1、*USACE / NAVFAC / AFCESA / NASA UFGS-01 45 04 (August 2008)-Preparing Activity: NASA SupersedingUFGS-01 45 00.00 40 (January 2008)UNIFIED FACILITIES GUIDE SPECIFICATIONS*SECTION TABLE OF CONTENTSDIVISION 01 - GENERAL REQUIREMENTSSECTION 01 45 04NASA QUALITY CONTROL08/08PART 1 GENERAL1.1 SUMMARY1.2 S
2、UBMITTALS1.2.1 Quality Assurance (QA) Plan1.2.2 Records1.3 QUALITY ASSURANCE1.3.1 Qualifications1.3.2 Quality Control Requirements1.3.2.1 Management and Organization1.3.2.2 Identification and Data Retrieval1.3.2.3 Procurement1.3.2.4 Receiving Inspection System1.3.2.5 Nonconforming Articles and Mater
3、ial Control1.3.2.6 Fabrication, Process, and Work Control1.3.2.7 Quality Control Records1.3.2.8 Drawings and Change Control1.3.3 Quality Inspections1.3.3.1 Government Inspections1.3.3.2 Contractors Quality Inspections1.3.4 Field Services1.3.4.1 Responsibility for Inspection and Testing1.3.4.2 Inspec
4、tion and Test Records1.4 HANDLING AND STORAGE1.5 SEQUENCING AND SCHEDULINGPART 2 PRODUCTSPART 3 EXECUTION- End of Section Table of Contents -SECTION 01 45 04 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-0
5、1 45 04 (August 2008)-Preparing Activity: NASA SupersedingUFGS-01 45 00.00 40 (January 2008)UNIFIED FACILITIES GUIDE SPECIFICATIONS*SECTION 01 45 04NASA QUALITY CONTROL08/08*NOTE: This specification covers the requirements for inspections, test reports, and contractor obligations for establishing ef
6、fective quality assurance procedures.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whethe
7、r or not brackets are present.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended chan
8、ges to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL1.1 SUMMARYThe requirements of this Section apply to, and are a component part of, each section of the specifications.1.2 SUBMITTALS*NOTE: Review Submittal Description (SD) definitions in Section 01 33 00 SUBMITTAL P
9、ROCEDURES and edit the following list to reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked
10、 with a “G”. Only SECTION 01 45 04 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-delete an existing “G” if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a “G” if the submittal i
11、s sufficiently important or complex in context of the project.For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the “G“ designation to indicate the approving authority. Codes for Army projects using the Res
12、ident Management System (RMS) are: “AE“ for Architect-Engineer; “DO“ for District Office (Engineering Division or other organization in the District Office); “AO“ for Area Office; “RO“ for Resident Office; and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy, Air Forc
13、e, and NASA projects.Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.*Government approval is required for submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approva
14、l.for information only. When used, a designation following the “G“ designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-06 Test ReportsSubmit the following items in accordance with paragr
15、aph entitled, “Records,“ of this section.Quality Control DataQuality Control Coordinating ActionsQuality Control TrainingInspection RecordsLetters of Authority or DelegationField TestsFactory TestsSD-07 CertificatesSubmit a detailed written statement describing procedures that will be implemented to
16、 achieve quality on the project according to the paragraph entitled, “Quality Assurance (QA) Plan,“ of this section.Submit the following in accordance with paragraph entitled, “Qualifications,“ of this section.Contractors Quality Representative QualificationsSpecial CertificationsSECTION 01 45 04 Pa
17、ge 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.2.1 Quality Assurance (QA) PlanAddress the following within the QA Plan:Description of the authority, responsibilities and coordinating procedures, of on-site/off-site quality assurance personnel,
18、 including those QA personnel not under direct control of the Contractor.List personnel designated by the Contractor to accomplish the work required by the contract.Provide an appendix with a copy of each form, report format, or similar record to be used in the QA program.Contractors organization th
19、at handles construction contract activities.Contractors operational plan for accomplishing and reviewing work controls, fabrication controls, certifications, and documentation of quality control operations, inspections, and test records, including those for subcontractors.Include within these provis
20、ions the methods to be used during the procurement cycle (order to delivery) for those materials or equipment that require source inspections, shop fabrications, or similar operations located separately from the work site.Description of on-site personnel training.Certification(s) of personnel, proce
21、dures, processes, and equipment.Nondestructive testing requirements.Identification of independent certifying and testing laboratories.1.2.2 RecordsInclude all quality control data; factory tests or manufacturers certifications, quality control coordinating actions; records of quality control trainin
22、g/certifications as well as routine hydrostatic, electrical continuity, grounding, welding, line cleaning, field tests and similar tests. Quality records must be available for examination by the Contracting Officer.Furnish legible copies of the test and inspection records to the Contracting Officer.
23、 Cover work placement traceable to the contract schedule, specifications and drawings, and must be verified by the Contractor.Submit for approval, the narrative description of an inspection system which provides for compliance with the quality requirements and technical criteria of the contract with
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- NASAUFGS0145042008NASAQUALITYCONTROLNASA 质量 控制 代替 NASAUFGS0145000040PDF

链接地址:http://www.mydoc123.com/p-836570.html