REG NASA-LLIS-6796-2012 Lessons Learned TRaiNED Deployment Failure Was Traced to Design Flaws and Process Escapes [Export Version].pdf
《REG NASA-LLIS-6796-2012 Lessons Learned TRaiNED Deployment Failure Was Traced to Design Flaws and Process Escapes [Export Version].pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-6796-2012 Lessons Learned TRaiNED Deployment Failure Was Traced to Design Flaws and Process Escapes [Export Version].pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、 Public Lessons Learned Entry: 6796 Lesson Info: Lesson Number: 6796 Lesson Date: 2012-08-28 Submitting Organization: JPL Submitted by: David Oberhettinger Subject: TRaiNED Deployment Failure Was Traced to Design Flaws and Process Escapes Export Version Abstract: A payload door failed to deploy on a
2、 sounding rocket mission intended to advance the technology for autonomous navigation. In addition to several design flaws, an anomaly investigation board identified several process escapes. Several rigorous mechanical design practices are recommended, along with processes to verify that the specifi
3、ed materials are used, wiring harnesses are not mis-mated, and key knowledge is retained upon personnel rotations. Description of Driving Event: The Terrain-Relative Navigation and Employee Development (TRaiNED) project was a Class D (i.e., low cost, high risk) mission employing a sounding rocket to
4、 capture exoatmospheric and low-altitude imagery. Using the imagery to refine navigation algorithms, the payload developed by the NASA/Caltech Jet Propulsion Laboratory (JPL) for the 41.087 mission (Dr. Martin Heyne, Principal Investigator) was intended to advance the technology for autonomous terra
5、in-relative navigation and hazard detection, providing aerial and surface access to key sites in the solar system. The launch of the 41.087/Heyne Terrier-Improved Orion sounding rocket (Figure 1) from White Sands Missile Range (WSMR) on December 6, 2010 was nominal, but no data was received from the
6、 JPL-furnished cameras located in the exoatmospheric section. The camera field of view was blocked by a blow-off door, which did not release early in the flight as planned. The sounding rocket for the “Heyne“ mission employed a legacy design in which the door (Figure 2) is held in place by tabs and
7、by a single brass screw that is severed in flight by a pyrotechnic guillotine cutter. Rotational acceleration forces then act on the released door, which rotates away from the payload. . Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Figure 1. Heyne
8、 mission sounding rocket just prior to flight at WSMR Figure 2. Close-up of the sounding rocket, with an Exoatmospheric Camera Door clearly visible on the left Review of telemetry records, inspection of the remaining door hardware, and material analysis, established that the blow-off door release (F
9、igure 3) was actuated at the proper time in flight, but the deployment screw was only partially severed by the cutter (Reference (1). A more common industry practice is to use high strength fasteners with an extremely high pre-load, so that the cutter only need weaken the screw to the point that the
10、 tensile load induces failure in the remainder of the material. Figure 3. A detailed diagram of the blow-off door mechanism has been redacted for International Traffic in Arms Regulations (ITAR) compliance. Although the Heyne mission failed to capture camera imagery at 120 km altitude from its exoat
11、mospheric experiment section, the JPL payload did succeed in capturing the requisite descent imagery. References: 1. “41.087/Heyne Terrier-Orion Anomaly Investigation Board Final Report,“ NASA Sounding Rocket Program Office, May 10, 2011. 2. Donald R. Sevilla, e-mail with subject “Re: TRaiNED AIB Fi
12、nal Report - Bolt Cutter Failure,” July 7, 2011. 3. “Mate/Demate, Verify, and Document Connectors One-at-a-Time,“ NASA Lesson Learned No. 1619, NASA Engineering Network, August 8, 2005. Portions of the following text have been redacted, as indicated, for ITAR compliance. “U.S. Persons“ may obtain a
13、copy of the complete lesson learned by contacting the JPL Office of the Chief Engineer (David Oberhettinger at davidonasa.gov). Lesson(s) Learned: In-flight failures are not unexpected on low cost, high risk, projects like the Phaeton projects that provide a learning experience for junior engineers.
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS67962012LESSONSLEARNEDTRAINEDDEPLOYMENTFAILUREWASTRACEDTODESIGNFLAWSANDPROCESSESCAPESEXPORTVERSIONPDF

链接地址:http://www.mydoc123.com/p-1019552.html