REG NASA-LLIS-1485--2004 Lessons Learned The Risk Reduction From Two-fers (Multiple Sister Spacecraft) May Outweigh the Incremental Cost (2002).pdf
《REG NASA-LLIS-1485--2004 Lessons Learned The Risk Reduction From Two-fers (Multiple Sister Spacecraft) May Outweigh the Incremental Cost (2002).pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1485--2004 Lessons Learned The Risk Reduction From Two-fers (Multiple Sister Spacecraft) May Outweigh the Incremental Cost (2002).pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1485Lesson Info:a71 Lesson Number: 1485a71 Lesson Date: 2004-05-17a71 Submitting Organization: JPLa71 Submitted by: David OberhettingerSubject: The Risk Reduction From ?Two-fers? (Multiple Sister Spacecraft) May Outweigh the Incremental Cost (2002) Abstract: NASA elected at th
2、e end of MER Phase A to build a second Mars Exploration Rover at an estimated cost of $243 million. In addition to potentially doubling science return from Mars and mitigating the program impact were a rover to fail, this “two-fer” approach proved helpful in controlling development risks. Consider t
3、he benefits to system development and I&T that may accrue from building a “sister” spacecraft and from maintaining multiple testbeds.Description of Driving Event: At the end of Mars Exploration Rover (MER) Phase A development in July 2000, the cost of a single rover was estimated at $445.5 million,
4、including 20 percent budget reserves. The following month, JPL committed to a two-rover mission with an estimated cost of $243 million for the second rover. In addition to potentially doubling science return from Mars and mitigating the program impact were a rover to fail, this “two-fer” approach pr
5、oved helpful in controlling development risks.Having two rovers under development provided enhanced flexibility to the Integration & Test process (referred to as “ATLO” at JPL). ATLO (Assembly, Test, and Launch Operations) began in late February 2002 for MER-1, and in early May 2002 for the second r
6、over. Experience with MER-1 permitted an abbreviated ATLO for MER-2 and the availability of the additional MER-2 hardware in ATLO helped to isolate problems experienced by MER-1. The MER-2 funding also covered procurement of extra spare assemblies. Schedule risk was mitigated by this “hardware-rich”
7、 ATLO test environment, and was also alleviated by parallel development using four main testbeds run by separate teams. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-DThe complex rovers were developed under major schedule risk. The MER schedule pro
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS14852004LESSONSLEARNEDTHERISKREDUCTIONFROMTWOFERSMULTIPLESISTERSPACECRAFTMAYOUTWEIGHTHEINCREMENTALCOST2002PDF

链接地址:http://www.mydoc123.com/p-1019123.html