REG NASA-LLIS-0594-1998 Lessons Learned ACE SEPICA Micro-machined Silicon Valve On-orbit Anomaly.pdf
《REG NASA-LLIS-0594-1998 Lessons Learned ACE SEPICA Micro-machined Silicon Valve On-orbit Anomaly.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-0594-1998 Lessons Learned ACE SEPICA Micro-machined Silicon Valve On-orbit Anomaly.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 0594Lesson Info:a71 Lesson Number: 0594a71 Lesson Date: 1998-06-17a71 Submitting Organization: GSFCa71 Submitted by: Ellen L. HerringSubject: ACE SEPICA Micro-machined Silicon Valve On-orbit Anomaly Description of Driving Event: The SEPICA instrument, one of 9 instruments flow
2、n on the ACE Mission, uses isobutane gas as part of its particle detection scheme. Three proportional counters, one associated with each of SEPICAs 3 detectors (1-high resolution, 2-low resolution), were to be held at a constant pressure by the use of a Commercial-Off-The-Shelf (COTS) bi-metallic mi
3、cro-machined silicon valve assigned to each of the detectors. Following one month of flawless operations, detector operations indicated pressure being maintained slightly higher than pressure set point. It was thought that this state could be attributed to a loss of valve seat tightness or to a fund
4、amental shift in valve baseline response. Approximately 6 months following launch, pressure in the high resolution detector totally decayed to zero at a rate consistent with that of a normal closed-valve rate. Analysis of the pressure decay and the inability to command the valve seems to indicate th
5、at the valve associated with this detector is in a closed state and there exists a lack of ability to flow required current across the system to open the valve. Although unproven, analysis seems to indicate the failure is within the valve. Impact of this failure to mission and instrument science is
6、minimal due to a combination of the availability of high resolution data obtained earlier in the mission, the continuing availability of the other 2 SEPICA low resolution detectors, and the availability of complementary science from other ACE instruments.Although pre-mission analysis did indicate in
7、consistent workmanship in the chosen COTS valves, it was determined that these COTS valves were the only acceptable design approach given mission limitations (e.g., power, mass, etc.) and that the risk mitigation approach to select the best valves through instrument team-led filtering process and th
8、e performance of extensive ground testing was consistent with the mission/instrument class (i.e., mission was Class C and instrument suite was Class D).Considerable experience was gained in extensive pre-launch and post-launch ground testing which was performed at on-orbit thermal and vacuum conditi
9、ons. However due to safety concerns, the Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-majority of life testing on the spare unit at the University of New Hampshire was performed with nitrogen, rather than the on-orbit isobutane gas. The use of nit
10、rogen did not necessarily fully simulate effects in the on-orbit configuration due to the different properties from the on-board gas. Post-anomaly evaluation also indicated that, although the spare gas system had undergone some level of vibration test, the valves had been replaced afterward. The fli
11、ght valves that are being tested in the spare have not been vibrated at all and, therefore, may not be an adequate model of the on-orbit valves.The valve manufacturer did supply recommended valve operational boundaries (e.g., duty cycle, power, etc). In some of these areas, the on-orbit valves were
12、operated on or near the manufacturers recommended boundaries and, in the area of duty cycle, the valves were operated outside of the manufacturers documented recommendations with verbal confirmation from the manufacturer that the out-of-boundary conditions should be acceptable. The selected valve wa
13、s a commercial product, is no longer produced by the vendor, and vendor-expertise is no longer available.No on-orbit back-up/redundancy to control the gas flow, possibly in a degraded fashion, in case of failure of the valves was developed or contemplated.Lesson(s) Learned: 1. Inconsistencies in Gro
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS05941998LESSONSLEARNEDACESEPICAMICROMACHINEDSILICONVALVEONORBITANOMALYPDF

链接地址:http://www.mydoc123.com/p-1018241.html