REG NASA-LLIS-0666-2000 Lessons Learned Foreign Object Debris (FOD) Program at KSC.pdf
《REG NASA-LLIS-0666-2000 Lessons Learned Foreign Object Debris (FOD) Program at KSC.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-0666-2000 Lessons Learned Foreign Object Debris (FOD) Program at KSC.pdf(10页珍藏版)》请在麦多课文档分享上搜索。
1、Best Practices Entry: Best Practice Info:a71 Committee Approval Date: 2000-03-06a71 Center Point of Contact: KSCa71 Submitted by: Wil HarkinsSubject: Foreign Object Debris (FOD) Program at KSC Practice: Enhance the Reliability of Flight Hardware Processing Systems by including in the Program a relia
2、ble Foreign Object and Debris (FOD) policy and related procedures for use during launch and landing operations, vehicle and payload processing, and maintenance activities at designated areas of Kennedy Space Center (KSC) and off-site landing facilities under KSC responsibility.Programs that Certify
3、Usage: This practice has been used on the Space Shuttle Program as well as military and civilian aircraft operations. KSC use includes all processing areas: three Orbiter Processing Facilities (OPFs), Vehicle Assembly Building (VAB), Launch Pads 39 A no ingress or egress obstacles; no unmarked or un
4、identified tools, parts, equipment, chemicals, etc.; no unsecured or untethered items above ground level; no unkempt areas; no hazards; nothing left in the area that does not have a specific purpose for work in process or functional requirement or is not stored properly.4. 5. Only authorized personn
5、el with valid requirements to perform work or surveillance will be allowed in the controlled work areas.6. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-7. Personnel entering into the designated flight hardware operational processing area will prac
6、tice the “clean as you go“ method, cleaning up assigned tools, parts, equipment, worksite, etc. as practical, during and at the end of the assigned task and/or shift.8. 9. Organizations having possession of hardware inventories and/or tools and equipment will be responsible for those items and have
7、a closed-loop tracking system, with tools and equipment traceable to location and user.10. 11. The user is responsible for the physical location of all items carried into the flight hardware operational processing area and will be held accountable.12. 13. Perform random inventory of toolbags upon in
8、gress and egress of the flight element for compliance with the requirements. Report discrepancies.14. 15. Each employee is expected to practice safety and good housekeeping habits and prevent FOD at all times in the designated flight hardware areas.16. 17. Each operational processing area will have
9、a FOD control board to hold clipboards for daily checklists and related FOD prevention data. FOD boards will be kept neat and clean.18. 19. All personnel will view the KSC FOD Prevention Video and sign a personal commitment to “Clean As You Go“. A copy will be on record in individual administrative
10、files.20. 21. Site Managers will be appointed by the Site Director.22. 23. FOD prevention walkdowns will be scheduled on a regular basis in all operational processing areas by the Site Manager and the Site FOD Prevention Office. The Site Manager or delegate will attend all FOD prevention walkdowns.
11、The work area will be checked for potential hazards and anything out of place that could potentially cause damage to flight hardware or injury to personnel. In addition to the scheduled walkdowns, daily walkdowns will be conducted by Site FOD Monitors.24. 25. Site FOD Monitors will be selected for e
12、ach shift at regular shift meetings, on a volunteer basis. Alternates will be appointed to cover absenteeism. Monitor duty will last for 1 month and will be in addition to normal work responsibilities. Before an employee can be selected for a second time, each work group member will have the opportu
13、nity to serve as Site FOD Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Monitor.26. 27. Ensure that FOD prevention is stressed with subcontractors prior to award of contracts, have subcontractors sign a letter agreeing to follow the “clean as you g
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS06662000LESSONSLEARNEDFOREIGNOBJECTDEBRISFODPROGRAMATKSCPDF

链接地址:http://www.mydoc123.com/p-1018313.html