1、*USACE / NAVFAC / AFCESA / NASA UFGS-21 22 00.00 20 (May 2011)-Preparing Activity: NAVFAC SupersedingUFGS-21 22 00.00 20 (November 2009)UFGS-21 22 00.00 20 (April 2006)UFGS-13966N (September 2000)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2011*SECTION TA
2、BLE OF CONTENTSDIVISION 21 - FIRE SUPPRESSIONSECTION 21 22 00.00 20HALON 1301 FIRE EXTINGUISHING05/11PART 1 GENERAL1.1 REFERENCES1.2 GENERAL REQUIREMENTS1.2.1 Description of Work1.3 SUBMITTALS1.4 QUALITY ASSURANCE1.4.1 Record of Prior Installations1.4.2 Halon Fire Extinguishing System1.4.3 Manufactu
3、rers Representative1.5 DESIGN OF HALON FIRE EXTINGUISHING SYSTEMS1.5.1 Piping Layout and Wiring Diagrams1.5.2 Calculations1.5.3 Flooding Concentration1.5.3.1 Halon Concentration1.5.4 Discharge Time1.5.5 Reserve Supplies1.5.6 Record Drawings1.6 SYSTEM CONTROL1.6.1 Controls1.6.2 Sequence of Operation1
4、.6.2.1 Activation By Manual Station1.6.2.2 Manual Activation of Inhibit Switch1.6.3 Transfer to reserve supply1.6.4 Remote Control Station Operating InstructionsPART 2 PRODUCTS2.1 PIPING2.1.1 Pipe2.1.2 Fittings2.1.3 Pipe Hangers and Supports2.1.4 Pipe Sleeves2.1.5 Escutcheon PlatesSECTION 21 22 00.0
5、0 20 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-2.1.6 Discharge Nozzles2.1.7 Storage Cylinders2.1.8 Jointing Compound2.2 CONTROL PANEL2.3 SECONDARY POWER SUPPLY2.3.1 Storage Batteries2.3.2 Battery Charger2.4 MANUAL ACTUATION STATIONS2.5 SM
6、OKE DETECTORS2.5.1 Ionization Detectors2.5.2 Photoelectric Detectors2.5.3 Detector Spacing and Location2.6 DUCT SMOKE DETECTORS2.7 INHIBIT SWITCH2.8 ALARM SIGNALING DEVICES2.8.1 Audible Alarms2.8.2 Visual Alarms2.9 MAIN ANNUNCIATOR2.9.1 Annunciation Zones2.9.2 Annunciator Panels2.10 AUTOMATIC FIRE D
7、AMPERS2.11 ELECTROMAGNETIC DOOR HOLDER RELEASE2.12 ELECTRICAL WORK2.12.1 Wiring2.12.2 Operating Power2.12.3 Conductor IdentificationPART 3 EXECUTION3.1 PIPE INSTALLATION3.2 FIELD PAINTING3.2.1 Systems in Unfinished Areas3.2.2 Systems in All Other Areas3.3 FIELD TESTING3.3.1 Preliminary Tests3.3.2 Fo
8、rmal Inspection and Tests3.3.2.1 System Function Tests Without Halon Discharge3.3.2.2 Halon Discharge Tests3.4 OPERATING INSTRUCTIONS3.5 TRAINING REQUIREMENTS- End of Section Table of Contents -SECTION 21 22 00.00 20 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without
9、license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-21 22 00.00 20 (May 2011)-Preparing Activity: NAVFAC SupersedingUFGS-21 22 00.00 20 (November 2009)UFGS-21 22 00.00 20 (April 2006)UFGS-13966N (September 2000)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated
10、April 2011*SECTION 21 22 00.00 20HALON 1301 FIRE EXTINGUISHING05/11*NOTE: This guide specification covers the requirements for Halon 1301 fire extinguishing systems for protection of data processing equipment and similar electronics occupancies.Adhere to UFC 1-300-02 Unified Facilities Guide Specifi
11、cations (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate informati
12、on.Remove information and requirements not required in respective project, whether or not brackets are present.Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR).*NOTE: Use of this guide specification requ
13、ires a waiver in accordance with NAVFAC Ozone Depleting Substances (ODS) Procurement Policy and Procedures with the approval of a Senior Acquisition Officer (SAO). With minor changes, this guide can be adapted to other occupancies or needs, such as the protection of electric generators and flight si
14、mulators. The extent and location of the work to be accomplished, and the type of electric service, cables, wire, conduit, location of storage cylinders, actuating stations, control panels, storage batteries, battery chargers, and accessories indicated, specified, or necessary for the complete insta
15、llation required shall be indicated on the project drawings. If there are questions concerning SECTION 21 22 00.00 20 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-system design, the cognizant Engineering Field Division Fire Protection Engine
16、er should be consulted. Due to the toxicity of decomposed Halon, an engineered smoke and Halon removal system (not part of this specification) will be required for each protected space. Such a system shall be manually key operated, for fire department use only. See also NFPA 12A section on relief ve
17、nting.*NOTE: The following information should be shown on the drawings:1. On the electrical power floor plans show locations of control panel, annunciator(s), audible and visual alarm devices, manual actuation stations, point of connection to the building fire evacuation alarm system, remote trouble
18、 device, and point of connection to the incoming power supply and fusible safety switch. Do not show conduit sizes or number of conductors for DC circuits. Do not show locations of smoke detectors.2. Show single line riser diagram for all detection, activation, and alarm circuits. Connection of equi
19、pment shall be indicated by circuit runs and not conduit runs. Do not indicate number and size of conductors for interconnection of fire alarm components.3. On the mechanical floor plans, show locations for Halon storage containers. Show areas of system coverage, with zone designations (if multiple
20、zones). Do not show Halon piping layout and nozzle placement.*PART 1 GENERAL1.1 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organi
21、zation, designation, date, and title.Use the Reference Wizards Check Reference feature when you add a RID outside of the Sections Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizards Check Reference feature to update the issue dates.Referenc
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- NAVYUFGS21220000202011HALON1301FIREEXTINGUISHING 卤化 1301 消防设施 PDF

链接地址:http://www.mydoc123.com/p-984791.html