REG NASA-LLIS-1199-1990 Lessons Learned OV-104 STS-38 Avionics Bay Platform Beam Assembly Incident - Formal Accident Investigation Board Report.pdf
《REG NASA-LLIS-1199-1990 Lessons Learned OV-104 STS-38 Avionics Bay Platform Beam Assembly Incident - Formal Accident Investigation Board Report.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1199-1990 Lessons Learned OV-104 STS-38 Avionics Bay Platform Beam Assembly Incident - Formal Accident Investigation Board Report.pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1199Lesson Info:a71 Lesson Number: 1199a71 Lesson Date: 1990-09-03a71 Submitting Organization: KSCa71 Submitted by: J.L. Sullivan/ Eric RaynorSubject: OV-104 STS-38 Avionics Bay Platform Beam Assembly Incident - Formal Accident Investigation Board Report Description of Driving
2、 Event: On October 3, 1990, at approximately 0940 hours at the Vertical Assembly Building Transfer Aisle, the OV-104 Orbiter was being rotated toward the vertical position when three loud, thud noises were heard emanating from the Orbiter. IPR 38V-0182 was documented to investigate cause of the nois
3、e. The three (3) thuds occurred in succession, not simultaneously. Discussions were held with Engineering, Operations, Technicians, and Quality personnel to determine possible causes of the noise. A management decision was made to proceed with the soft mate of Orbiter to External Tank, visually insp
4、ect to verify Aft external tank attach nuts were in place prior to mate, mate Orbiter, remove weight of Orbiter from the attach sling (sling weight only on crane), open the Aft section and look for possible cause of noise. All of the mate functions were accomplished and Aft Section 50-1 and 50-2 doo
5、rs were removed to gain access to the Aft Compartment. An avionics platform beam (G070-502677-001) was observed in the Aft Compartment. Preliminary inspection indicated flight hardware had been damaged. Photographs were initially taken of the beam location and surrounding areas. As sufficient platfo
6、rms were installed, additional photos were taken to document damage. Beam G070-502677-001 was installed in the OPF by JC V35-00001 on August 15, 1990. This beam was verified as removed by Tech/Quality on October 1, 1990, prior to close-out of the Aft compartment to support roll-over from the OPF to
7、the VAB for mating operations. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Lesson(s) Learned: The primary and major contributory causes of the mishap were: 1. Failure to remove the beam. If the standard sequence of access platform removal is foll
8、owed, the beam is one of the last components to come out. Also, the beam cannot be safely removed until either the 50-1 or 50-2 entry level platforms are removed. Since other scheduled work was in process, requiring the entry level platforms, the beam was temporarily and intentionally left resting a
9、gainst the 1307 bulkhead for approximately 40 minutes. Due to the elapsed time and remote location of the beam, plus reduced lighting, the beam was forgotten and overlooked.2. The check and balance by the technician and the Quality Control inspector failed. The technician and inspector were using a
10、job card matrix, consisting of prerecorded platform component numbers which had been initially recorded during platform component installation. The removal check-off and accountability operation was being performed at floor level as opposed to the more traditional method of verification where the pl
11、atform components are removed and verified as they cross the access door thresholds. The rationale for this change consisted of three considerations: (A) the bay was destined for maintenance rather than early roll-in of the next orbiter and, therefore, the platform components had to be completely re
12、moved from the work site and stowed; (B) the area where the platform components would have been inventoried and temporarily stowed was congested; (C) an opinion existed that a better check-off and accountability could be accomplished at the floor level rather than at the 50-1 and 50-2 access door ex
13、its.The team responsible for job card matrix execution and ultimate removal verification consisted of one technician and one inspector. Several technicians were transporting the platform set assemblies from the 50-1 and 50-2 doors to the floor. As the technician read component part numbers, the qual
14、ity inspector checked off the pre-recorded matrix. There were reported confusion factors consisting of multiple numbers on components and faded numbers; however, there was no practical correlation between these factors to explain why an error in accounting for the platform components occurred. For a
15、n unknown reason, the G070-502677-001 beam was counted as having been removed, and therefore, no subsequent search for it was made. A probable scenario for the human error follows: piece number G070-502777-001 was mistakenly checked off the inventory list as G070-502677-001. After almost the entire
16、inventory of platforms had been completed, the Tech and QC on the OPP floor started to review the inventory list to account for several items that had not yet been verified. Piece number G070-502777-001 was still not verified. In reviewing the assemblage of components, the Tech and QC found G070-502
17、777-001 in the equipment storage area and marked it off the inventory list. Thus, component G070-502777-001 was probably counted twice as two pieces of equipment. This scenario was not presented by the Tech or QC, but is the most probable sequence of events that the Board feels occurred. Provided by
18、 IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Recommendation(s): FINDINGS, OBSERVATIONS AND RECOMMENDATIONS PRIMARY CAUSE: Avionics Bay Platform Beam Assembly was left in the Aft Compartment of OV-104. Other work unrelated to platform removal and Aft Closeout
19、 had been scheduled for the Aft Compartment during the same period as platform removal and Aft Closeout. This unrelated work required that the entry platforms inside the 50-1 and 50-2 doors remain in place. The unrelated jobs contributed to an excessive man loading in the Aft Compartment, as did som
20、e OJT by NASA QC. The beam could not physically be removed from the Aft with the entry platforms still in place. Therefore, the beam was temporarily positioned against the 1307 bulkhead forward of Avionics Bay 6, awaiting removal of the entry platforms. When the entry platforms were removed, approxi
21、mately 40 minutes later, the platform removal crew had forgotten about the beam. RECOMMENDATIONS All unrelated work should be completed before performing platform removal. Limit personnel access to the Aft Compartment to minimum essential personnel required to perform platform removal and Aft Closeo
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS11991990LESSONSLEARNEDOV104STS38AVIONICSBAYPLATFORMBEAMASSEMBLYINCIDENTFORMALACCIDENTINVESTIGATIONBOARDREPORTPDF

链接地址:http://www.mydoc123.com/p-1018838.html