CSA C282 LOGBOOK-2015 Emergency electrical power supply for buildings maintenance logbook.pdf
《CSA C282 LOGBOOK-2015 Emergency electrical power supply for buildings maintenance logbook.pdf》由会员分享,可在线阅读,更多相关《CSA C282 LOGBOOK-2015 Emergency electrical power supply for buildings maintenance logbook.pdf(130页珍藏版)》请在麦多课文档分享上搜索。
1、C282 Logbook-15Emergency electrical power supply for buildings maintenance logbookPublished in March 2015 by CSA GroupA not-for-profit private sector organization178 Rexdale Blvd., Toronto, Ontario, Canada M9W 1R31-800-463-6727 416-747-4044Visit our Online Store at shop.csa.caC282 Logbook-15Emergenc
2、y electrical power supply for buildings maintenance logbookTMA trade-mark of the Canadian Standards Association, operating as “CSA Group”ISBN 978-1-77139-860-2 2015 CSA GroupAll rights reserved. No part of this publication may be reproduced in any form whatsoever without the prior permission of the
3、publisher.C282 Logbook-15Emergency electricalpower supply for buildingsmaintenance logbookInspection, test, and maintenance of emergency electrical power supply for buildings 1Table 2 Weekly inspection, test, and maintenance requirements 1Table 3 Monthly inspection (weekly in health care facilities)
4、, test, and maintenance requirements 1Table 4 Semi-annual inspection, test, and maintenance requirements 1Table 5 Annual inspection, test, and maintenance requirements 2Table 6 Quinquennial (every five years) inspection, test, and maintenance requirements 3Weekly inspection, test, and maintenance re
5、quirements 5Monthly inspection, test, and maintenance requirements 93Semi-annual inspection, test, and maintenance requirements 103Annual inspection, test, and maintenance requirements Sheet #1 105Annual inspection, test, and maintenance requirements Sheet #2 107Annual inspection, test, and maintena
6、nce requirements Sheet #3 109Quinquennial (every five years) inspection, test, and maintenance requirements 111Unscheduled maintenance 113March 2015 Refer to CSA C282-15, Emergency electrical power supply for buildings 1 2015 CSA GroupInspection, test, and maintenance of emergency electrical power s
7、upply for buildingsTable 2 Weekly inspection, test, and maintenance requirements1. Consumables:(a) Inspect auxiliary supply tank fuel level (gas pressure) and main tank level (gas pressure) (if applicable). There shall be a minimum supply of 2 h (see Clause 7.3.1). (b) Inspect lubricating oil level.
8、(c) Inspect engine coolant level.(d) Inspect engine, generator, fuel tank(s), and cooling systems for leakage.(e) Inspect for proper operation of fuel transfer pump (if applicable).(f) Inspect fuel filter for contamination if filter is equipped with a transparent bowl.2. Starter system:(a) Inspect e
9、lectric starter for cleanliness, mounting, and terminal security.(b) Air starter: (i) Inspect air tanks for pressure.(ii) Inspect valves for leakage.(iii) Test auxiliary engine and compressor for proper operation.(iv) Bleed off any condensation.3. Batteries and charging equipment:(a) Inspect all bat
10、tery cells for correct electrolyte fill level (applicable to vented or flooded lead-acid batteries only).(b) Test all battery cells for correct electrolyte specific gravity (applicable to vented or flooded lead-acid batteries only).(c) Inspect electrical connections for tightness and evidence of cor
11、rosion.(d) Inspect battery for cleanliness and dryness between terminals.(e) Inspect charger electrical connections for cleanliness and tightness.4. Engine:(a) Test lubricant and/or coolant heaters for proper operation.(b) Inspect governor control linkages and oil level (if applicable).(c) Inspect f
12、uel pump oil sump (if applicable).(d) Inspect fan belts for correct tension and wear. 5. Control panel:(a) Inspect control panel covers for security.(b) Test annunciator lamps to confirm that they are operational.(c) Inspect control panel settings (ensure that the unit is ready for automatic start-u
13、p).(d) Test remote visual and audible trouble signals at the building fire alarm panel. 6. Inspect air control louvre settings to ensure proper operation.7. Test emergency lighting unit(s).8. Verify whether room temperature is above 10 C.9. Inspect generator and transfer switch room(s) for cleanline
14、ss and accessibility to all components of the emergency system. 10. Correct all defects found during inspections and tests.11. Record all inspections, tests, and corrective actions in the log (see Clause 11.5.3).Note: The work described in this Table shall be carried out by a competent person or ind
15、ividuals trained by the system manufacturer.Table 3 Monthly (weekly in health care facilities) inspection, test, and maintenance requirements1. Complete all items specified in Table 2.2. Test and verify the entire system as follows:(a) Simulate a failure of the normal electrical supply to the buildi
16、ng. (b) Verify that the battery charger current output increases while cranking.(c) Operate the system under at least 30% of the rated load for 60 min.(d) Operate all automatic transfer switches under load. (e) Inspect brush operation for sparking, if applicable.(f) Inspect for bearing seal leakage.
17、(g) Inspect for correct operation of all auxiliary equipment, e.g., radiator shutter control, coolant pumps, fuel transfer pumps, oil coolers, and engine room ventilation system(s). (h) Record the readings for all instruments in the log (see Clause 11.5.3) and verify that they are normal. (i) Drain
18、the exhaust system condensate trap.3. Inspect block heater hoses and wires. 4. Correct all defects found during inspections and tests.5. Record all inspections, tests, and corrective actions in the log (see Clause 11.5.3).6. Inspect all electrical components to ensure proper function.Note: The work
19、described in this Table shall be carried out by a competent person or individuals trained by the system manufacturer.Table 4 Semi-annual inspection, test, and maintenance requirements1. Complete all items specified in Tables 2 and 3.2. Inspect and clean engine crankcase breathers.3. Inspect and clea
20、n all engine linkages.4. Lubricate the engine governor and ventilation system.5. Test protective devices for proper operation.6. Before start-up, perform two full cranking cycles (as specified in Clauses 10.4.1 and 10.4.2). Near the end of each cycle (and while still cranking), measure and record th
21、e lowest indicated battery voltage. If the measured voltage is less than 80% of the batterys rated voltage, replace the battery. Alternatively, perform a battery load test using a suitable load tester. 7. Inspect ventilation system belt(s). 8. Correct all defects found during inspections and tests.9
22、. Record all inspections, tests, and corrective actions in the log (see Clause 11.5.3).Notes: (1) Items 2 to 9 require special skill and shall be carried out by a competent person or individuals trained by the system manufacturer. (2) For Item 5, if it is not possible to create the fault condition,
23、a simulated fault condition should be performed if possible2 Refer to CSA C282-15, Emergency electrical power supply for buildings March 2015 2015 CSA GroupInspection, test, and maintenance of emergency electrical power supply for buildingsTable 5 Annual inspection, test, and maintenance requirement
24、s1. Complete all items specified in Tables 2 to 4.2. Control panel (see Clause B.23):(a) Open all inspection covers and inspect all electrical connections.(b) Test breakers for proper operation.(c) Clean insulators and bushings.(d) Test voltage regulator for proper operation.(e) Operate all moving p
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- CSAC282LOGBOOK2015EMERGENCYELECTRICALPOWERSUPPLYFORBUILDINGSMAINTENANCELOGBOOKPDF

链接地址:http://www.mydoc123.com/p-621385.html