1、*USACE / NAVFAC / AFCESA / NASA UFGS-26 29 01.00 10 (November 2008)-Preparing Activity: USACE (CW) SupersedingUFGS-26 29 01.00 10 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated October 2008*SECTION TABLE OF CONTENTSDIVISION 26 - ELECTRICALSECTION 26 29
2、 01.00 10ELECTRIC MOTORS, 3-PHASE VERTICAL INDUCTION TYPE11/08PART 1 GENERAL1.1 REFERENCES1.2 SYSTEM DESCRIPTION1.3 SUBMITTALS1.4 QUALITY ASSURANCE1.4.1 Corrosion Prevention and Finish Painting1.4.1.1 Fastenings and Fittings1.4.1.2 Corrosion-Resisting Materials1.4.1.3 Corrosion-Resisting Treatments1
3、.4.1.4 Frames1.4.1.5 Cores1.4.1.6 Shafts1.4.1.7 Finish Painting1.4.2 Government StudyPART 2 PRODUCTS2.1 NAMEPLATES2.2 MOTORS2.2.1 Rating2.2.2 Operating Characteristics2.2.2.1 Torques2.2.2.2 Locked-Rotor Current2.2.2.3 Starting Capabilities2.2.2.4 Duty Cycle2.2.2.5 Balance2.2.2.6 Noise2.2.2.7 Power F
4、actor and Efficiency2.2.3 Frames and Brackets2.2.3.1 Stator Frame2.2.3.2 Supporting Bracket2.2.3.3 Overspeed Alternate2.2.3.4 Antireverse Device Alternate2.2.3.5 Eyebolts2.2.4 CoresSECTION 26 29 01.00 10 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from
5、IHS-,-,-2.2.5 Insulated Windings2.2.6 Thermal Protection2.2.7 Winding Heaters2.2.7.1 Heating Element2.2.7.2 Sheath2.2.7.3 Insulation2.2.7.4 Terminals2.2.8 Shafts2.2.9 Bearings2.2.9.1 Loading2.2.9.2 Thrust Bearings2.2.9.3 Guide Bearings2.2.9.4 Lubrication2.2.9.5 Housings2.2.9.6 Cooling2.2.9.7 Rating2
6、.2.9.8 Shaft Currents2.3 SURGE PROTECTION2.3.1 Surge Capacitors2.3.2 Surge Arresters2.3.3 Space Heater2.4 MOTOR TERMINALS AND BOXES2.4.1 Stator Terminal Box2.4.2 Stator Terminals2.4.3 Grounding2.4.4 Accessory Leads and Boxes2.5 WRENCHES, TOOLS, AND SPECIAL EQUIPMENT2.6 FACTORY TESTS2.6.1 Complete Te
7、st2.6.2 Check Test2.6.3 Form Wound Coil Test2.6.4 Winding Space Heater TestPART 3 EXECUTION (Not Applicable)- End of Section Table of Contents -SECTION 26 29 01.00 10 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NA
8、SA UFGS-26 29 01.00 10 (November 2008)-Preparing Activity: USACE (CW) SupersedingUFGS-26 29 01.00 10 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated October 2008*SECTION 26 29 01.00 10ELECTRIC MOTORS, 3-PHASE VERTICAL INDUCTION TYPE11/08*NOTE: This guid
9、e specification covers the requirements for procurement of 3-phase vertical induction motors for driving storm-water pumps for local flood-control pumping stations.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose appli
10、cable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A list
11、ing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL*NOTE: This section covers motors with special features of construction which are conside
12、red necessary to provide maximum insurance against failures where the motors are to be operated only for short periods of time, at infrequent intervals, and at locations where the average relative humidity of the air is high. Where operating characteristics or features of motor construction differ f
13、rom this specification but are considered desirable, this specification may be modified accordingly. The designer must also consider unusual service conditions such as direct exposure to the sun, vermin infestation, or high altitude.SECTION 26 29 01.00 10 Page 3Provided by IHSNot for ResaleNo reprod
14、uction or networking permitted without license from IHS-,-,-In adapting this specification to any project, the form and phraseology will be changed as necessary to properly specify the work contemplated. When deviations from this specification are considered necessary, prior approval from HQ USACE w
15、ill be obtained.*1.1 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.Use the Reference Wiza
16、rds Check Reference feature when you add a RID outside of the Sections Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizards Check Reference feature to update the issue dates.References not used in the text will automatically be deleted from
17、this section of the project specification when you choose to reconcile references in the publish print process.*The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.AMERICAN BEARING MA
18、NUFACTURERS ASSOCIATION (ABMA)ABMA 11 (1990; R 1999) Load Ratings and Fatigue Life for Roller BearingsABMA 9 (1990; R 2000) Load Ratings and Fatigue Life for Ball BearingsASTM INTERNATIONAL (ASTM)ASTM A 123/A 123M (2008) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
19、 ProductsASTM A 153/A 153M (2005) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel HardwareASTM B 344 (2001) Standard Specification for Drawn or Rolled Nickel-Chromium and Nickel-Chromium-Iron Alloys for Electrical Heating ElementsSECTION 26 29 01.00 10 Page 4Provided by IHSNot fo
20、r ResaleNo reproduction or networking permitted without license from IHS-,-,-NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)NEMA MG 1 (2007) Standard for Motors and Generators1.2 SYSTEM DESCRIPTIONThe work under this section includes providing all labor, equipment, and material and performing a
21、ll operations required to design, manufacture, assemble, test, and package and deliver the vertical induction motors for driving pumps specified under Section 22 10 00.00 10 VERTICAL PUMPS, AXIAL-FLOW AND MIXED-FLOW IMPELLER TYPE. These motors shall be supplied complete with all accessories, spare p
22、arts, tools, and manufacturers data and instructions as specified herein.1.3 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. Submittals should be kept to the m
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS26290100102008ELECTRICMOTORS3PHASEVERTICALINDUCTIONTYPE 垂直 感应 电动机 PDF

链接地址:http://www.mydoc123.com/p-449663.html