1、信息系统项目管理师-10 及答案解析(总分:100.00,做题时间:90 分钟)一、单项选择题(总题数:38,分数:100.00)1.Project _ Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.(分数:2.00)A.IntegrationB.ScopeC.ConfigurationD.Requiremen
2、t2.On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and _ are so linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.(分数:2.00)A.time estimatingB.co
3、st estimatingC.project planningD.schedule development3.In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including _.(分数:2.00)A.budgetB.planC.riskD.contract4.Project Quality Management must address the management of the project and the _ of the p
4、roject. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.(分数:2.00)A.performanceB.processC.productD.object5._ is a category assigned to pr
5、oducts or services having the same functional use but different technical characteristics. It is not same as quality.(分数:2.00)A.ProblemB.GradeC.RiskD.Defect6.Project _ Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distri
6、bution, storage, retrieval, and ultimate disposition of project information.(分数:2.00)A.IntegrationB.TimeC.PlanningD.Communication7.The _ process analyzes the effect of risk events and assigns a numerical rating to those risks.(分数:2.00)A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Ri
7、sk AnalysisD.Risk Monitoring and Control8.Project Quality Management processes include all the activities of the _ that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.(分数:2.00)A.projectB.project management teamC.perf
8、orming organizationD.customer9.The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not _.(分数:2.00)A.executed inB.inspected inC.check-inD.look-in10.The project _ is a key input to quality planning sinc
9、e it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(分数:2.00)A.work performance informationB.scope statementC.change requestsD.process analysis11.Performing _ involves monitoring specific proje
10、ct results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.(分数:2.00)A.quality planningB.quality assuranceC.quality performanceD.quality control12._ involves using mathematical techniques to forecast future outcomes based
11、on historical results.(分数:2.00)A.Trend analysisB.Quality auditC.Defect repair reviewD.FlowchartingThe _ is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment ser
12、vice is the heart of a workflow system which consists of several _.(分数:4.00)A.waterfall modelB.workflow reference modelC.evolutionary modelD.spiral modelA.workflow enginesB.processesC.workflow threadsD.tasks13.The project maintains a current and approved set of requirements over the life of the proj
13、ect by doing the following: all changes to the requirements Maintaining the relationships among the requirements, the project plans, and the work products (分数:2.00)A.MonitoringB.ManagingC.GatheringD.Reducing14.The receiving activities conduct analyses of the requirements with the requirements provid
14、er to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result of this analysis and dialog is an _ set of requirements.(分数:2.00)A.agreed-toB.agree-toC.agree-to-doD.agree-with15.During the project, requirements change for a variety of reasons. As needs
15、change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each
16、requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised _ are necessary.(分数:2.00)A.proceedingsB.controlsC.forecasting“sD.prelibations16.Define Activities is th
17、e process of identifying the specific actions to be performed to produce the _.(分数:2.00)A.project elementsB.work draftsC.work packageD.project deliverables17.Project work packages are typically decomposed into smaller components called activities to provide a basis for _, scheduling, executing, and
18、monitoring and controlling the project work.(分数:2.00)A.reviewingB.estimatingC.auditingD.expecting18.The Estimate Activity Resource process is closely coordinated with the _ process.(分数:2.00)A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements19.Estimating activity duratio
19、ns uses information on activity scope of _, required resource types, estimated resource quantities, and resource calendars.(分数:2.00)A.milestoneB.baselineC.qualityD.work20.Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activ
20、ities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to _ progress.(分数:2.00)A.analyzeB.trackC.levelD.extendMany of the activities performed during the preliminar
21、y investigation are still being conducted in _, but in much greater depth than before. During this phase, the analyst must become fully aware of the _ and must develop enough knowledge about the _ and the existing systems to enable an effective solution to be proposed and implemented. Besides the _
22、for process and data of current system, the deliverable from this phase also includes the _ for the proposed system.(分数:10.00)A.analysis phaseB.design phaseC.implementation phaseD.maintenance phaseA.main symptomB.root problemC.final blueprintD.data specificationA.hardware environmentB.testing enviro
23、nmentC.software environmentD.business environmentA.logical modelsB.physical modelsC.design modelsD.implementation modelsA.hardware and software specificationB.system performance specificationC.formal requirements definitionD.general problem statement21.The _ process ascertains which risks have the p
24、otential of affecting the project and documenting the risks“ characteristics.(分数:2.00)A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control22.The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 信息系统 项目 管理 10 答案 解析 DOC