engine fleet size as a variable, a typical trend of impact on LCC percentage allocations is shown for a 50-50,000 unit range of engine fleet size (Figure 11). 5.5.2 Engine Program Life LCC Impact: more dominant is the engine development and acquisition cost. Conversely, the longer the engine progr
24、am life the more dominant is the engine maintenance and fuel cost. With only engine program life as a variable, a typical trend of impact on LCC percentage allocations is shown for a 1-45 year range of engine program life (Figure 12). 5.6 Coordination and Responsibility Requirements: As was indicate
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- SAEAIR19391986AIRCRAFTENGINELIFECYCLECOSTGUIDE 飞机 发动机 生命周期 成本 指南 PDF

链接地址:http://www.mydoc123.com/p-1020100.html