ACI 364 10T-2014 Rehabilitation of Structure with Reinforcement Section Loss.pdf
《ACI 364 10T-2014 Rehabilitation of Structure with Reinforcement Section Loss.pdf》由会员分享,可在线阅读,更多相关《ACI 364 10T-2014 Rehabilitation of Structure with Reinforcement Section Loss.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、1ACI 364.10T-14Rehabilitation of StRuctuRe with ReinfoRcement Section loSSKeywords: concrete cover; corrosion; load-carrying capacity; rehabilitation; reinforcement; repair.IntroductionIntegrity of reinforcement is fundamental to the strength, ductility, and safety of reinforced concrete structures.
2、 Determining the necessity of additional or replacement reinforcement is a primary concern in rehabilitation projects containing corrosion of reinforcing steel.QuestionHow should an engineer address exposed and corroded rein-forcement when repairing a conventionally reinforced concrete structure (Fi
3、g. 1), and should there be a concern if the loss of reinforcement is less than 10 percent of the cross-sectional area?AnswerAfter determining the condition of the reinforcement, remove unsound concrete, clean reinforcement, and provide additional reinforcement as needed. The structural consequences
4、of a 10 percent cross-sectional area loss due to corrosion are usually minor for nonprestressed concrete components because there are usually redundancies in design.DiscussionBegin by identifying the source, extent and level of activity of reinforcement corrosion (ICRI No. 310.1R; ACI 364.6T), and d
5、eter-mining the overall condition and cross-sectional area of the affected reinforcing steel. Remove all unsound concrete; undercut the exposed corroded bars to provide clearance for under-bar cleaning and full bar embedment in the repair material; and secure the repair structurally, so as to ensure
6、 the required load-carrying capacity is achieved (Fig. 2). The clear space behind the reinforcing steel should be greater than 1/4 in. (6 mm), plus the dimension of the maximum-sized aggregate in the repair material (ACI 364.6T). Generally, a 3/4 to 1 in. (20 to 25 mm) gap is required to inspect and
7、 clean the bar. Place the repair material and encapsulate the bar with it.Clean the reinforcement by means of wire brushing, sandblasting, shot-blasting, or water-blasting. Do not use solvents as they can penetrate the concrete, which may create a poor bond surface for repair materials. If the reinf
8、orcing bars are epoxy-coated, the epoxy in the area surrounding the exposed corrosion should be removed and the bar cleaned.Measure the cross section. Use calipers to measure the reduced diameter of the reinforcing steel. If the loss of cross-sectional area is greater than 10 percent, additional (su
9、pplemental) reinforcement may be required (Fig. 3). If corro-sion pits with depths greater than 25 percent of the bar diameter are observed, additional reinforcement could also be required.The structural consequences of a 10 percent cross-section area loss due to corrosion are usually minor for nonp
10、re-stressed concrete components because of redundancies in design, as discussed in items (a) through (c) as follows. In practice, there is usually no concern with less than 10 percent loss of cross-sectional area.(a) Reinforcement reserveSteel reinforcement used in construction is typically larger t
11、han required by structural considerations. Extra steel is attributed to varying practical design requirements such as bar layout and spacing. Five to 10 percent more steel area is typically provided than is required by analysis.(b) Corrosion locationCorrosion damage is often uneven throughout the me
12、mber length and frequently may be at Fig. 1Example of severe reinforcing steel deterioration due to corrosion in a reinforced concrete beam (courtesy of the Ministry of Transportation of Quebec).TechNote2Fig. 2ICRI recommendations for cleaning and undercutting of reinforcing steel prior to repair (I
13、CRI No. 310.1R).3a location most distant from the crit-ical design locations for maximum moments or maximum shear. In this case, evaluate the remaining area of reinforcement by calculating moment and shear at the affected sections.(c) ACI code provisionsProvi-sions of Chapter 20 of ACI 318-11 may be
14、 used to modify the strength-reduction factor when the actual dimensions and material proper-ties have been determined through measurements and testing. Moment redistribution provisions (ACI 318-11, Section 8.4) may be used to consider inelastic effects that may reduce the required capacity at the s
15、ection under consideration.Where a loss of 10 percent or more has been identified, check the orig-inal design to determine if the remaining reinforcement is adequate. Also, confirm the absence of design errors and that structure use remains the same.If additional or replacement reinforcement is requ
16、ired, a new reinforcing bar may be lap spliced to the existing bar(s). Lap length is determined in accordance with ACI 318. Additional concrete removal may be necessary to properly splice the new steel reinforcing bar. Mechanical or welded splices that follow code provisions could also be used. Weld
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ACI36410T2014REHABILITATIONOFSTRUCTUREWITHREINFORCEMENTSECTIONLOSSPDF

链接地址:http://www.mydoc123.com/p-1242827.html