ARMY UFGS-32 31 26-2008 WIRE FENCES AND GATES《铁丝篱笆和大门》.pdf
《ARMY UFGS-32 31 26-2008 WIRE FENCES AND GATES《铁丝篱笆和大门》.pdf》由会员分享,可在线阅读,更多相关《ARMY UFGS-32 31 26-2008 WIRE FENCES AND GATES《铁丝篱笆和大门》.pdf(10页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-32 31 26 (April 2008)-Preparing Activity: USACE SupersedingUFGS 32 31 26 (January 2008)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated March 2008*SECTION TABLE OF CONTENTSDIVISION 32 - EXTERIOR IMPROVEMENTSSECTION 32 31 26WIRE F
2、ENCES AND GATES04/08PART 1 GENERAL1.1 REFERENCES1.2 SUBMITTALS1.3 QUALITY ASSURANCE1.4 DELIVERY, STORAGE, AND HANDLINGPART 2 PRODUCTS2.1 FENCE FABRIC2.1.1 Woven Wire2.1.2 Barbed Wire2.2 GATES2.3 POSTS2.3.1 Metal Posts for Farm Style Fence2.3.2 Composite Polyester Resin Reinforced Line Posts2.3.3 Woo
3、d Posts2.4 BRACES AND RAILS2.5 CONCRETE2.6 PADLOCKSPART 3 EXECUTION3.1 INSTALLATION3.2 EXCAVATION3.3 POST INSTALLATION3.4 BARBED WIRE3.5 GATE ASSEMBLY3.6 GROUNDING- End of Section Table of Contents -SECTION 32 31 26 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without l
4、icense from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-32 31 26 (April 2008)-Preparing Activity: USACE SupersedingUFGS 32 31 26 (January 2008)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated March 2008*SECTION 32 31 26WIRE FENCES AND GATES04/08*NOTE: This guide sp
5、ecification covers the requirements for Wire Fences and Gates.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable item(s) or insert appropriate information.Remove information and requirements not required in re
6、spective project, whether or not brackets are present.This guide specification includes tailoring options for USACE. Selection or deselection of a tailoring option (select view-tailoring options) will include or exclude that option in the section. Specific project editing is still required for the r
7、esulting section.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS
8、 should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL*NOTE: This section covers non security applications for farm style fences. Edit this section throughout for the applicable project.Use Section 32 31 13 for CHAIN LINK FENCES AND GATES.SECTION 32 31 26 Page 2Provided by IHSNot fo
9、r ResaleNo reproduction or networking permitted without license from IHS-,-,-Use Section 32 31 13.53 for HIGH-SECURITY CHAIN LINK FENCES AND GATES.Standard drawings STD 872-90-02 through 872-90-13 of fence and gate types required will be included as part of the contract drawings; the standard drawin
10、gs are available at https:/pdc.usace.army.mil/library/drawings/fence. Layout of fence will be shown including types and locations of gates, and gate sizes. Drawings will also indicate the extent of clearing required.*1.1 REFERENCES*NOTE: This paragraph is used to list the publications cited in the t
11、ext of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.Use the Reference Wizards Check Reference feature when you add a RID outside of the Sections Reference Article to automati
12、cally place the reference in the Reference Article. Also use the Reference Wizards Check Reference feature to update the issue dates.References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish pri
13、nt process.*The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.AMERICAN WOOD-PRESERVERS ASSOCIATION (AWPA)AWPA C1 (2003) All Timber Products - Preservative Treatment by Pressure Proc
14、essesAWPA C4 (2003) Poles - Preservative Treatment by Pressure ProcessesASTM INTERNATIONAL (ASTM)ASTM A 116 (2005) Standard Specification for Metallic-Coated, Steel Woven Wire Fence FabricASTM A 121 (2007) Standard Specification for Metallic-Coated Carbon Steel Barbed WireASTM A 153/A 153M (2005) St
15、andard Specification for Zinc Coating (Hot-Dip) on Iron and Steel SECTION 32 31 26 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-HardwareASTM A 702 (1989; R 2006) Standard Specification for Steel Fence Posts and Assemblies, Hot WroughtASTM A
16、780 (2001; R 2006) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized CoatingsASTM C 94/C 94M (2007) Standard Specification for Ready-Mixed ConcreteASTM D 4541 (2002) Pull-Off Strength of Coatings Using Portable Adhesion TestersASTM F 1043 (2006) Strength and Protective
17、 Coatings on Metal Industrial Chain-Link Fence FrameworkASTM F 1083 (2006) Standard Specification for Pipe, Steel, Hot-Dipped Zinc Coated (Galvanized) Welded, for Fence StructuresASTM F 1184 (2005) Industrial and Commercial Horizontal Slide GatesASTM F 626 (1996a; R 2003) Standard Specification for
18、Fence FittingsASTM F 883 (2004) PadlocksASTM F 900 (2005) Industrial and Commercial Swing Gates1.2 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. Submittals s
19、hould be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through t
20、he Contractors Quality Control system. Only add a “G” if the submittal is sufficiently important or complex in context of the project.For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the “G“ designation to
21、 indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: “AE“ for Architect-Engineer; “DO“ for District Office SECTION 32 31 26 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-(Engineering Divis
22、ion or other organization in the District Office); “AO“ for Area Office; “RO“ for Resident Office; and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy, Air Force, and NASA projects.Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the s
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS3231262008WIREFENCESANDGATES 铁丝 篱笆 大门 PDF

链接地址:http://www.mydoc123.com/p-449741.html