REG NASA-LLIS-6536-2012 Lessons Learned - Communicate Requirements Associated with Analysis Tied to Required Verification Data.pdf
《REG NASA-LLIS-6536-2012 Lessons Learned - Communicate Requirements Associated with Analysis Tied to Required Verification Data.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-6536-2012 Lessons Learned - Communicate Requirements Associated with Analysis Tied to Required Verification Data.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Public Lessons Learned Entry: 6536 Lesson Info: Lesson Number: 6536 Lesson Date: 2012-04-2 Submitting Organization: MSFC Submitted by: Jennifer Stevens Subject: Communicate Requirements Associated with Analysis Tied to Required Verification Data Abstract: A specific analysis was required to be perfo
2、rmed by a contractor in support of design, development, verification, and validation of ARES 1-X hardware. The Systems Engineering and Integration (SE&I) group of the prime contractor failed to adequately communicate the requirements associated with an analysis, including a requirement to use specif
3、ic, approved sources for material capability properties with test-verified certainty boundaries (variation dispersions) for use in design analysis to the subcontract engineering group that performed the analysis. The analysis was completed without being verified by the subcontractor or prime contrac
4、tor that the analysis methodology and assumptions complied with contractually stipulated verification data deliverable requirements. The error was found during a late life-cycle review, and the government engineering team was tasked to complete the proper analysis and documentation under extreme tim
5、e constraints to ensure proper verification of the design. The additional unplanned work added cost and time delay to the budget and schedule. Description of Driving Event: In the specific discipline area, the project office contracted with a prime contractor to produce the necessary engineering ana
6、lysis reports to verify that the hardware met the government furnished equipment (GFE) requirements at a component level. The prime contractor subcontracted the work to another company, who then assigned it to their analysis group. The analysis group already had previous experience performing analys
7、is on similar GFE, but for a different prime contractor. Prior to a major review, the prime contractor indicated their intention to verify subsystem safety requirements at the subsystem level rather than at the component level for this particular discipline. Verification compliance was to be summari
8、zed in a single report on a single Verification Data Requirements Sheet (VDRS). At that time, it was agreed that the subcontractor would document the GFE compliance status in a section of their analysis report, and that the prime contractor would include a reference to this report in their subsystem
9、-level integrated compliance report. This arrangement would eliminate the need for an additional set of component VDRSs. When the subcontractor analysis report was released, the subcontractor and prime contractor failed to ensure that the subcontractors work was consistent with the agreed upon verif
10、ication plan. The documentation was submitted to NASA without the agreed-upon component-level verification compliance matrix. The failure to review the product at the subcontractor and prime contractor levels resulted in a significant cost and schedule risk that threatened to delay the mission becau
11、se it was identified very late in the development lifecycle. The non-compliance was discovered during a major review by the governments insight/oversight team during final verification. Expedited and unplanned last minute effort was required to mitigate the impact to the schedule, at an unplanned co
12、st and repetition of technical analytical work to the program. It then became the governments responsibility to perform the compliance analysis. MSFC engineers identified several discrepancies with the report, primarily the use of material design allowable properties from unapproved sources, which h
13、ad to be addressed under deadline by MSFC Engineering. When the prime contractor released the subsystems Analysis Inspection Report, it did not include a section (or even placeholder) to document the GFE component compliance. Due to the time constraints, the MSFC component SE&I team was forced to in
14、itiate a separate set of VRDSs to document the component level verification and use the VRDSs to capture the compliance analysis that had not been included in the subcontractors report. Instead of reducing the level of effort and number of documents, the agreed-upon approach resulted in additional V
15、RDSs that added to the total number that had to be generated, reviewed, and approved by engineering and the project office. Lesson(s) Learned: 1. Communication of verification requirements is essential through all levels of hierarchy and to all organizations performing analysis or producing engineer
16、ing products that support verification and validation rationale. Responsibility for ensuring that work products comply with, and meet the standards of quality, validity and requirements, reside at each level of management and designated governing authority in the hierarchy of authority. Provided by
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS65362012LESSONSLEARNEDCOMMUNICATEREQUIREMENTSASSOCIATEDWITHANALYSISTIEDTOREQUIREDVERIFICATIONDATAPDF

链接地址:http://www.mydoc123.com/p-1019543.html