REG NASA-LLIS-0763-2000 Lessons Learned - Systems Test Considerations for High Performance Liquid Propellant Rocket Engines.pdf
《REG NASA-LLIS-0763-2000 Lessons Learned - Systems Test Considerations for High Performance Liquid Propellant Rocket Engines.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-0763-2000 Lessons Learned - Systems Test Considerations for High Performance Liquid Propellant Rocket Engines.pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Best Practices Entry: Best Practice Info:a71 Committee Approval Date: 2000-04-06a71 Center Point of Contact: MSFCa71 Submitted by: Wilson HarkinsSubject: Systems Test Considerations for High Performance Liquid Propellant Rocket Engines Practice: To achieve high overall liquid rocket fueled propulsio
2、n system reliability, conduct a comprehensive test program that verifies and validates the liquid rocket engines operation as it interacts and interfaces with other elements of the propulsion system, (i.e., structures, propellant feed systems, propellant tankage, and control electronics).Programs th
3、at Certify Usage: This practice has been used on Space Shuttle Main Engine (SSME), and Main Propulsion Test Article (MPTA) testing at MSFC, Rocketdyne, and Stennis Space Center.Center to Contact for Information: MSFCImplementation Method: This Lesson Learned is based on Reliability Practice number P
4、T-TE-1439 from NASA Technical Memorandum 4322A, NASA Reliability Preferred Practices for Design and Test.Experience in systems testing of the Space Shuttle Main Engine has shown that integrated propulsion system testing, (1) provides the necessary test data for “model basing,“ thus enhancing the rel
5、iability of system analysis techniques; (2) integrates vehicle hardware, ground hardware, and procedures for propellant loading, safing, and firing operations; (3) provides a resource for determining stage/engine design margins, establishing redlines, developing procedures and time lines, and confir
6、ming extrapolated criteria used in engine development; (4) identifies potential risks for catastrophic flight failure, vehicle hardware damage, and launch complex damage; and (5) identifies potential risks of a Provided by IHSNot for ResaleNo reproduction or networking permitted without license from
7、 IHS-,-,-delayed initial launch and subsequent launches.Implementation Method:I. Background:The Space Shuttle Main Propulsion Test Article (MPTA) program was conducted at NASAs Stennis Space Center test site in Mississippi. The program involved NASA and Space Shuttle element contractors. The tests i
8、ncluded an orbiter aft fuselage with three Space Shuttle Main Engines, an External Tank, and related ground and flight support equipment. Three non-firing tests and twelve combination development/verification firings met planned pretest objectives. The main propulsion test article was of a flight co
9、nfiguration with a few practical exceptions. External Tank insulation was of non-flight configuration. The auxiliary power unit was simulated by a ground powered hydraulic system. The Shuttle Avionics Test Set was used for propulsion system control rather than flight computers. A special load bearin
10、g structure was provided on the test stand to react against the engines thrust. Non-flight hardware was used for payload bay purge into the aft compartment, propellant loading, ground umbilical disconnects, and some Ground Support Equipment consoles.II. Propulsion System TestingTwenty hot-firing att
11、empts were required to meet the requirements of the 12 test series. Hot firing aborts were distributed throughout the 20 firing attempts, although the frequency of occurrence decreased after the sixth test series or after 50 percent of the test program was completed. Twenty-six terminal counts were
12、required. Fourteen of these were required during the first six firing attempts. Hydrogen leakage within the aft compartment occurred on 12 tests. Two tests experienced high leaks.The degree of severity of some of the test failures underscores both the risk involved in propulsion system development a
13、nd the absolute necessity of this type of testing in order to avoid and eliminate these types of failures during a flight mission. For example, fires occurred in nine firings. Eight of the nine fires resulted from engine discrepancies. Four of the fires at the vehicle base were typical of main fuel
14、valve leaks through the engine after shutdown. One aft compartment fire resulted in extensive hardware damage. Two external fires produced significant damage to the vehicle and facility, particularly to the instrumentation.III. Changes and Modifications Brought About by the Main Propulsion Test Arti
15、cle (MPTA) ProgramThe important issues that were addressed in the Space Shuttle Program to enhance the reliability, safety, and performance of the vehicle by MPTA testing were (1) unworkable designs and procedures were made workable by changes and then verified, (2) workable designs and procedures,
16、for which adjustments to achieve acceptance were initially anticipated, were tested and the adjustments were accomplished. Many action items resulted and were resolved in each test series. Table 1 is an example listing of some of the most important action items that resulted from the Provided by IHS
17、Not for ResaleNo reproduction or networking permitted without license from IHS-,-,-propellant loading test, an early test where there was not a hot firing. Thirty to forty similar actions from a hot firing test were not unusual.Table 1. Example Action Items From Engine System Testinga71 Review LH2hi
18、gh point feedline liquid level sensor operation during propellant load test and repair. Review the need for redundancy.a71 Determine the cause of tripped circuit breaker for LH2recirculation pump #2.a71 Determine requirements for a backup GHe injection system for the LOX antigeyser system operationa
19、71 Review the system requirements and reactivate MEC backup power.a71 Provide necessary engineering to connect the KSC hazardous gas detection system to the LH2vent system.a71 Perform special cryogenic test of LOX and LH2auxiliary dump valves using a solenoid actuated system as well as the existing
20、pressure control actuation system and recommend system changes required to improve valve performancea71 Review the need for changing the 1/8“ sample line on the bottom of the LH2tank to 1/4“ or larger line to facilitate tank sampling and verification of purge procedures.Testing identified oversights
21、 which could have resulted in serious consequences under differing circumstances later in the development program. For example, design and manufacturing methods were changed to prevent the release of large hydrogen quantities as a result of main fuel valve structural failure. Design changes were mad
22、e to prevent fuel preburner burn-through and associated engine software changes were made to facilitate automated prevalve closure under all failure conditions. Manual closure was delayed under some failure conditions until the prevalve benefits were seriously compromised. Changes to software correc
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS07632000LESSONSLEARNEDSYSTEMSTESTCONSIDERATIONSFORHIGHPERFORMANCELIQUIDPROPELLANTROCKETENGINESPDF

链接地址:http://www.mydoc123.com/p-1018409.html