FORD FLTM BB 117-01-2014 RESISTANCE SPOT WELDING ACCEPTANCE TEST FOR ALUMINUM.pdf
《FORD FLTM BB 117-01-2014 RESISTANCE SPOT WELDING ACCEPTANCE TEST FOR ALUMINUM.pdf》由会员分享,可在线阅读,更多相关《FORD FLTM BB 117-01-2014 RESISTANCE SPOT WELDING ACCEPTANCE TEST FOR ALUMINUM.pdf(8页珍藏版)》请在麦多课文档分享上搜索。
1、 FORD LABORATORY TEST METHOD BB 117-01 Date Action Revisions Rev. 0 2014 04 01 Released E. Hetrick / W. Moision, NA Controlled document at www.MATS Copyright 2014, Ford Global Technologies, Inc. Page 1 of 8 RESISTANCE SPOT WELDING ACCEPTANCE TEST FOR ALUMINUM Application The procedure outlined herei
2、n is a standard welding acceptance test for a given aluminum alloy + pretreatment + lubricant + heat treatment system of a specific gauge from a specific supplier. Upon passing this procedure, the aluminum alloy system (gauge, pretreatment, lubricant, and heat treatment-specific) is recognized as re
3、sistance weldable by Ford Motor Company. Essentially, it is a procedure to approve the capability of a supplier or Company activity to obtain a spot weldable surface. This procedure shall constitute a method by which such a supplier or Company activity may become an approved supplier of spot weldabl
4、e aluminum and as a quality control procedure for checking consistency of weldability. Chemicals, materials, parts, and equipment referenced in this document must be used and handled properly. Each party is responsible for determining proper use and handling in its facilities. Equipment Required Res
5、istance Spot Welder This test shall be conducted using a Medium Frequency Direct Current (MFDC) inverter combined with servo-actuated force including force feedback and servo-inverter synchronization. The weld gun shall be capable of electrode forces up to 10 kN. It shall be equipped with a Ford app
6、roved aluminum resistance welding control and gun. The weld controller shall have current capacities to meet the requirements of the range of material to be tested at a minimum rate of 10 welds per minute. The welder must be equipped with electrode holders capable of sufficient water flow capacity s
7、o that a minimum of 2.0 gal/min will flow through each electrode holder with a 20 psi pressure differential. In addition, other cooling circuits (e.g. transformer, secondary conductors, and control panel) must meet the minimum manufacturer-specified flow rates and temperature requirements at the req
8、uisite duty cycle. Welding Electrodes Ford standard, male, ”, “hi water flow“ electrode caps, with two inch radius face (Ford part number: WC11R263), as specified in WC1-002, will be used for all tests. The electrode caps must be made from RWMA Class 2 CuCr (ISO Type A2/1) material, unless otherwise
9、 specified by the Ford Vehicle Operations Joining Supervisor. The electrode caps, adapters and holders to be used will be found under the following standards: Identification Ford Standard Designation Electrode Cap WC1-002 WC11R263-A2/1 Cap Adapter WB1 WB1S36-1XX Tip Dresser An electric or pneumatic,
10、 automatic tip dresser or a handheld tip dresser is required to dress the top and bottom electrodes to clean, fresh copper during the test setup and test procedures. Cutter blade and holder must be matched to the WC11R263 electrode cap face. Changer & Dresser Corporation Cutter Part Number KTW(U)-14
11、0 and Holder Part Number KTWH(U)-140 or equivalent are required. Knife Edge Caliper Mitutoyo Absolute Digimatic Model No. CD-6”CSX or equivalent is required to measure weld button diameter. FORD LABORATORY TEST METHOD BB 117-01 Copyright 2014, Ford Global Technologies, Inc. Page 2 of 8 Instrumentati
12、on Calibrated Miyachi Weld Tester MM-380A or equivalent, capable of simultaneous measurement of force AND current and/or voltage, is required to set up and document weld schedule. Metallurgical Sample Preparation and Microstructural Feature Measurement Suitable equipment shall be available to cross
13、section, polish, etch, and examine at 10x magnification welded samples. Procedure Surface Preparation of Material The material submitted for approval shall be prepared according to the practice proposed to be used for production quantities. A letter shall accompany the material noting all pertinent
14、data to identify completely the method of preparation. A minimum of 7.5 square meters of material shall be submitted in a width equal to the maximum capability of the surface preparation equipment. The material shall be sheared in 25 mm x 300 mm and 100 mm x 300 mm pieces. Care shall be exercised to
15、 obtain pieces of each size from various positions of its width. All material is to be welded in the as-received condition, with no modification to the temper or surface condition. The Welding Acceptance Test shall be conducted as outlined herein. If failure occurs, the material is rejected. If the
16、material passes the initial Welding Acceptance Test, the unused portion of the submitted material shall be stored on a rack permitting exposure of both surfaces of the sheets to normal shop atmosphere for 90 days. The Welding Acceptance Test is then repeated on the material after 90 days of exposure
17、. Approval Criteria Approval is granted when all of the following conditions are met: (1) Welding Acceptance Test on material before and after 90 days exposure to shop atmosphere produces a minimum of 2500 consecutive acceptable welds on panels without failure. Identical weld parameters are to be us
18、ed on both sets of material (i.e. fresh and post-90-day storage). (2) 25 mm x 300 mm test strips are free of surface expulsion (whiskers), not assignable to operator error. (3) Surface indentation (I1 and I2), as shown in Figure 1, does not exceed 15% of original sheet thickness (t1 and t2, respecti
19、vely). (4) No sheet separation or buckling occurs due to indentation. (5) Surface roughness meets applicable paintability specification requirements. (6) Metallographic acceptance criteria are achieved at setup and at the 2500th weld interval. Following approval, no changes in material or processing
20、 may be made without prior written approval from the responsible Ford activity. I1t1I2t2Figure 1. Measurement of surface indentation FORD LABORATORY TEST METHOD BB 117-01 Copyright 2014, Ford Global Technologies, Inc. Page 3 of 8 Welding Acceptance Test Equipment Setup The electrode caps shall be in
21、stalled in the machine so that they are in precise alignment in the vertical plane and their welding faces are parallel under the electrode force requirement for the thickness of the material under test. Test Setup Procedure The following procedural details shall be followed during the test setup: (
22、1) Contact Ford Vehicle Operations Joining Supervisor for initial weld schedules and weld setup procedures. (2) Dress electrodes prior to commencing setup and after every 5 setup strips. Top and bottom electrode cap faces shall be dressed to clean, fresh copper at each dress interval. (3) Using 25 m
23、m x 300 mm test strips, make six welds on the centerline approximately 35 mm50 mm apart, as shown in Figure 2. (4) Do not measure the first weld on each test strip (the “shunt weld”). (5) Measure the minimum and maximum diameter of the remaining five weld buttons using the method described in the se
24、ction entitled “Determination of Spot Weld Diameter” and record the data on the sheet provided in Appendix A (or similar). (6) Governing metal thickness (GMT) for double panel welding is defined as the thickness of the thinnest sheet. (7) Setup is achieved when the average button diameter of the fiv
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- FORDFLTMBB117012014RESISTANCESPOTWELDINGACCEPTANCETESTFORALUMINUMPDF

链接地址:http://www.mydoc123.com/p-746905.html