IEC 62270-2013 Guide for Computer-based control for hydroelectric power plant automation《水电厂自动化用计算机控制指南》.pdf
《IEC 62270-2013 Guide for Computer-based control for hydroelectric power plant automation《水电厂自动化用计算机控制指南》.pdf》由会员分享,可在线阅读,更多相关《IEC 62270-2013 Guide for Computer-based control for hydroelectric power plant automation《水电厂自动化用计算机控制指南》.pdf(168页珍藏版)》请在麦多课文档分享上搜索。
1、 IEC 62270 Edition 2.0 2013-09 INTERNATIONAL STANDARD NORME INTERNATIONALE Guide for computer-based control for hydroelectric power plant automation Guide pour lautomatisation des centrales hydrolectriques laide de systmes de commande informatiques IEC62270:2013IEEE Std1249-2013IEEE Std 1249colourin
2、sideTHIS PUBLICATION IS COPYRIGHT PROTECTED Copyright 2013 IEEE All rights reserved. IEEE is a registered trademark in the U.S. Patent any IEC National Committee interested in the subject dealt with may participate in this preparatory work. International, governmental and non-governmental organizati
3、ons liaising with the IEC also participate in this preparation. IEEE Standards documents are developed within IEEE Societies and Standards Coordinating Committees of the IEEE Standards Association (IEEE-SA) Standards Board. IEEE develops its standards through a consensus development process, approve
4、d by the American National Standards Institute, which brings together volunteers representing varied viewpoints and interests to achieve the final product. Volunteers are not necessarily members of IEEE and serve without compensation. While IEEE administers the process and establishes rules to promo
5、te fairness in the consensus development process, IEEE does not independently evaluate, test, or verify the accuracy of any of the information contained in its standards. Use of IEEE Standards documents is wholly voluntary. IEEE documents are made available for use subject to important notices and l
6、egal disclaimers (see http:/standards.ieee.org/IPR/disclaimers.html for more information). IEC collaborates closely with IEEE in accordance with conditions determined by agreement between the two organizations. This Dual Logo International Standard was jointly developed by the IEC and IEEE under the
7、 terms of that agreement. 2) The formal decisions of IEC on technical matters express, as nearly as possible, an international consensus of opinion on the relevant subjects since each technical committee has representation from all interested IEC National Committees. The formal decisions of IEEE on
8、technical matters, once consensus within IEEE Societies and Standards Coordinating Committees has been reached, is determined by a balanced ballot of materially interested parties who indicate interest in reviewing the proposed standard. Final approval of the IEEE standards document is given by the
9、IEEE Standards Association (IEEE-SA) Standards Board. 3) IEC/IEEE Publications have the form of recommendations for international use and are accepted by IEC National Committees/IEEE Societies in that sense. While all reasonable efforts are made to ensure that the technical content of IEC/IEEE Publi
10、cations is accurate, IEC or IEEE cannot be held responsible for the way in which they are used or for any misinterpretation by any end user. 4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications (including IEC/IEEE Publications) transparently to
11、 the maximum extent possible in their national and regional publications. Any divergence between any IEC/IEEE Publication and the corresponding national or regional publication shall be clearly indicated in the latter. 5) IEC and IEEE do not provide any attestation of conformity. Independent certifi
12、cation bodies provide conformity assessment services and, in some areas, access to IEC marks of conformity. IEC and IEEE are not responsible for any services carried out by independent certification bodies. 6) All users should ensure that they have the latest edition of this publication. 7) No liabi
13、lity shall attach to IEC or IEEE or their directors, employees, servants or agents including individual experts and members of technical committees and IEC National Committees, or volunteers of IEEE Societies and the Standards Coordinating Committees of the IEEE Standards Association (IEEE-SA) Stand
14、ards Board, for any personal injury, property damage or other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and expenses arising out of the publication, use of, or reliance upon, this IEC/IEEE Publication or any other IEC or IEEE Publications. 8) At
15、tention is drawn to the normative references cited in this publication. Use of the referenced publications is indispensable for the correct application of this publication. 9) Attention is drawn to the possibility that implementation of this IEC/IEEE Publication may require use of material covered b
16、y patent rights. By publication of this standard, no position is taken with respect to the existence or validity of any patent rights in connection therewith. IEC or IEEE shall not be held responsible for identifying Essential Patent Claims for which a license may be required, for conducting inquiri
17、es into the legal validity or scope of Patent Claims or determining whether any licensing terms or conditions provided in connection with submission of a Letter of Assurance, if any, or in any licensing agreements are reasonable or non-discriminatory. Users of this standard are expressly advised tha
18、t determination of the validity of any patent rights, and the risk of infringement of such rights, is entirely their own responsibility. IEC 62270 2 IEEE Std 1249 Published by IEC under license from IEEE. 2013 IEEE. All rights reserved. International Standard IEC 62270/IEEE Std 1249 has been jointly
19、 revised by the Energy Development b) update of communications, user and plant interfaces aspects; c) suppression of case studies, because of the quickness of evolution of the technology; d) complete review of the bibliography, making mention of many IEC and IEEE standards as new references; e) addi
20、tion of a new informative Annex B on legacy control systems. This publication is published as an IEC/IEEE Dual Logo standard. The text of this standard is based on the following IEC documents: FDIS Report on voting 4/284/FDIS 4/287/RVD Full information on the voting for the approval of this standard
21、 can be found in the report on voting indicated in the above table. International standards are drafted in accordance with the rules given in the ISO/IEC Directives, Part 2. The IEC Technical Committee and IEEE Technical Committee have decided that the contents of this publication will remain unchan
22、ged until the stability date indicated on the IEC web site under “http:/webstore.iec.ch“ in the data related to the specific publication. At this date, the publication will be reconfirmed, withdrawn, replaced by a revised edition, or amended. IMPORTANT The colour inside logo on the cover page of thi
23、s publication indicates that it contains colours which are considered to be useful for the correct understanding of its contents. Users should therefore print this document using a colour printer. IEC 62270 IEEE Std 1249 3 Published by IEC under license from IEEE. 2013 IEEE. All rights reserved. GUI
24、DE FOR COMPUTER-BASED CONTROL FOR HYDROELECTRIC POWER PLANT AUTOMATION 1 Overview The automation of control and data logging functions has relieved the plant operator of these tasks, allowing the operator more time to concentrate on other duties. In many cases, the plants operating costs can be sign
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。