1、*USACE / NAVFAC / AFCESA / NASA UFGS-01 32 16.00 20 (November 2009)-Preparing Activity: NAVFAC SupersedingUFGS-01 32 16.00 20 (April 2006)UFGS-01320N (December 2003)UNIFIED FACILITIES GUIDE SPECIFICATIONS*SECTION TABLE OF CONTENTSDIVISION 01 - GENERAL REQUIREMENTSCONSTRUCTION PROGRESS DOCUMENTATION1
2、1/09PART 1 GENERAL1.1 SUBMITTALS1.2 ACCEPTANCE1.3 SCHEDULE FORMAT1.3.1 Bar Chart Schedule1.3.2 Network Analysis Schedule (NAS)1.3.2.1 NAS Submittals and Procedures1.4 UPDATED SCHEDULES1.5 3-WEEK LOOK AHEAD SCHEDULE1.6 CORRESPONDENCE AND TEST REPORTS:PART 2 PRODUCTSPART 3 EXECUTION- End of Section Ta
3、ble of Contents -SECTION 01 32 16.00 20 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-01 32 16.00 20 (November 2009)-Preparing Activity: NAVFAC SupersedingUFGS-01 32 16.00 20 (April 2006)UFGS-01320N (Decem
4、ber 2003)UNIFIED FACILITIES GUIDE SPECIFICATIONS*SECTION 01 32 16.00 20CONSTRUCTION PROGRESS DOCUMENTATION11/09*NOTE: This guide specification covers the requirements for the preparation and use of Design-Bid-Build Schedules.Specification Section 01 32 16.00 20 may be inserted when the contract amou
5、nt is expected to be less than $750,000 and the contract duration is expected to be less than 6 months, when there are no known critical completion dates for the Supported Command. Use Specification Section 01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS) when there is a known critical completion dat
6、e for the Supported Command. Consult the Administering FEAD/ROICC Office on all construction contracts to determine which guide specification to insert.This section shall be reviewed and approved by the administering FEAD/ROICC prior to completion of the Invitation For Bids (IFB).Edit bracketed item
7、s for project specific requirements by choosing applicable items(s) or insert appropriate information.Comments and suggestions on this guide specification are welcome and should be directed to the Technical Proponent of the specification. A listing of technical proponents, including their organizati
8、on designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL1.1 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES. Edit the SECTION 01 32 16.00 20 Pag
9、e 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-following list to reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that
10、the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a “G” if the submittal is sufficiently important or complex in cont
11、ext of the project.*Government approval is required for submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-01 Preconstruction SubmittalsCo
12、nstruction schedule; G1.2 ACCEPTANCE*NOTE: Select the first bracketed option when a line or bar chart is sufficient to administer theproject. Generally, line and bar chart constructionschedules should only be specified for very simple,low dollar value projects, with short contract duration. Always s
13、elect the Network Analysis Schedule (NAS) option when there is a known critical completion date for the Supported Command. Consult with the administering FEAD/ROICC to determine the form of construction schedule required.*Prior to the start of work, prepare and submit to the Contracting Officer for
14、acceptance a construction schedule in the form of a Bar ChartNetwork Analysis Schedule (NAS) in accordance with the terms in Contract Clause “FAR 52.236-15, Schedules for Construction Contracts,“ except as modified in this contract. Acceptance of an error free Baseline Schedule and updates is a cond
15、ition precedent to processing the Contractors pay request.1.3 SCHEDULE FORMAT*NOTE: Delete bracketed 1.3.1 Bar Chart Schedule from TABLE OF CONTENTS and requirements if a Network Analysis Schedule is required on this project.*1.3.1 Bar Chart ScheduleThe Bar Chart shall show submittals, government re
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- NAVYUFGS01321600202009CONSTRUCTIONPROGRESSDOCUMENTATION 施工进度 文件 PDF

链接地址:http://www.mydoc123.com/p-984685.html