1、PMP 项目管理员资格认证考试-3 及答案解析(总分:200.00,做题时间:90 分钟)一、单项选择题(总题数:200,分数:200.00)1.概率和影响评估是哪个过程的工具与技术?( )A规划风险管理 B识别风险C实施定性风险分析 D实施定量风险分析(分数:1.00)A.B.C.D.2.采购组织可以自己编制独立成本估算或请外部专业人员代为编制成本估算,并作为标底,然后把标底与投标人的报价进行比较,从而选择卖方。这种情况下,招标人采用的是哪一种投标人选择工具?( )A专家判断 B独立估算C采购谈判 D卖方建议书评估技术(分数:1.00)A.B.C.D.3.You are the projec
2、t manager of a large software development project. There is a conflict between two module leads on where the changes have to be made. You intervene and tell them the importance of getting the project on time and ask them to find a solution which is acceptable to both of them. Which conflict resoluti
3、on technique are you using here? A) Confronting. B) Compromising. C) Smoothing. D) Forcing.(分数:1.00)A.B.C.D.4.以下哪个可以最好地显示工作包或活动与项目团队成员之间的联系?( )A组织机构图 BRACI 矩阵C文本型职位描述文件 D工作分解结构(分数:1.00)A.B.C.D.5.你所在的公司生产方便面。你们的产品一直很受消费者欢迎,更没有出现任何与食品安全有关的问题。但是,最近一个月,你们已经接到三次关于质量问题的消费者投诉,说是在食用方便面之后发生腹泻。被消费者投诉的产品,是一种新型
4、的产品,其中有一种新的调味品。它是通过一条专门的作业线添加的。公司高级管理层任命你领导一个团队来调查所发生的问题。你和你的团队决定使用以下哪一种技术?( )A实验设计 B控制图 C流程图 D帕累托图(分数:1.00)A.B.C.D.6.A customer informed you that it is preferable to change a certain aspect of the project. What should you do first? A) Talk with team members to understand implications of the change.
5、 B) Communicate the change to the management to get their inputs. C) Open up a change control. D) Do sizing for the change and communicate to the customer.(分数:1.00)A.B.C.D.7.You are the project manager of Alpha Network Inc. Your company is doing network planning for a major bank. You are planning to
6、 digram the activity dependancies using activity list. Which of the following is true? A) PDM is also the AOA diagramming method. B) PDM is also the AOD digramming method. C) PDM is also AON digramming method. D) PDM is also ADM diagramming method.(分数:1.00)A.B.C.D.8.项目通常都有众多的干系人。他们之间的利益会存在冲突。为了平衡众多干
7、系人的需求,最好的方法是( )。A妥协 B强迫 C撤退 D面对(分数:1.00)A.B.C.D.9.你和你的团队正在另一个国家承担水电站建设的施工任务。有人告诉你,为了使项目工作顺利进行,需要给政府官员付小费。你应该( )。A支付合理的小费,以保证项目进展B调查付小费的理由,然后请示管理层C给他们赠送等值的小礼物,而不支付现金,以避免可能的道德问题D不付小费(分数:1.00)A.B.C.D.10.你即将参加 (分数:1.00)A.B.C.D.11.项目的控制进度过程着眼于( )。A比进度计划提前开始的项目活动 B进度基准变更控制C关键路径上的活动 D资源紧缺的活动(分数:1.00)A.B.C.
8、D.12.产品核实不同于范围核实,产品核实( )。A核实产品的各种特性 B确认创造了正确的产品C获得客户的签字认可 D确保所有工作都已完成(分数:1.00)A.B.C.D.13.在举报违反职业道德的行为之前,你应该( )。A确定该行为已经产生不良后果 B有合理的事实依据C召集一个小组对该行为进行讨论 D确定该行为将对项目目标产生不良影响(分数:1.00)A.B.C.D.14.You are managing a project in a foreign country, where you realize that you will have to pay a fee to some gove
9、rnment agencies to get your work done. You should_. A) pay the fee to the government agencies B) refuse to pay the fee because they are bribes and hence unethical C) instead of paying the fee, you provide small gifts to government officials to get their support D) make a case for why fees should be
10、paid to government agencies, and present it to your management(分数:1.00)A.B.C.D.15.根据以前已经完成的某个范围、功能相似的项目而进行的估算,属于以下哪种类型的估算?( )A自上而下 B自下而上 C参数估算 D确定性估算(分数:1.00)A.B.C.D.16.你是一个项目经理,负责为组织采购项目管理培训服务。你选择卖方 A 来提供这项服务,卖方 A 又将部分工作分包给了卖方 B,而卖方 B 的绩效没有达到你的要求。在这种情况下,你应该( )。A直接找卖方 B 处理 B找卖方 A 处理C同时找卖方 A 和卖方 B 处理
11、 D要求卖方 A 取消与卖方 B 的分包合同(分数:1.00)A.B.C.D.17.As per PMBOK, various executing processes fall into specific knowledge areas. “Develop project team“ is a part of which of the following knowledge areas? A) Project management integration. B) Project procurement management. C) Project human resource manageme
12、nt. D) Project communications management.(分数:1.00)A.B.C.D.18.你是一位项目经理,服务于一家专门从事高新技术产品开发的公司,你正在为一个跨部门的新项目考虑合适的组织结构。可能的选择方案是( )。A职能型 B紧密式矩阵 C矩阵型 D项目型(分数:1.00)A.B.C.D.19.A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce st
13、eel bolts with a length of 20cm. The control limits are 19.955cm and 20.045cm. The measurements made at the end of the process yielded the following results: 20.033cm, 19.982cm, 19.995cm, 20.006cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm. What should be done? A) The proc
14、ess is tinder contr01. It should not be adjusted. B) A special cause should be investigated, the process should be adjusted. C) The control limits should be adjusted. D) The measuring equipment should be recalibrated.(分数:1.00)A.B.C.D.20.你所管理的项目将需要在多个物理地点开展,涉及的风险比较多。你从公司的组织过程资产中了解到,过去类似项目的风险管理工作比较混乱。
15、你想要在本项目上改变这种局面。为了有效地管理本项目的风险,你首先应该( )。A识别潜在的风险及影响 B指定专门人员负责风险管理C编制风险管理计划 D编制风险登记册(分数:1.00)A.B.C.D.21.Cost performance measurement is BEST done through which of the following? A) Asking for a percent complete from each team member and reporting that in the monthly progress report. B) Calculating earn
16、ed value and using the indexes and other calculations to report past performance and forecast future performance. C) Using the 50/50 rule and making sure the life cycle cost is less than the project cost. D) Focusing on the amount expended last month and what will be expended the following month.(分数
17、:1.00)A.B.C.D.22.在识别出众多的干系人之后,可以应用各种方法对干系人进行分类,例如权力/影响方格、权力/利益方格、凸显模型。其中,凸显模型是指根据以下三个方面来考察干系人的重要性( )。A干系人的权力、需要立即关注的紧急程度、有参与项目的合法资格B干系人的权力、参与项目的愿望、需要立即关注的紧急程度C干系人在项目上的利益大小、参与项日的愿望、有参与项目的合法资格D干系人在项目上的利益大小、需要立即关注的紧急程度、有参与项目的合法资格(分数:1.00)A.B.C.D.23.在风险分析过程中,你认为某些风险的发生可能性低且影响较小。对这些风险,最有效地处理办法是( )。A列入观察清
18、单并建立应急储备 B不需要采取任何措施C等待作进一步的分析 D风险转移(分数:1.00)A.B.C.D.24.你的一个朋友是很有经验的项目经理。他告诉你,在编制成本预算时,要防止预算定得太低,不能满足项目的实际需求。他甚至建议你故意把预算夸大 20%,以确保现同有足够的资金。在编制预算时,你应该( )。A把预算加大 20%,但并不打算花完所有的钱B进行风险储备分析,并如实编制预算C尽量压低预算,并打算在执行过程中向发起人要求增加资金D把预算加大 20%,并准备用剩余的钱(如果有)来改进项目质量(分数:1.00)A.B.C.D.25.在最近的一次变更控制会上,变更控制委员会批准对项目新增 4 项
19、活动。这种变更会对 CPI 有何影响?( )A会导致 CPI 提高 B会导致 CPI 降低C对 CPI 没有影响 D可能导致 CPI 提高或降低(分数:1.00)A.B.C.D.26.可能影响管理项目团队过程的组织过程资产包括( )。A组织的工作授权系统 B嘉奖证书、新闻报道、额外待遇C组织结构与组织文化 D过去项目所积累的风险数据库(分数:1.00)A.B.C.D.27.你所负责的项目,其总预算为 12000 美元,需要在 6 周内建造 100 个产品。你刚刚开始第 4 周。到目前为止,你花了 4000 美元成功地建造了 50 个产品。在这种情况下,成本偏差说明了什么?( )A项目正在 11
20、0%地按照预期进度计划执行B项目低于预算 2000 美元C项目在预算内D项目每花费 1 美元做了 2 美元的工作(分数:1.00)A.B.C.D.28.在合同实施过程中,你发现卖方的一个分包商的施工中存在错误。为了保证项目进度,你以书面方式直接向该分包商指示纠正措施。你的行为( )。A是错误的,因为分包商不会采纳你的指示B是错误的,因为这有可能免除卖方的责任C是正确的,因为必须保证项目进度D是正确的,因为你是买方的合法代表(分数:1.00)A.B.C.D.29.在对项目状态进行分析之后,你确定挣值低于计划价值。如果继续保持这种趋势,你预期结果将如何?( )A实际成本将低于计划成本 B完工估算将
21、低于项目预算C项目将延期完成 D项目完工成本将低于最初的成本估算(分数:1.00)A.B.C.D.30.You are working on a project for Bright Idea Inc. and working on a project for a large retail bank. You have already prepared the WBS and got it signed off. Because of some new government regulations, you need to add some more activities to the WBS
22、. You have got the change requests approved through the CB. The WBS changes in turn require which of the following? A) Cost changes. B) Scope changes. C) Schedule revisions. D) Risk response change.(分数:1.00)A.B.C.D.31.在工作分解结构自上而下的细分中,将导致( )。A估算准确度降低 B估算准确度增加C管理工作本身的成本更低 D某些工作的遗漏(分数:1.00)A.B.C.D.32.你
23、所负责的项目正在执行过程中,一个团队成员找到你,询问关于他的职责和工作,因为他不知道如何去完成工作。项目经理应该给他们看( )。A职责分配矩阵 B人员配备管理计划 C项目管理计划 D项目组织机构图(分数:1.00)A.B.C.D.33.在项目即将进入收尾阶段时,你发现了一项原来没有考虑到的新风险。该风险一旦发生,可能给最终的可交付成果带来重要影响,甚至可能使其不能通过客户验收。你应该( )。A把该风险的影响通知管理层和客户 B进行定性风险分析C制定风险缓解措施 D增加应急储备(分数:1.00)A.B.C.D.34.which of the following is the BEST tool
24、for showing the team the project schedule status during project execution? A) Milestone chart. B) Gantt chart. C) Work breakdown structure. D) Network diagram.(分数:1.00)A.B.C.D.35.沟通管理计划的内容包括( )。A干系人的基本信息 B问题升级流程C组织机构图 D问题清单和问题解决策略(分数:1.00)A.B.C.D.36.你们公司为项目团队建立了一个认可与奖励制度。该制度规定,项目的成本绩效是用来确定奖励的重要因素。怎样
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 项目 管理员 资格 认证 考试 答案 解析 DOC