1、PMP 资格认证考试-项目范围管理(三)及答案解析(总分:20.00,做题时间:90 分钟)一、B单项选择题/B(总题数:20,分数:20.00)1.The scope of a project is fully described by _. A. the Statement of Work B. a five level project/work breakdown structure C. the sum of the products and service delivered D. the Request for Proposal(分数:1.00)A.B.C.D.2.The Scop
2、e Management Plan is included in which of the following document? A. Project plan. B. The Work Breakdown Structure. C. The Scope Statement. D. Project Specification.(分数:1.00)A.B.C.D.3.Which of the following is NOT a good characteristic of an effective project objective? A. Specific completion date.
3、B. Measurable. C. Definitive associated costs. D. Inconsistent with strategic organizational objective.(分数:1.00)A.B.C.D.4.A project control system _. A. monitors and controls the projects schedule, costs, scope, budgets, etc. B. is a mechanism which reacts to the current project status in order to e
4、nsure accomplishment of project objectives C. is only needed on large “mega“ projects D. is a system for controlling and executing project documentation in a uniform and timely manner(分数:1.00)A.B.C.D.5.The scope baseline is _. A. the original description of the projects end results B. a summary desc
5、ription of the projects original content and end product, including basic budgetary, and time constraint data C. the original project budget and schedule D. A and C(分数:1.00)A.B.C.D.6.All of the following rules are true about the lowest level WBS work packages EXCEPT work package _. A. can be complet
6、ed without interruption in one location B. can be confidently estimated C. must be assigned to only one person D. must be completed with 80 hours(分数:1.00)A.B.C.D.7.The preparation of the scope baseline involves the _. A. functional manager B. project team C. all the stakeholders D. project sponsor(分
7、数:1.00)A.B.C.D.8.Which of the following is an important input to scope verification? A. Work results B. Historical information C. Formal acceptance D. Change request(分数:1.00)A.B.C.D.9.All of the following are tools for scope verification EXCEPT _. A. product review B. audit C. walk through D. sensit
8、ivity analysis(分数:1.00)A.B.C.D.10.All of the following are needed to create the WB$ EXCEPT _. A. history information B. project charter C. change request D. scope statement(分数:1.00)A.B.C.D.11.When should scope verification be done? A. At the end of the project. B. At the beginning of the project. C.
9、 During each phase of the project. D. During planning.(分数:1.00)A.B.C.D.12.Product verification is different from scope verification, product verification _. A. occurs during the execution phase B. verifies that the correct products have been used C. obtains customer sign-off D. make sure all work is
10、 completed(分数:1.00)A.B.C.D.13.As a project manager of IT, if your supplier asked you to provide a product description, which of the fowling is _. A. scope statement B. statement of work C. project charter D. contract(分数:1.00)A.B.C.D.14.The mark of project success is _. A. satisfying with time and co
11、st B. satisfying with time, cost and quality C. within time, cost, performance and accepted by the customer D. none of above(分数:1.00)A.B.C.D.15.The project consists of 15 separate projects. The PMO will have a project management information system. This system will be an on-line repository of all pr
12、ogram data. You will collect description of all work components for each of the 15 projects. This information will form an integral part of the _. A. chart of account B. WBS dictionary C. WBS structure template D. earned value management reports(分数:1.00)A.B.C.D.16.The project scope statement furnish
13、es a basis for _. A. future project decision including the criteria used to determine if the project or phase has been successfully finished B. provides link to the client functional management groups C. allowing the project to move to the next phase D. a way to provide updated information to the ac
14、counting department(分数:1.00)A.B.C.D.17.May the project team do to confirm the scope of the project is on track? A. Review change requests that have been submitted and approved. B. Obtain status from responsible individuals on the team. C. Conduct walk through, inspections and reviews. D. Complete a
15、scope report and submit it to management.(分数:1.00)A.B.C.D.18.Marketing department has just discovered that a competitor is offering a new feature, using a new technology, on a product similar to the one being created by your project. They submit a change request that is result of _. A. an external e
16、vent B. an error or omission in defining the scope of the product C. an error or omission in defining the scope of the project D. a value-adding change(分数:1.00)A.B.C.D.19.The project scope is measured against the _, while the product scope is measured against the _. A. plan, requirements B. requirem
17、ents, measure of success C. scope baseline, scope definition D. contract, verification(分数:1.00)A.B.C.D.20.An example of scope verification is _. A. review the performance of an installed software module B. managing changes to the project schedule C. decomposing the WBS to a work package level D. per
18、forming a benefit/cost analysis to determine if we should proceed with the project(分数:1.00)A.B.C.D.PMP 资格认证考试-项目范围管理(三)答案解析(总分:20.00,做题时间:90 分钟)一、B单项选择题/B(总题数:20,分数:20.00)1.The scope of a project is fully described by _. A. the Statement of Work B. a five level project/work breakdown structure C. th
19、e sum of the products and service delivered D. the Request for Proposal(分数:1.00)A.B.C. D.解析:选项 A 不完全。没有包括产品的特性与功能。B“五级的项目”概念不清楚。C 正确。描述范围的总和。D 在定义范围以前的文档。对范围只有粗略意向,没有边界定义等。 项目范围可以由_全部描述。 A) 工作说明 B) 五级的项目/工作分解结构 C) 提交的产品和服务的总和 D) 征求意见书2.The Scope Management Plan is included in which of the following
20、document? A. Project plan. B. The Work Breakdown Structure. C. The Scope Statement. D. Project Specification.(分数:1.00)A.B.C. D.解析:选项 A 不完全正确。项目计划是各个管理过程的总和,项目范围管理计划也罗列在其中,但是一种不具体的描述。B 可交付成果的总和。不是管理计划。C 正确。项目范围管理计划是制作范围说明书的依据。范围说明书里包括项目范围管理计划。D 规范是需求的概念,与范围管理计划无关。 项目范围管理计划包括在下面哪个文档中? A) 项目计划。 B) 工作分解
21、结构。 C) 范围说明书。 D) 项目规范。3.Which of the following is NOT a good characteristic of an effective project objective? A. Specific completion date. B. Measurable. C. Definitive associated costs. D. Inconsistent with strategic organizational objective.(分数:1.00)A.B.C.D. 解析:选项 A 完成日期是项目目标之一。B 目标本身应该是可以衡量的。C 确定
22、的相关成本是项目目标之一。D 为正确答案。战略组织目标是项目目标之一,与战略组织目标不相一致不是一个有效的项目目标的特征。 下面哪个不是一个有效的项目目标的特征? A) 具体的完成日期。 B) 可以衡量的。 C) 确定的相关成本。 D) 与战略组织目标不相一致。4.A project control system _. A. monitors and controls the projects schedule, costs, scope, budgets, etc. B. is a mechanism which reacts to the current project status in
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 范围 管理 答案 解析 DOC