1、Designation: E2947 16aStandard Guide forBuilding Enclosure Commissioning1This standard is issued under the fixed designation E2947; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the year of last revision. A number in parentheses
2、indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 PurposeThis guide provides procedures, methods anddocumentation techniques that may be used in the applicationof the building enclosure commissioning (BECx)
3、process. Thisguide is complementary to Practice E2813 and is aligned withANSI/ASHRAE/IES Standard 202 and ASHRAE Guideline 0.1.2 ExtentThe process outlined in this standard guideapplies to each building delivery phase from pre-designthrough Owner occupancy and operation. The specific appli-cation of
4、 this guide may vary to suit the Owner, the projectdelivery method and the building project as outlined in theOwners Project Requirements (OPR).1.3 Primary FocusThe primary focus of this processincludes, but may not be limited to, new construction ofbuilding enclosures, existing building enclosures
5、undergoingsubstantial renovation or alteration, and continuous commis-sioning of enclosure systems.1.4 Contractual and Regulatory ObligationsThe methodsdescribed in this guide are not intended to supersede orotherwise replace the contractual obligations reserved specifi-cally for the parties respons
6、ible for the design and constructionof a building or structure, nor to alter the roles, responsibilitiesand duties that may otherwise be assigned to those parties byapplicable regulatory or statutory law.1.5 This standard does not purport to address all of thesafety concerns, if any, associated with
7、 its use. It is theresponsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2E631 Terminology of Building ConstructionsE2813 Practice for Buildin
8、g Enclosure Commissioning2.2 ASHRAE Guidelines and Standards:3ANSI/ASHRAE/IES Standard 202 Commissioning Processfor Buildings and SystemsASHRAE Guideline 0 The Commissioning Process3. Terminology3.1 DefinitionsRefer to the most current edition of thefollowing:3.1.1 ASTM E631 Terminology of Building
9、Constructions.3.1.2 ASHRAE Guideline 0, Section 4, Definitions.3.1.3 ANSI/ASHRAE/IES Standard 202, Section 3, Defini-tions.3.2 Definitions of Terms Specific to This Standard:3.2.1 The following definitions, abbreviations, and acro-nyms are specific to the implementation of the commissioningprocess f
10、or building enclosure systems. These definitions areapplicable throughout this guideline. Terms that are not definedhave their ordinarily accepted meanings within the context inwhich they are used.3.2.2 basis of design, BOD, na document developed bythe design team that records the technical concepts
11、,assumptions, calculations, decisions, and product selectionsused to meet the Owners Project Requirements and to satisfyapplicable regulatory requirements, standards and guidelines.3.2.2.1 DiscussionThe BOD document includes both nar-rative descriptions and lists of individual items that supportsthe
12、 design process.3.2.3 bidding and negotiation phase, npreparatory phaseof the construction process delivery that assists in the solicita-tion and selection of prospective bidders, including evaluationof requests for information, substitutions, development ofAddenda, review of bids and qualifications
13、 and the award oftrade contracts.3.2.3.1 DiscussionThis phase is followed by the pre-construction sub-phase.3.2.4 building enclosure, nthe terms “building enclosure”and “enclosure” refer collectively to materials, components,systems, and assemblies intended to provide shelter and1This guide is under
14、 the jurisdiction of ASTM Committee E06 on Performanceof Buildings and is the direct responsibility of Subcommittee E06.55 on Perfor-mance of Building Enclosures.Current edition approved June 1, 2016. Published August 2016. Originallyapproved in 2014. Last previous edition approved in 2016 as E2947-
15、16. DOI:10.1520/E2947-16A.2For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.3Available from American Society of
16、 Heating, Refrigerating, and Air-Conditioning Engineers, Inc. (ASHRAE), 1791 Tullie Circle, NE, Atlanta, GA30329, http:/www.ashrae.org.Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States1environmental separation between interior and exter
17、ior, orbetween two or more environmentally distinct interior spacesin a building or structure.3.2.4.1 DiscussionThe building enclosure may includebut is not limited to walls, fenestration, roofs, ceilings andfloors (and the intentional openings and penetrations throughthem).3.2.5 building enclosure
18、commissioning, BECx,narchitecture or engineering-related technical services orboth, performed on behalf of the Owner that implements aquality-focused process for enhancing the delivery of a projectby focusing on validating during the design phase and verify-ing during the construction phase that the
19、 performance ofbuilding enclosure materials, components, assemblies andsystems are designed and installed to meet the Owners ProjectRequirements.3.2.6 building enclosure commissioning plan, BECx plan,na document that outlines the scope, organization, schedule,allocation of resources, responsibilitie
20、s, testing and documen-tation requirements of the building enclosure commissioningprocess to meet the OPR.3.2.6.1 DiscussionThe BECx plan may be a portion of thewhole building Cx plan.3.2.7 building enclosure commissioning provider, BECxP,na duly authorized person or firm in the jurisdiction of thep
21、roject retained by the Owner to develop, manage, and be inresponsible charge of the BECx process.3.2.7.1 DiscussionThe BECxP should be trained,experienced, and knowledgeable in the building enclosurecommissioning process, and possess and be able to demon-strate proficiency in the core competencies l
22、isted in 4.2.1 ofPractice E2813. The person or firm performing the role ofBECxP should be identified by the Owner. The role of theBECxP may be performed by the Building Enclosure Commis-sioning Specialist (BECxS), the overall building commission-ing authority (CxA), or another qualified member to th
23、e Cxteam.3.2.8 building enclosure commissioning specialist, BECxS,na registered design professional (Professional Engineer orRegistered Architect) and/or duly authorized firm in the juris-diction of the project, who is retained by the Owner with theapplicable experience and technical knowledge of th
24、e perfor-mance of building enclosure systems and who is able todemonstrate and maintain throughout the project third partyindependence in order to avoid conflicts of interest.4Refer to1.4 for additional information.3.2.8.1 DiscussionThe BECxS possesses the experienceand technical skills needed to as
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTME29472016ASTANDARDGUIDEFORBUILDINGENCLOSURECOMMISSIONING 建筑 围护结构 试运行 标准 指南 PDF

链接地址:http://www.mydoc123.com/p-532153.html