ASHRAE LO-09-071-2009 Improving Control and Operation of a Single Duct VAV System through CCLEP《通过CCLEP提高控制与操作单管可变空气量系统》.pdf
《ASHRAE LO-09-071-2009 Improving Control and Operation of a Single Duct VAV System through CCLEP《通过CCLEP提高控制与操作单管可变空气量系统》.pdf》由会员分享,可在线阅读,更多相关《ASHRAE LO-09-071-2009 Improving Control and Operation of a Single Duct VAV System through CCLEP《通过CCLEP提高控制与操作单管可变空气量系统》.pdf(9页珍藏版)》请在麦多课文档分享上搜索。
1、760 2009 ASHRAEABSTRACTThis paper discusses the implementation of new innova-tive technologies in a Continuous Commissioning Leading Energy Project (CCLEP). Results of a case study show that CCLEP implementation can improve building operations and reduce energy costs. Energy consumption is compared
2、in detailbefore and after CCLEP. Results show average electricity savings of 26.8% and gas savings of 47.8%. INTRODUCTIONWith the energy crisis of the early 1970s came the realization that buildings could be made much more efficient without sacrificing comfort. Over the last 30 years, use of variabl
3、e air volume systems has become common practice.Many variable air volume (VAV) systems with pneumatic controls were installed in the 1980s and are still in use. However, these systems often have outdated control strategies and deficient mechanical systems are deficient, which may cause occupant disc
4、omfort and excess energy consumption. An ASHRAE committee proposed building commission-ing in 1988 to ensure that system performance met design specifications. Continuous Commissioning (CC) technologywas developed and implemented in 1992. CC is an ongoing process to resolve operating problems, impro
5、ve comfort, opti-mize energy use and identify retrofits for existing commercial and institutional buildings and central plant facilities 1-5. Since 1999, the Energy Systems Laboratory (ESL) at the University of Nebraska has conducted extensive research to implement optimal system control during the
6、design phase and finalize the optimal setpoints after system installation. ESL researchers have developed and implemented the Continuous Commissioning Leading Energy Project (CCLEP) process with federal and industry support. The CCLEP process has two stages: the contracting stage and the implementat
7、ion stage. During the contracting stage, a comprehensive technical evaluation is performed. The CCLEP implementation stage involves planning, retrofit and trouble shooting, and optimization and follow-up. The CCLEP process, procedures and seven case study results are presented in 6. This paper prese
8、nts information on the case study facility, existing and improved control sequences, and building perfor-mance improvement and energy consumption measures before and after CCLEPimplementation.FACILITY INFORMATIONThe case study building is a 5-story office building in Omaha, Nebraska, which was built
9、 in 1988 with a total floor area of 91,200 square feet (8,472 square meters). The plant consists of one chiller and three gas boilers. There are two single-duct VAV air handling units (AHU) supplying condi-tioned air to 106 VAV terminal boxes. The typical office hours are from 8:00 a.m. to 5:00 p.m.
10、 during the weekdays.Terminal BoxesThere are two types of pressure independent VAV t e r m i -nal boxes. One is a VAV box with reheat coil for exterior zones and the other is a VAV box without reheat coil for interior zones. All of these terminal boxes are controlled by pneumatic controllers. Air-Ha
11、ndling UnitsThere are two similar single-duct VAV air-handling units serving this building. AHU 1 serves the basement, 1st and 2ndfloors. AHU 2 serves the 3rd, 4th and 5thfloors. Both use similar Improving Control and Operation of a Single Duct VAV System through CCLEPYoung-Hum Cho Mingsheng Liu, Ph
12、D, PE Xiufeng PangStudent Member ASHRAE Member ASHRAE Student Member ASHRAEJinrong Wang Thomas G. LewisMember ASHRAE Member ASHRAEYoung-Hum Cho and Xiufeng Pang are doctoral students and Mingsheng Liu is a professor in the Department of Architectural Engineering, University of NebraskaLincoln, Linco
13、ln, NE. Jinrong Wang is a senior technical analysis engineer and Thomas G. Lewis is a technical anal-ysis engineer in Omaha Public Power District (OPPD), Omaha, NE.LO-09-071 2009, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Tr
14、ansactions 2009, vol. 115, part 2. For personal use only. Additional reproduction, distribution, or transmission in either print or digital form is not permitted without ASHRAEs prior written permission.ASHRAE Transactions 761control sequences but have different parameter settings. The AHUs include
15、one 50 HP (37.3 kW) supply fan and one 20 HP (14.9 kW) relief fan. The supply fans and relief fans have their respective variable frequency driver (VFD) controls. A typical single-duct AHU system is shown in Figure 1.Chilled Water SystemThe chilled water system includes one 250-ton chiller, one 250-
16、ton cooling tower with one 40 HP (29.8 kW) two-speed tower fan, two 25 HP (18.6 kW) chilled water pumps and two 20 HP (14.9 kW) condenser water pumps. The chilled water system is shown in Figure 2.Hot Water SystemThe hot water system consists of 2800 MBH (820 kW) three gas boilers, seven main loop c
17、onstant-speed pumps and 10 HP (7.46 kW) two constant-speed pumps for case study building. The hot water is supplied to the case study building through a heat exchanger. The hot water system also provides heating to an adjacent building. The system is shown in Figure 3.SYSTEM UPGRADETo realize the op
18、timal control and better building energy operation and energy performance, three CCLEP retrofits were made: 1) the pneumatic controllers for HVAC system were upgraded to DDC, 2) the Energy Management System (EMS) was installed, and 3) a VFD was installed on the chilled water pump. SYSTEM IMPROVEMENT
19、SThe existing control sequences were verified based on analyzing trending data and taking measurements for selected parameters under the existing operating schedules. Based on the actual site conditions, recommendations for Continuous Commissioning (CC) were developed. Table 1 summarizes the major r
20、ecommendations and actions taken. Comparison of the major control schedules before and after CCLEP, as well as other CCLEP activities, are presented in the subsec-tions below.Terminal BoxesFigure 1 Single-duct AHU system (original design).Figure 2 Chilled water system with installed VFD.762 ASHRAE T
21、ransactionsThe major CCLEP measures for the terminal boxes involve resetting the minimum primary airflow and fixing thebox mechanical problems to achieve building thermal comfort. Existing Schedule. The terminal boxes were originally tested and balanced to provide a minimum primary airflow of 25% to
22、 50%. The minimum primary airflow of 25% - 50% in the existing control caused a majority of the rooms to become too cold when the boiler was not operating during the summer months. Also, the lack of primary airflow at the maximum primary airflow setting caused several rooms to be too hot.Improved Sc
23、hedule. To solve these issues, adjustments to the minimum and maximum primary airflows were made. For VAV reheat terminal boxes that serve exterior zones, the minimum airflow setpoint is typically selected to be the largest of the following: 1) the airflow required by the room design heating load, o
24、r 2) the minimum required for ventilation. Where applicable, the minimum primary airflow in interior zone was set to 0% and the exterior zone was set to 20%. In this building, multiple zones serve an open office area. The open office plan allows some VAV boxes serving a space to go to zero airflow,
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAELO090712009IMPROVINGCONTROLANDOPERATIONOFASINGLEDUCTVAVSYSTEMTHROUGHCCLEP 通过 CCLEP 提高 控制 操作 可变

链接地址:http://www.mydoc123.com/p-455355.html