REG NASA-LLIS-1764--2006 Lessons Learned Critical Facilities Maintenance Assessment.pdf
《REG NASA-LLIS-1764--2006 Lessons Learned Critical Facilities Maintenance Assessment.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1764--2006 Lessons Learned Critical Facilities Maintenance Assessment.pdf(13页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1764Lesson Info:a71 Lesson Number: 1764a71 Lesson Date: 2006-07-27a71 Submitting Organization: JPLa71 Submitted by: David Oberhettingera71 POC Name: Wilson Harkinsa71 POC Email: wilson.b.harkinsnasa.gova71 POC Phone: 202-358-0584Subject: Critical Facilities Maintenance Assessm
2、ent Abstract: CFMA is an ongoing NASA activity that was initiated following the March 2000 HESSI spacecraft overtest incident that severely damaged the spacecraft. CFMA is a comprehensive assessment of NASA critical facilities and equipment to identify inadequacies in ground facility readiness that
3、could harm people or NASA hardware. It involves an inventory of critical facilities and equipment, identification of equipment failure modes, establishment of appropriate reliability centered maintenance (RCM) methods, and related activities. This lesson captures a NASA Preferred Practice that was d
4、rafted but did not complete a NASA-wide review cycle.Description of Driving Event: This lesson learned documents a NASA Preferred Practice for Design and Test that was drafted shortly before the cancellation of the Preferred Practice task. Hence, the draft was not subjected to review by the NASA fie
5、ld centers and should not be viewed as a formally accepted NASA-wide practice. Practice Prepare and implement an institutional plan for the comprehensive assessment of NASA critical facilities and equipment that includes: 1. An inventory of critical facilities and equipment. Provided by IHSNot for R
6、esaleNo reproduction or networking permitted without license from IHS-,-,-2. Comprehensive assessment of failure modes for critical equipment. 3. Establishment of appropriate Reliability Centered Maintenance (RCM) methods. 4. Acquisition of necessary Predictive Testing and Inspection (PT&I) equipmen
7、t. 5. Implementation of RCM using a Computerized Maintenance Management System (CMMS) and appropriate performance metrics 6. Center-wide training in RCM and Critical Facilities Maintenance Assessment procedures. Benefit Critical Facilities Maintenance Assessment (CFMA) was first implemented by NASA
8、following the March 2000 High Energy Solar Spectroscopic Imager (HESSI) spacecraft overtest incident. Inadequate maintenance of the test equipment was one of the principal causes of the major structural damage sustained by HESSI during this JPL test. Subsequently, other incidents have occurred at NA
9、SA centers such as contamination in an assembly facility that housed a spacecraft due to rainwater from a leaky roof. CFMA identifies inadequacies in ground facility readiness that could affect the safety of the public, the NASA workforce, flight hardware, and other critical equipment and property.
10、Implementation Method To simulate the extreme environments of space, test equipment may subject spaceflight hardware to stress levels that approach the test articles limits. Often with repeated test-analyze-and-fix cycles and few or no flight spares, it is essential that testing be conducted with hi
11、gh reliability and fidelity. The potential cost and schedule impact of a test failure or facility failure increases disproportionably with proximity to the systems launch date. The March 2000 HESSI spacecraft overtest incident alerted NASA to the substantial risks of utilizing aging industrial facil
12、ities for the development of high value, one-of-a-kind products. The assessment and management of these programmatic risks, as well as safety risks, require data on the facilities condition, characteristic failure modes, and maintenance practices. Hence, NASA initiated a review of all critical groun
13、d facilities at each of the NASA centers shortly after the HESSI mishap. A comprehensive program was begun to define RCM gaps, complete a critical facility inventory, perform failure assessments, define and document maintenance procedures, and implement a CMMS. This process is depicted in Figure 1.
14、NASA Policy Directive NPD 8831.1, Maintenance of Institutional and Program Facilities and Related Equipment (Reference (1), was revised to require self-assessments of facilities maintenance programs and utilization of accepted standards as a guideline to determining facilities maintenance funding re
15、quirements. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Figure 1 is a color flow chart of the CFMA process. The first block is labeled ?Business Model? within which an ?Identify Critical Systems? box flows into a ?Determine Key Performance Indica
16、tors? box. The first block flows into an ?FMEA & RCM? block, which contains a single ?Generate RCM Based Maintenance Strategy? box. This second block flows into a ?CMMS? block which contains a single ?Implement Strategy? box. This third block flows into the last block? ?Reliability Engineering? cont
17、aining a single ?Reliability Based Analysis? box. There is a feedback loop from the last block flowing back to the ?FMEA & RCM? block, with the feedback loop labeled ?Continuous Improvement.?Figure 1. NASA Vision for Asset ManagementCFMA is conducted on NASA facilities only. However, given the oppor
18、tunities for damage to NASA flight systems in facilities owned by system contractors, contractor proposals and operations should be reviewed for the maturity of their maintenance practices. For on-site contractors, opportunities for collaborative use of maintenance resources (e.g., sharing FMEA data
19、) should be pursued. Facility Inventory and Audit: Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-CFMA should be conducted by a working group composed of maintenance specialists competent to review the health of the centers current maintenance progr
20、ams and identify any needed improvements. The CFMA Working Group (CWG) should also include those individuals responsible for key facilities such as major integration and test laboratories, with support by reliability engineers and other specialists as needed. The first task for the CWG is to complet
21、e a comprehensive inventory of equipment and facilities that are critical to the mission of the center. Critical equipment may be defined as “equipment, which if not operated or maintained correctly, could endanger the operating personnel or the product being processed.“ The inventoried items are th
22、en ranked in order of relative criticality. Technical equipment with primary functions related to flight system development and operation are identified and ranked separately from non-technical, general-purpose equipment such as HVAC facilities. The purpose is to separate civil engineering related i
23、tems with well-understood failure modes and maintenance needs from specialized engineering facilities that are candidates for failure mode analysis and RCM. Technical equipment that processes flight hardware, defined as “product items deliverable to a customer or deliverable to a significantly high-
24、level of integration,“ is given a high ranking. High ranking items are given priority for further assessment within the CFMA process, and this prioritization may also impact capital equipment improvement plans and other institutional processes. Once the critical facilities are identified, they are a
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS17642006LESSONSLEARNEDCRITICALFACILITIESMAINTENANCEASSESSMENTPDF

链接地址:http://www.mydoc123.com/p-1019276.html