ASME STP-NU-015-2008 A Guide to American Crane Standards for Electric Overhead Traveling Cranes Hoists and Related Equipment for Nuclear Facilities《核能设施用电气高架移动式起重机 小型起重机和相关设备的美国起重机.pdf
《ASME STP-NU-015-2008 A Guide to American Crane Standards for Electric Overhead Traveling Cranes Hoists and Related Equipment for Nuclear Facilities《核能设施用电气高架移动式起重机 小型起重机和相关设备的美国起重机.pdf》由会员分享,可在线阅读,更多相关《ASME STP-NU-015-2008 A Guide to American Crane Standards for Electric Overhead Traveling Cranes Hoists and Related Equipment for Nuclear Facilities《核能设施用电气高架移动式起重机 小型起重机和相关设备的美国起重机.pdf(25页珍藏版)》请在麦多课文档分享上搜索。
1、STP-NU-015A GUIDE TO AMERICANCRANE STANDARDSFor Electric Overhead Traveling Cranes,Hoists, and Related Equipment for NuclearFacilitiesSTP-NU-015 A Guide to American Crane Standards for Electric Overhead Traveling Cranes, Hoists and Related Equipment for Nuclear Facilities Prepared by: ASME Committee
2、 on Cranes for Nuclear Facilities Date of Issuance: April 8, 2008 This report was prepared as an account of work sponsored by the ASME Board on Nuclear Codes that is, “should” is used rather than “shall” throughout the document. However, when nuclear power plant owners invoke NUREG-0554 in crane spe
3、cifications, they typically intend that the crane designer consider all of its guidelines as mandatory. Appendix 3.1 to NUREG-0554, “Checklist of Most Important NUREG-0554 Requirements,” was written by the NRC separately from the NUREG (and apparently not formally issued or added to the base documen
4、t). This Appendix does not cover all the guidelines of the NUREG. It is assumed that NRC licensees (U.S. nuclear power generation plants) and their crane suppliers are expected to demonstrate compliance with all guidelines, and that any deviations are potentially subject to acceptance by the license
5、e and the NRC. The primary intent of NUREG-0554 is to preclude dropping the critical load. A SFP crane design conforming to NUREG-0554 could be assumed acceptable to the NRC and therefore to satisfy regulatory concerns, upon review and acceptance of its design features. Such a design may be enhanced
6、 to provide additional features to protect against the potential for a dropped load, depending on the level of protection desired by the owner. Although NUREG-0554 specifies provisions for emergency lowering and manual positioning of the rated load, it does not consider issues such as operational re
7、coverability from component or system failures, or electrical redundancy/supervisory control. These are frequently important to owners of facilities handling highly radioactive or other hazardous materials, or fragile, explosive, flammable or valuable loads where the consequences of loss of operabil
8、ity or unwanted motion may be unacceptable. In the absence of industry standards, the owner must write his own specifications covering such criteria. 4.2 NUREG-0612, Control of Heavy Loads at Nuclear Power Plants 14 This NRC document, issued in 1980, provides guidelines to operators of nuclear power
9、 plants for handling heavy loads, particularly those moved by overhead cranes. The guidance is based on a philosophy of “defense in depth” against serious load-handling accidents by implementation of training, inspections, safe load paths, administrative controls and analysis of the consequences of
10、dropped loads. The objectives are to preclude damage to nuclear fuel, impairment of equipment necessary for safe shutdown of the reactor or release of radioactive material to the environment. If a load must unavoidably be handled in an area where its falling could result in unacceptable consequences
11、, NUREG-0612 guides the owner to use a SFP crane designed in accordance with NUREG-0554, in addition to the implementation of other appropriate safeguards. Appendix C to NUREG-0612 provides guidelines for modification of existing cranes, including commentary on implementation of NUREG-0554 for opera
12、ting plants with cranes that may need to be upgraded with single-failure-proof features. Note that NUREG-0612 does not offer complete guidelines for SFP crane design. It also is not intended to impose additional guidance to that given in NUREG-0554, and therefore need not be invoked if NUREG-0554 is
13、 already specified. However, its Appendix C suggests optional methods for compliance with certain of the NUREG-0554 guidelines, particularly for existing cranes. A Guide to American Crane Standards STP-NU-015 9 4.3 NUREG-0800, Standard Review Plan (Formerly NUREG-75/087) 15 This NRC document was pub
14、lished to provide guidance to its own staff responsible for review of applications to construct and operate nuclear power plants. Although compliance with standard review plans is not mandatory, familiarity with them can be of considerable benefit to plant owners in their efforts to secure regulator
15、y acceptance. Some sections of NUREG-0800 are applicable to crane design and may be invoked in owners specifications. These would typically be Sections 3.7.2, Seismic System Analysis, and 3.7.3, Seismic Subsystem Analysis. 4.4 Generic Letter 83-42 16 This NRC letter to all nuclear power plant operat
16、ors, dated December 19, 1983, informs them that certain electrical system problems can cause loss of control of the load in certain instances. The potential problem areas include phase loss and phase reversal in AC powered motor and control systems. Appendix 3.1 to NUREG-0554 refers to Generic Lette
17、r 83-42. For new or upgraded SFP cranes, 83-42 can be treated as an addendum to NUREG-0554. However, it is not limited to cranes designated as SFP. All cranes in U.S. nuclear power plants should potentially be evaluated against the criteria in this letter. 4.5 Bulletin 96-02: Movement of Heavy Loads
18、 over Spent Fuel, over Fuel in the Reactor Core or over Safety-Related Equipment 17 This bulletin was issued by the NRC to nuclear plant operators on April 11, 1996. It alerts them to the importance of complying with existing regulatory guidelines related to control of heavy loads, requests that the
19、y review their plans and capabilities for handling heavy loads, and requires that they report to the NRC their compliance with the requirements of the bulletin. It clarifies the regulatory intent regarding NUREG-0612 and related NRC documents. Bulletin 96-02 expresses concern on the part of the NRC
20、that licensees may believe they comply with guidelines for control of heavy loads based on prior reviews of the subject, when in fact the NRC did not necessarily take the same view and may not consider all of the licensees conclusions to be valid. The required reports are to address handling heavy l
21、oads with the reactor at power, with consideration to the possibility of damage to safety-related equipment, fuel in the reactor core or spent fuel. The reports also must consider the potential complications resulting from the breach of a dry storage cask. Bulletin 96-02 does not address the design
22、of cranes or other load-handling equipment. Its implementation may lead to the conclusion that a crane once considered safe enough should be upgraded with SFP features. 4.6 NRC Regulatory Issue Summary 2005-25: Clarification of NRC Guidelines for Control of Heavy Loads 18 This Regulatory Issue Summa
23、ry (RIS) was issued by the NRC on October 31, 2005, followed by Supplement 1 dated May 29, 2007. It summarizes, clarifies and emphasizes regulatory guidance provided in previous NRC documents, primarily NUREG-0612 but also including NUREG-0554, NUREG-1774 and GL 96-02. It addresses a range of issues
24、 including safe load paths, procedures for load handling, crane operators, crane design, crane inspection, testing and maintenance, special lifting devices, slings, consequence evaluations of load drops, upgrade of existing cranes to SFP and seismic qualification of crane structures. The RIS states
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASMESTPNU0152008AGUIDETOAMERICANCRANESTANDARDSFORELECTRICOVERHEADTRAVELINGCRANESHOISTSANDRELATEDEQUIPMENTFORNUCLEARFACILITIES

链接地址:http://www.mydoc123.com/p-456906.html