REG NASA-LLIS-1580--2005 Lessons Learned - This document contains lessons learned from the NOAA-N Prime mishap which occurred at Lockheed Martin Space Systems Company in Sunnyvale .pdf
《REG NASA-LLIS-1580--2005 Lessons Learned - This document contains lessons learned from the NOAA-N Prime mishap which occurred at Lockheed Martin Space Systems Company in Sunnyvale .pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1580--2005 Lessons Learned - This document contains lessons learned from the NOAA-N Prime mishap which occurred at Lockheed Martin Space Systems Company in Sunnyvale .pdf(17页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1580Lesson Info:a71 Lesson Number: 1580a71 Lesson Date: 2005-01-18a71 Submitting Organization: GSFCa71 Submitted by: David Coolidgea71 Authored by: Karen HaltermanSubject: This document contains lessons learned from the NOAA-N Prime mishap which occurred at Lockheed Martin Spa
2、ce Systems Company in Sunnyvale, CA on September 6, 2003. Abstract: The fully assembled NOAA N-Prime satellite was significantly damaged after sliding off an improperly configured cart while being rotated from a vertical position to a horizontal orientation for an instrument shimming operation at th
3、e prime contractors facility on September 6, 2003. This document presents several lessons learned and recommendations for proactive measures to prevent a recurrence of this unfortunate accident. They may be considered applicable to any government/contractor collaborative relationship established to
4、build, test, and launch space flight hardware. The lessons learned relate to the Integration and Test (I the planned operational scenario vs. the actual execution; and the planning activities, including scheduling, crew assembly and test documentation preparation. The second approach was to utilize
5、the Human Factors Analysis and Classification System (HFACS) 2000 to provide a comprehensive framework for identifying and analyzing human error. Evidence from a number of sources, including witness interviews, test and handling procedures, and project documents, were used to develop the accident sc
6、enarios and populate the HFACS model. The Board found that the direct cause of the mishap was a failure of the contractor operations team to follow procedures to properly configure the turn over cart prior to placing NOAA-N Prime on the cart. The necessary 24 bolts to secure the adapter plate were n
7、ot in place and the team relied on paperwork rather than through visual and mechanical verification as required by the procedures. The Board also discovered that the entire operation was flawed and it exposed issues that were systemic in nature. The I providing training for supervisors in monitoring
8、 employees and correcting poor process discipline; establishing effective process guidelines for regulating I staffing product assurance and safety personnel according to requirements; establishing an effective safety program and promoting safety awareness to all levels of the organization, establis
9、hing an effective I using video monitoring as an aid to supervision and performance monitoring; and establishing a training program to disseminate lessons learned from this and other mishaps and near misses. The NASA corrective actions described in the NOAA-N Prime Corrective Action Plan and Impleme
10、ntation Report include: providing a full time, dedicated government civil servant in-plant representative; establishing clear roles and responsibilities for the government in-plant representatives; providing sufficient resources for the Defense Contract Management Agency (DCMA) product assurance fun
11、ctions; establishing oversight guidelines for I implementing oversight guidelines for I establishing an effective safety oversight program; implementing a thorough I and NASA conducting periodic independent reviews of the GSFC POES Project, which manages the Lockheed Martin spacecraft contract. In a
12、ddition, DCMA evaluated the effectiveness of their oversight process and more DCMA resources have been applied to the NOAA contract. Lesson(s) Learned: The lessons learned in the NOAA-N Prime mishap are listed below. They are not profound; they are all obvious. The accident occurred because a long d
13、uration program that had experienced several years of high performance success grew complacent, both at the government and at the contractor. The rules were relaxed, shortcuts were taken, product assurance grew sloppy, and proper oversight was not applied. The recommended actions are equally straigh
14、tforward. Obey the rules, follow the procedures proactively, train the team, always consider systems safety, and provide effective independent oversight. In order to emphasize specific points, ten lessons are identified. The lessons are not independent, stand alone items. All are interrelated facets
15、 of the overall NOAA-N Prime mishap lesson which is to perform I no one saw it coming. The government and the contractor were overconfident and complacent based on past successes. The lesson learned is that successful performance in the past does not predict success in the future, especially on long
16、 duration projects. Even the most extraordinary effort in the past does not guarantee that future efforts will be sustained at the same high quality level. Proactive measures must be taken to maintain a highly functional I the test procedure was scissored out of existing procedures without a clear t
17、op level road map. The Responsible Test Engineer (RTE) did not have the full I the proper I and hazardous operations need special care. The product assurance representatives must understand their roles as witnesses and they must be trained to not buy off procedure steps unless they have personally w
18、itnessed them.Everyone needs to be concerned about the safety of people and high value flight hardware. If any member of the team has a question or a doubt, it should be investigated, not dismissed. Each member of the team should be empowered to halt an operation. Organizational practices must be es
19、tablished to reinforce the role and responsibility of contractor and government inspectors as independent verification agents. Long duration contracts and/or contracts for multiple satellites need extra attention. While there are advantages to being familiar with the spacecraft and the I safety engi
20、neering should not be a part time function drawn from a centralized corporate safety engineering pool. Safety engineers should participate in satellite design, manufacturing and I they should be replaced with specific actions having measurable results where possible. I&T team members should be able
21、to ask questions at any time and every I&T team member should know that he is authorized to stop an operation if he feels there is a problem. Government presence required by a procedure can only be waived by approval from the Project Offices System Assurance Manager. Waiving mandatory government I&T
22、 presence should be rarely, if ever, permitted. The role of the government must be clear. Which government I&T responsibilities are delegated by NASA to DCMA should be known to everyone in the contractors and governments organizations. NASA responsibilities on the I&T floor should be defined so that
23、 the contractor understands each type of oversight. The contractor must track, examine, categorize and trend the nature and closure of the contractor identified non-conformance reports or the DCMA generated Corrective Action Requests. The government must also monitor and track the closure of actions
24、, deficiencies, and recommendations resulting from outside audits and reviews. All results should be shared with the contractor. Corrective measures to improve I&T should be jointly developed with the contractor and jointly monitored for effectiveness. Provided by IHSNot for ResaleNo reproduction or
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS15802005LESSONSLEARNEDTHISDOCUMENTCONTAINSLESSONSLEARNEDFROMTHENOAANPRIMEMISHAPWHICHOCCURREDATLOCKHEEDMARTINSPACESYSTEMSCOMPANYINSUNNYVALEPDF

链接地址:http://www.mydoc123.com/p-1019203.html