MSFC NASA MPR 7123 2-2009 TECHNICAL REVIEWS AND REVIEW ITEM DISCREPANCY (RID) PROCESSING MSFC PROGRAMS AND PROJECTS《技术审查和审查项目差异(rid)处理 马歇尔太空飞行中心计划和项目》.pdf
《MSFC NASA MPR 7123 2-2009 TECHNICAL REVIEWS AND REVIEW ITEM DISCREPANCY (RID) PROCESSING MSFC PROGRAMS AND PROJECTS《技术审查和审查项目差异(rid)处理 马歇尔太空飞行中心计划和项目》.pdf》由会员分享,可在线阅读,更多相关《MSFC NASA MPR 7123 2-2009 TECHNICAL REVIEWS AND REVIEW ITEM DISCREPANCY (RID) PROCESSING MSFC PROGRAMS AND PROJECTS《技术审查和审查项目差异(rid)处理 马歇尔太空飞行中心计划和项目》.pdf(63页珍藏版)》请在麦多课文档分享上搜索。
1、CHECK THE MASTER LIST at https:/repository.msfc.nasa.gov/directives/directives.htm VERIFY THAT THIS IS THE CORRECT VERSION BEFORE USE MPR 7123.2 BASELINE EFFECTIVE DATE: July 10, 2009 EXPIRATION DATE: July 10, 2014 MARSHALL PROCEDURAL REQUIREMENTS DA01 TECHNICAL REVIEWS AND REVIEW ITEM DISCREPANCY (
2、RID) PROCESSING, MSFC PROGRAMS AND PROJECTS Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Marshall Procedural Requirements DA01 Technical Reviews and Review Item Discrepancy (RID) Processing, MPR 7123.2 Revision: Baseline MSFC Programs and Projects
3、 Date: July 10, 2009 Page 2 of 63 DOCUMENT HISTORY LOG Status (Baseline/ Revision/ Canceled) Document Revision Effective Date Description Baseline 7/10/2009 Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Marshall Procedural Requirements DA01 Technic
4、al Reviews and Review Item Discrepancy (RID) Processing, MPR 7123.2 Revision: Baseline MSFC Programs and Projects Date: Page 3 of 63 CHECK THE MASTER LIST at https:/repository.msfc.nasa.gov/directives/directives.htm VERIFY THAT THIS IS THE CORRECT VERSION BEFORE USE TABLE OF CONTENTS Preface P.1 Pur
5、pose P.2 Applicability P.3 Authority P.4 Applicable Documents P.5 References P.6 Cancellation Document Content 1. Definitions 2. Responsibilities 3. Procedures 4. Records 5. Flow Diagram Appendix A Conducting Successful Reviews A.1 Program/Project Readiness A.2 RID Criteria/Ground Rules A.3 PreRID S
6、creening A.4 RID Tracking A.5 Review Kickoff Meeting A.6 Pre-board and Board A.7 Example RID form Appendix B Acronyms Appendix C Systems Engineering Review “Focus Items” Figure A 4-1 Typical RID Tracking Chart Example Table 3-1 Flight Systems and Ground Support Project Reviews Table C-1A PDR “Focus
7、Items” Table C-1B PDR “Focus Items” (continued) Table C-2A Life Cycle “Focus Item” Maturity Table C-2B Life Cycle “Focus Item” Maturity (continued) Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Marshall Procedural Requirements DA01 Technical Review
8、s and Review Item Discrepancy (RID) Processing, MPR 7123.2 Revision: Baseline MSFC Programs and Projects Date: Page 4 of 63 CHECK THE MASTER LIST at https:/repository.msfc.nasa.gov/directives/directives.htm VERIFY THAT THIS IS THE CORRECT VERSION BEFORE USE PREFACE P.1 PURPOSE This Marshall Procedur
9、al Requirement (MPR) document provides requirements for planning and conducting formal Technical Reviews compliant with NASA Procedural Requirements (NPR) 7123.1 and NPR 7120.5. It provides a consistent and disciplined process to assure thorough technical reviews and adequate management oversight pr
10、ior to authorization for programs/projects to proceed to the next stage of development. P.2 APPLICABILITY This MPR applies to the personnel, programs, projects, and activities at Marshall Space Flight Center (MSFC) and MSFCs Michoud Assembly Facility (MAF), including contractors and resident agencie
11、s to the extent specified in their respective contracts or agreements. (“Contractors,” for purposes of this paragraph, include contractors, grantees, Cooperative Agreement recipients, Space Act Agreement partners, or other agreement parties.) P.3 AUTHORITY a. NPR 7120.5, “NASA Space Flight Program a
12、nd Project Management Requirements” b. NPR 7123.1, “NASA Systems Engineering Processes and Requirements” P.4 APPLICABLE DOCUMENTS a. NPR 1441.1, “NASA Record Retention Schedules” b. MPD 1150.1, “Establishment of Councils, Boards, and Committees” c. MPR 1440.2, “MSFC Records Management Program” d. MP
13、R 7120.1, “Program/Project Planning” e. MPR 7123.1, “MSFC Systems Engineering Processes and Requirements” f. MPR 8040.1, “Configuration Management, MSFC Programs/Projects” g. MPR 8823.1, “Design Control of Facilities” P.5 REFERENCES a. NASA/SP-2007-6105, “NASA Systems Engineering Handbook” Provided
14、by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Marshall Procedural Requirements DA01 Technical Reviews and Review Item Discrepancy (RID) Processing, MPR 7123.2 Revision: Baseline MSFC Programs and Projects Date: Page 5 of 63 CHECK THE MASTER LIST at https:/r
15、epository.msfc.nasa.gov/directives/directives.htm VERIFY THAT THIS IS THE CORRECT VERSION BEFORE USE b. MPR 8500.1, “MSFC Environmental Management Program” c. MSFC-HDBK-3173, “Project Management and Systems Engineering Handbook” P.6 CANCELLATION None Original signed by Robert M. Lightfoot Acting Dir
16、ector Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Marshall Procedural Requirements DA01 Technical Reviews and Review Item Discrepancy (RID) Processing, MPR 7123.2 Revision: Baseline MSFC Programs and Projects Date: Page 6 of 63 CHECK THE MASTER L
17、IST at https:/repository.msfc.nasa.gov/directives/directives.htm VERIFY THAT THIS IS THE CORRECT VERSION BEFORE USE DOCUMENT CONTENT 1. DEFINITIONS 1.1 Board - The management panel that serves as the final disposition authority for RIDs. This is an ad hoc Board, in accordance with MPD 1150.1. 1.2 Ce
18、nter Management Council (CMC) - The council at a Center that performs oversight of all Center programs and projects by evaluating all program and project work executed at the Center. 1.3 Data Package - Package of Review Documentation and supporting Reference Documents, provided for evaluation during
19、 the review. 1.4 Decision Authority (DA) - The Agencys responsible individual who authorizes the transition at a Key Decision Point (KDP) to the next life-cycle phase for a program/project. 1.5 Designated Governing Authority (DGA) - The management entity above the program, project, or activity level
20、 with technical oversight responsibility. The Center Director or the person or organization that has been designated to ensure the appropriate level of technical management oversight. The DGA is the final approval signature on the Systems Engineering Management Plans (SEMPs), waiver authorizations,
21、and other key technical documents. 1.6 Document Developer - Individual or organization involved in development of the documents comprising the Data Package. 1.7 Disposition - Authorized Individual, Committee, Board and/or Pre-board approval of a proposed plan of action to resolve a RID. 1.8 Editoria
22、l Comments - Comments that do not relate to or affect technical content, e.g., typographical errors, punctuation, grammar, misspelled words, different way of saying the same thing, and format. 1.9 KDP - An event where the DA makes a decision on the readiness of a program/project to progress to the n
23、ext phase of the life-cycle. 1.10 Mission Management Team (MMT) - The management team that evaluates performance during specific missions and makes decisions on implementing mission operations to obtain the mission objectives. 1.11 Peer Review - Independent evaluation by internal or external subject
24、 matter experts who do not have a vested interest in the work product under review. Peer reviews can be planned and focused reviews conducted on selected work products by the producers peers to identify defects and issues prior to that work product moving into a milestone review or approval cycle. P
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- MSFCNASAMPR712322009TECHNICALREVIEWSANDREVIEWITEMDISCREPANCYRIDPROCESSINGMSFCPROGRAMSANDPROJECTS 技术 审查

链接地址:http://www.mydoc123.com/p-822882.html